Coffee Pot Bridge Sections B-M

View the file

Other files for this federal contract opportunity

Other files attached to Coffee Pot #2 Bridge Construction, newest first.
File Type Posted
Coffee_Pot_Pre-Bid_QA.pdf PDF
Atth_5_Performance_Bond_SF25-16a.pdf PDF
Atth_3_DOL_Wage_CO13_and_CO23.pdf PDF
Atth_1_Section_C_Specifications.pdf PDF
Atth_4_Payment_Bond_SF25A-16a.pdf PDF
Atth_7_Experience_Questionnaire.doc DOC document
Atth_2_Coffee_Pot_PSE_plans-stamped.pdf PDF
Atth_6_Bid_Bond_SF24.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 1282D718R0006 Coffee Pot Bridge Replacement

White River National Forest

SECTION B—SCHEDULE OF ITEMS - PAGE 1 OF 2

Pay Item Description Pay Estimated Unit No. Unit Quantity Price Amount

15101 Mobilization LS 1 $ $

15205 Bridge survey and staking LS 1 $ $

15212 Slope, reference, and clearing and grubbing stakes; method 1, tolerance A

LS 1 $ $

15255 Grade finishing stakes, aggregate surface, tolerance A LS 1 $ $

15702 Silt fence FT 173 $ $

15752 Sediment basin EA 1 $ $

20102 Clearing and grubbing LS 1 $ $

20305 Removal of structures and obstructions LS 1 $ $

20455 Embankment construction CY 36 $ $

20801 Structure excavation CY 373 $ $

20803 Structural backfill CY 277 $ $

25102 Placed riprap, class 5 TON 107 $ $

25501 Mechanically stabilized earth wall SY 107.7 $ $

30109 Aggregate surface course, grading F, compaction method B TON 44 $ $

55501 Structural steel, channel stiffener, furnished, fabricated, and erected

LB 725 $ $

55703 Treated structural timber and lumber MBFM 2.8 $ $

55752 Treated structural timber, dowel-laminated MBFM 11.2 $ $

62502 Seeding, dry method (government furnished seed mix) SY 400 $ $

62901 Erosion control mat, type 3.B SY 400 $ $

63306 Object markers, furnish and install EA 4 $ $

63310 Removing object markers EA 7 $ $

63501 Temporary traffic control LS 1 $ $

Total Project Items $

SECTION B - BID SCHEDULE

Coffee Pot #2 Bridge #600-27.5 Replacement

SECTION B—SCHEDULE OF ITEMS - PAGE 2 OF 2

Company Name: ____________________________________

DUNS #: ____________________________________

POC: ____________________________________

Email: ____________________________________

Phone: ____________________________________

B-2 - NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed- Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under Mobilization.

Payment will be made on actual work performed unless otherwise noted.

To be eligible for award, contractors MUST be registered in the System for Award Management (SAM), www.sam.gov

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

See attachment 1 – Section C AllSpecs

AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)

Contractor shall furnish the necessary personnel, materials, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Referenced in Section J.

AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract. This includes Standard Specifications and Supplemental specifications applicable to this project.

SECTION D--PACKAGING AND MARKING

(There are no clauses for this Section)

SECTION E--INSPECTION AND ACCEPTANCE

52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(s): www.acquisition.gov/far/ http://www.sam.gov/ http://www.acquisition.gov/far/

White River National Forest

52.246-12 Inspection of Construction (AUG 1996)

52.246.13 Inspection-Dismantling, Demolition, or Removal of Improvements (Aug 1996)

AGAR 452.246-70 Inspection and Acceptance. (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at: the project site.

SECTION F--DELIVERIES OR PERFORMANCE

52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 calendar days. The time state for completion shall include final cleanup of the premises.

452.236-75 Maximum Workweek – Construction Schedule (NOV 1996)

Within ten (10) calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.

The maximum workweek that will be approved is Forty (40) hours.

Submittals, Schedules, and Reports Pursuant to contract requirements the following submittals are required prior to issuance of the Notice to Proceed unless the contracting officer determines otherwise:

Item Description Copies Required 1 Proposed Schedule of Work 1 2 List of proposed sub-contractors and their intended work 1 3 Designation of Contractor’s Personnel describing responsibilities 1

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 INVOICE

G.1.1 The Department of Agriculture (USDA) mandated the transition of all Integrated Acquisition System (IAS) payments to the US Treasury Invoice Processing Platform (IPP). This allows electronic routing and approval of IAS related invoices. The Forest Service's (FS) completed transition to the new process is scheduled for February 24, 2014.

