This Statement of Work details a trailhead improvement project for the Eldorado National Forest in Amador and Alpine Counties, California. The project involves three trailheads along Highway 88: Shaelor Lake, Thunder Mountain, and Lake Margaret. Specific work includes demolition activities such as clearing, grubbing, tree removal, metal post removal, and existing kiosk structure removal, followed by construction of a new parking lot at Thunder Mountain Trailhead, installation of three single-unit vault toilets with paved turnouts, placement of site furnishings (fee tubes, picnic tables, trash receptacles, barrier rocks), and installation of three information kiosks with aggregate pads.

The project is scheduled to start on July 7, 2025, with a base bid contract time of 120 days. The work will be conducted within the Amador Ranger District, approximately 50-56 miles northeast of Jackson, California. The contractor will be responsible for site-specific requirements including public access closure, erosion control planning, equipment washing to prevent noxious weed spread, dust abatement, and working within designated site limitations. No water or toilet facilities will be available on-site during construction, and the contractor must adhere to specific environmental and construction guidelines outlined in the document.

View the file

Other files for this federal contract opportunity

Other files attached to Trailhead Upgrades Shealor, Thunder, Margaret, newest first.
File Type Posted
Schedule of Items.xlsx XLSX spreadsheet
Attachment 3 - Wage Determination.pdf PDF
Attachment 2 - Fire Plan.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1

Section C - Description/Specifications/Statement of Work

GENERAL SPECIFICATIONS

HWY 88 TRAILHEAD IMPROVEMENTS GAOA PROJECT

(FINAL – 03/28/2025)

1.1 SCOPE OF CONTRACT

A. This project consists of installing three single unit vault toilets with turnouts and information kiosks at three trailheads, construction of a new parking lot at one trailhead (Thunder Mountain), and installation of site furnishings.

B. Demolition work includes the following:

1. Clearing, grubbing, and tree removal.

2. Metal post removal.

3. Removal and disposal of existing kiosk structures (information boards to be saved, stored safely, and reinstalled on new kiosk structures).

C. Construction work includes the following:

1. Construction of parking lot at Thunder Mountain