It will be necessary for contractors to login to their IPP accounts every 90 days to keep their IPP accounts active. The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in the previous communications from USDA and Treasury. All invoices are to be submitted via the electronic Invoice Processing Platform. This is a mandatory requirement initiated by the U.S.

Department of Treasury and you can find more information located on the IPP website. Please make sure that your company has registered with IPP to establish your account.

G.1.2. INVOICE FORMAT

The invoice format/template the contractor shall use in submitting invoices is to reflect the award document with the individual line items through the IPP platform. The contractor shall attached their companies’ version of the paper invoice to the IPP invoice.

G.1.3 INVOICE SHALL BE SUBMITTED TO

Contractor shall submit invoices to the IPP platform @ www.ipp.gov

IN ACCORDANCE TO THE TERMS AND CONDITIONS OF THIS CONTRACT.

G.2. PAYMENT:

(1) Contractor and government personnel will decide on the method of payment, whether it be partial payments, based on some measure, or as one deliverable at the end of the project.

(2) Payment for Materials Off Site In accordance with Clause 52.232-5, progress payments may include payment for materials stored off site. Contractor shall provide a copy of the paid invoice; provide evidence that the material will be included in the finished project; and identify the location where the materials are stored, so that the government may make visual inspection if the Contracting Officer deems it necessary.

The Contractor shall be liable for loss, damage, or destruction of the materials until such time as the materials are physically in the possession and control of the government. The Contractor will not be held liable to the extent that the Contracting Officer determines that the loss, damage, or destruction occurred through the fault or negligence of the government or its agents.

G.2.1 PAYMENT WILL BE MADE BY:

Payments are made by the US Department of Treasury through information from System for Award Management (SAM).

G.3 Forest Service Representatives:

Lonnie D Root will serve as the Contracting Officer on this contract. He will have full warrant authority over all contract issues and can be reached at:

Lonnie D. Root Contracting Officer, R2, White River NF 900 Grand Ave Glenwood Springs, CO 81601 Email: lroot@fs.fed.us http://www.ipp.gov/ mailto:lroot@fs.fed.us

Erica Borum will serve as the Contracting Officer Representative on this contract. Her delegated authority and responsibilities will be defined on a delegation letter issued after contract award.

Erica can be reached at:

Erica Borum Civil Engineer, R2, White River NF 900 Grand Ave Glenwood Springs, CO 81601 Email: eborum@fs.fed.us Phone: 970-945-3277

452.215-73 Post award Conference. (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled within five (5) days after the date of contract award. The conference will be held at the following location or as otherwise agreed upon by the government and the contractor.

White River Supervisor’s Office 900 Grand Avenue Glenwood Springs, CO 81601

G.4 CONTRACT ADMINISTRATION DATA

1. Contract Award. A written award or acceptance of offer mailed or otherwise furnished to the Contractor shall result in a binding contract without further action by either party.

2. Notice to Proceed. The Contractor shall commence work upon receipt of a properly executed

Notice to Proceed.

3. Changes. The Contracting Officer is the only person authorized to approve changes in any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract the said authority remains solely with the Contracting Officer. In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.

4. Unauthorized Instructions from Government or Other Personnel. The Contractor shall not accept instructions issued by any person employed by the U.S. Government or otherwise other than the Contracting Officer, or the authorized representative of the Contracting Officer acting within the limits of his/her authority.

5. Designation of Contracting Officer’s Representative (COR). Designation will be made upon contract award and a copy of the designation letters will be furnished to the Contractor. Limits of authority are described in each designation letter.

6. Designation of Authorized Representative of the Contractor. The Contractor shall assign a member or employee who will act as Project Manager during the course of this contract or during the course of this project. The official shall be responsible for affording liaison between the contract forces and the contracting offices. This designation shall be in writing and a copy furnished to the Contracting Officer.

mailto:eborum@fs.fed.us

SECTION H--SPECIAL CONTRACT REQUIREMENTS

452.237-74 Key Personnel. (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel: Project Manager

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

452.236-77 (NOV 1996) Emergency Response

(a) Contractor’s Responsibility for Fire Fighting. (1) The Contractor, under the provisions of FAR Clause 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements, shall immediately extinguish all fires on the work site other than those fires in use as part of the work. (2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor’s agents or employees.

(b) Contractor’s Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires signed on or in the vicinity of the work site.

(c) Contractor’s Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Forest Service to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to firefighting). An equitable adjustment for the temporary use of employees and equipment will be made under the Changes Clause, FAR 52.243-4.

452.222-704 Personal Protective Equipment (Feb 2007)

1. The contractor will train in the safe operation and use of equipment to all workers using such equipment.

2. Personal protective equipment, including personal protective equipment for eyes, face, head, and extremities shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered in a manner capable of causing injury or impairment in the function of any part of the body.

3. Defective or damaged personal protective equipment shall not be used.

4. The contractor shall provide, at no cost to the employee, to each employee who operates a chain saw, chain saw chaps and assure the chaps are worn during saw operations. These chaps must be approved by Underwriters Laboratory or meet Forest Service specification 6170-47. The chaps shall cover the full length of the thigh to the top of the boot on each leg.

5. The contractor shall assure that each employee wears foot protection that provides adequate traction and ankle support. Employees operating chain saws shall wear foot protection that is constructed with cut-resistant material which will protect the employee against contact with a running chain saw.

6. The contractor shall provide, at no cost to the employee, and assure that each employee who works in an area where there is potential for head injury from falling objects or flying objects wears a hard hat that meets the minimum requirements of American National Standards Institute (ANSI) standard Z89.1-1997.

7. The contractor shall provide, at no cost to the employee, eye protection where there is potential for eye injury due to flying objects. This eye protection must meet the minimum requirements of ANSI standard Z87.1-2003.

8. The contractor shall provide, at no cost to the employee, hearing protection where there is a potential for hearing loss due to high intensity noise e.g., chain saw operation.

452.222-705 Camping Provisions for Labor Intensive Contracts (Feb 2007)

The following provisions apply to all camping on National Forest lands during performance of this contract:

1. These provisions are in addition to those contained in, or provided for, in the clause titled “Use of

Premises”, in this contract.

2. Every structure used as shelter shall provide protection from the elements. Where heat adequate for weather conditions is not provided, other arrangements should be made to protect workers from the cold.

Firewood may be cut only after obtaining a District Firewood Permit.

3. The campsite will not encroach beyond the boundaries designated by the Forest Service. The campsite shall be located so as to minimize impacts on streams, lakes, and other bodies of water. No camping shall be permitted within developed recreation sites or along primary recreation roads.

4. The campsite shall have a clean appearance at all times.

5. Upon abandonment of any campsite, or termination, revocation, or cancellation of camping privileges, the contractor shall remove, within 10 calendar days, all structures and improvements except those owned by the United States, and shall restore the site, unless otherwise agreed upon in writing or in the camping permit. If the contractor fails to remove all structures or improvements within the 10 calendar days, they shall become the property of the United States, but that will not relieve the contractor of liability for the cost of their removal and restoration of the site.

6. Unless otherwise designated by the Contracting Officer, the use of this area is not exclusive, and may be granted to other permittees, contractors, or recreating public. Disorderly conduct is not permitted.

7. Damaging or removing any natural feature or other property of the Forest Service is prohibited.

8. Servicing of equipment in the campsite is not permitted, unless the campsite is within the project area.

9. Sanitary facilities shall be provided for storing food. Ice chests or coolers, with ice supply made from potable water and replenished as necessary, shall be provided and sufficient for the storage of perishable food items.

10. An adequate and convenient potable water supply shall be provided in each camp for drinking and cooking purposes.

11. Toilet facilities adequate for the capacity of the camp shall be provided and supplied with adequate toilet paper. Such facilities shall be serviced and maintained in a sanitary condition.

12. Garbage shall be collected, stored, and disposed of in such a manner as to prevent scattering by the wind, minimize attraction of flies, and discourage access by rodents.

13. Basic first aid supplies shall be maintained, available and under the charge of a person trained to administer first aid. The supplies shall include:

a. Gauze pads (at least 4x4 inches)

b. Two large gauze pads (at least 8x10 inches)

c. Box adhesive bandages (band-aids)

d. One package of gauze roller bandage at least 2 inches wide

e. Two triangular bandages

f. Scissors

g. At least one blanket

h. Tweezers

i. Adhesive tape

j. Latex gloves

k. Resuscitation device such as resuscitation bag, airway, or pocket mask

14. Any washing of laundry shall be done in such a way as to provide for washing and rinsing without polluting lakes, streams, or other flowing water.

15. Waste water must be disposed of away from living and eating areas and in a fashion that minimizes pollution to lakes, streams, and other flowing water.

16. The contractor shall take all reasonable precautions to prevent and suppress forest fires. No material shall be disposed of by burning in open fires during the closed season established by law or regulation without the written permission from the Forest Service.

17. The contractor shall comply with the following fire regulations during fire season:

a. A shovel, axe or pulaski, 10 quart pail which is full of water for immediate use and a fire extinguisher with an Underwriters Laboratory (UL) rating of at least 1:A 10:BC is required during the fire season.

b. All fire rings or outside fireplaces will be approved by the Forest Service representative. The area will be cleared down to mineral soil for a distance of 1 foot outside of the ring or fireplace and it will not have any overhanging material. Fire rings will be dismantled and material disposed prior to leaving the site.

c. All generators and other internal combustion engines will be equipped with USFS approved spark arrestors and/or factory designed muffler and exhaust system in good working order. They will be located in a cleared area with the same requirements as in (b).

d. All fuel will be stored in UL approved flammable storage containers and be located at least 50 feet from any open flame or other source of ignition.

18. Any violation of these conditions constitutes a breach of contract, and may result in revocation of camping approval.

19. The Forest Service reserves the right to terminate a camping permit at any time.

452.222-701 Employment of Eligible Workers (DEC 1999)

Section 274A of the Immigration and Nationality Act (8 USC 1324a) makes it unlawful for an employer to hire undocumented workers. The Immigration and Naturalization Service (INS) has established the Form I- 9, Employment Eligibility Verification Form, as the document to be used for employment eligibility verification (see 8 CFR 274a).

The Contractor is required to (1) have all employees complete and sign the I-9 Form to certify that they are eligible for employment; (2) examine documents presented by the employee and ensure the documents appear to be genuine and related to the individual; (3) record information about the documents on the form, and complete the certification portion of the form; (4) retain the form for three years, or one year past the end of employment of the individual, whichever is longer.

It is illegal to discriminate against any individual (other than a citizen of another country who is not authorized to work in the United States) in hiring, discharging, or recruiting because of that individual's national origin or citizenship status.

Compliance with Section 274A of the Immigration and Nationality Act (8 U.S.C. 1324a) is a material condition of the contract. If the Contractor employs unauthorized workers during contract performance in violation of Section 274A, the Government may terminate the contract, in addition to other remedies or penalties prescribed by law.

For further information on the requirements of the Act, Contractors should contact the Employer and Labor Relations Officer of their local INS office.

H.1 Field Sanitation

In accordance with US Department of Labor Fact Sheet No. ESA 97-28 “Field Sanitation Standards” (Ref.

29CFR 1928.110), employers must provide:

• Potable drinking water, suitably cool and in sufficient amounts, dispensed in single-use cups or by fountains, located so as to be readily accessible to employees.

• Facilities maintained in accordance with public health sanitation practices include upkeep of water quality through daily change or more often if necessary.

• Notification to each employee of the location of the water and allowance of reasonable opportunities during the workday to use them. The employer also must inform the employee of the relevant health hazards in the field and the practices necessary to minimize them.

Employees cannot be made to bear the costs incurred by the employer for providing required facilities.

H.2 Prework Conference

Prior to commencement of work the Contractor shall attend a meeting to discuss the contract terms, work performance requirements and safety. Also at this meeting such items as work progress schedule, quality control, camping/worksite plan, and fire preventions plans shall be finalized in writing.

H.3 Safety Plan

When required by FAR 52.236-13 Accident Prevention Alt I, the Contractor shall prepare a Safety plan which addresses the specific hazards of the work site, and shall include working in areas of dead trees and falling debris. The Contractor shall identify the specific conditions that s/he considers is a hazard. The Safety Plan shall also address the personal protective equipment and mitigating measures the Contractor will do to increase safety on the worksite.

H.4 AGAR Advisory Number (No.) 88c – Contractor Performance Information and Contractor Performance system (CPS) Evaluations

The awarded Contractor shall be required to register in the civilian Contractor Performance System maintained by the National Institutes of health at http://cps.od.nih.gov/Contractor_Info7.html

H.5 Noxious Weeds Prevention and Requirements

All contractors and subcontractors performing work on National Forest System lands are required to use equipment and vehicles free of noxious weed seeds and/or propagating parts capable of producing a new noxious weed plant. This applies to ALL vehicles whether owned, leased or borrowed. This shall be accomplished by washing with a pressurized hose all equipment and vehicles used for construction, maintenance and support work prior to entering the National Forest according to Special Project Specification 171 Weed and Disease prevention

H.6 Signs and Traffic Control Requirements

In the performance of travel way maintenance, signs shall be located no more than one mile before and after the area of operation. Signs shall be posted only during the construction period. Traffic warning signs shall be provided by the contractor. Cost is incidental and is included in the Pay Items corresponding to the road maintenance work. Signs must conform to the Manual of Uniform Traffic Control Devices (MUTCD). No hand made signs will be allowed. No work shall be allowed to commence until construction signs have been approved by the CO.

http://cps.od.nih.gov/Contractor_Info7.html

H. 7. Fire Control

H.7.1. Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.

H.7.2. Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or his employees, the Contractor when requested by the Contracting Officer shall place his employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.

H.7.3. Any employees and equipment furnished will be relieved from fire fighting as soon as the

Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.

H.7.4. An equitable adjustment in contract time may be made for this period.

H.7.5. Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract.

H.7.5.1. Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under H.2.5.2.

and H.2.5.4. below shall count toward fulfillment of the above requirement.

Where additional tools, beyond those required below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.

H.7.5.2. Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

a. One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.

b. One - shovel, round point #0 lady or equal.

c. One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.

d. One - water container (at least 1-gallon capacity), not required with stationary equipment.

H.7.5.3. Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service.

Exceptions where the Forest Service may approve mufflers or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chainsaws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester.

Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.

H.7.5.4. Power saws. For each power saw used in connection with this contract, the following will be provided:

a. One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.

b. One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity.

The extinguisher must be immediately accessible to the saw operator at all times.

H.7.5.4.1. Any fueling or refueling of a powersaw or auger shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw or auger shall be moved at least 10 feet from place of fueling before starting.

H.7.5.5. Blasting. Fuse or prima cord shall not be used unless authorized in writing by the

COR with special precautions stated.

H.7.5.6. Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.

H.7.5.7. Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.

H.7.5.8. Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.

H.7.5.9. Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.

All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.

H.7.5.10. Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.

H.7.5.11. Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.

H.7.5.11.1. When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:

a. All high fire risk operations could be terminated at 1300 local time.

b. All burning could be stopped, including debris burning fires.

c. Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.

H.7.5.12. Pump and Trailer. Not required.

H.7.5.13. Burning. Before starting any open burning, the Contractor shall comply with the following:

a. Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.

b. Obtain a burning permit from the District Ranger.

c. Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.

d. Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.

e. Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.

f. Under certain atmospheric conditions, smoke accumulations may become excessive and, in these cases, the Regional Forester may, at his discretion, prohibit all open burning for definite periods within specific areas of the National Forest.

H-8. Suspensions for Other Than Government’s Convenience

The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of: (1) Weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project, or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to

White River National Forest access roads, rutting of project roads which causes otherwise suitable soils to become muddy or unsuitable;

or (2) Failure of the Contractor to comply with Specifications such as but not limited to placement of frozen material in fills, placing of asphalts at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements, or when conditions exist which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by his/her operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR: 52.242-14, Suspension of Work, and shall not qualify for equitable adjustment.

H-9. Performance and Payment Bonds

a. PERFORMANCE BONDS. For contracts over $150,000, a Performance and Payment Bond are required. The bond(s) must be submitted and approved, to the Government, within 10 calendar days after the Contractor’s receipt of the executed Task Order. Work shall not begin until a Notice to Proceed, fully executed by the Contractor Officer, has been received by the Contractor. The amount of the Performance Bond must equal 100% of the contract amount. (Standard Form 25 is attached, see Section J) (See Section I, 52.228-15)

b. PAYMENT BOND. For contract over $30,000, a Payment Bond is required. The bond must be submitted and approved within 10 calendar days after receipt of the contract. Work cannot begin until a Notice to Proceed, fully executed by the Contractor, has been given. The amount of the Payment Bond must equal 100% of the contract amount. (Standard Form 25A is attached, see Section J) (See Section I, 52.228-15)

Order Value Requirement

Orders <$30,000> Performance and Payment Bond are not required.

Orders $30,000 to $150,000 Only Payment Bond required for 100% of the order amount.

Orders $150,000+ Performance and Payment Bonds required for 100% of the order amount.

Value of bonds shall be equal to the value of the Task Order.

H-10. Performance Bond & Payment Bonds

Performance Bonds (Standard Form 25) and Payment Bonds (Standard Form 25A) in the following amounts are required. The deadline for submitting acceptable bonds and the sum of each bond is as follows:

H-11. Bid Bonds

In accordance with FAR 28.1--Bonds and Other Financial Protections Bidder(s) shall submit with their bid a Bid Guarantee with good and sufficient surety or sureties acceptable to the Government, or other form of security in the amount of 20 PERCENT OF THE BID PRICE OR $50,000.00 WHICHEVER IS LESS. The amount of the bid guarantee submitted, if less than that required by the solicitation for the maximum quantity offered, is determined by the Government to be sufficient for a quantity for which the Offeror/Bidder is otherwise eligible for award. Any award to the Offeror/Bidder shall not exceed the quantity covered by the bid guarantee, reference FAR 28.101-4(c)(3) Noncompliance with Bid Guarantee Requirements. (Standard Form 24 is attached hereto.

See Section J) (See Section I, 52.228-1)

PART II--CONTRACT CLAUSES

SECTION I—CONTRACT CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.202-1 Definitions (Nov 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (May 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (May 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (Oct 2010) 52.204-4 Printed or Copied Double- Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-7 Central Contractor Registration (Oct 2016) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Oct 2015) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (Oct 2010) 52.219-6 Notice of Total Small Business Set-Aside (Nov 2011) 52.219-8 Utilization of Small Business Concerns (Nov 2016) 52.219-9 Small Business Subcontracting Plan (Jan 2017) 52.219-14 Limitations on Subcontracting (Jan 2017) 52.219-16 Liquidated Damages – Subcontracting Plan (Jan 1999) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act-Overtime Compensation (May 2018) 52.222-6 Davis-Bacon Act (May 2014) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (May 2014) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination - Debarment (May 2014) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (May 2015) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Sep 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-35 Equal Opportunity for Veterans (Oct 2015) 52.222-36 Affirmative Action for Workers with Disabilities (Jul 2014) 52.222-37 Employment Reports on Veterans (Feb 2016) 52.222-50 Combating Trafficking in Persons (Mar 2015) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2011)

White River National Forest

52.223-6 Drug-Free Workplace (MAY 2001) 52.223-11 Encouraging Contractor Policies to Ban Text Messaging While Driving (Aug 2011) 52.225-13 Restrictions on Certain Foreign Purchases (Jun 2008) 52.227-1 Authorization and Consent. (Dec 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement. (Dec 2007) 52.227-4 Patent Indemnity—Construction Contracts. (Dec 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance - Work on a Government Installation (Jan 1997) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.229-3 Federal, State, and Local Taxes (Feb 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-17 Interest (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (Jul 2013) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Dec 2013) 52.233-1 Disputes (May 2014) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claims (Oct 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-15 Schedules for Construction Contracts (Apr 1984) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (Jun 2007) 52.245-1 Government Property (Jan 2017) 52.246-21 Warranty of Construction (MAR 1994) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (Apr 2012) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums - Fixed-Price Construction Contracts. (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988)

White River National Forest

52.222-5 – Construction Wage Rate Requirements—Secondary Site of the Work. (May 2014)

(a)

(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)

(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

(End of Provision)

52.225-9 Buy American–Construction Materials (May 2014)

(a) Definitions. As used in this clause--

“Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

http://farsite.hill.af.mil/reghtml/Regs/far2afmcfars/fardfars/Far/52_220.htm#P63_8969

White River National Forest

“Cost of components” means--

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements the 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: ______ [Contracting Officer to list applicable excepted materials or indicate “none”]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

White River National Forest

(c) Request for determination of inapplicability of the Buy American statute.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government…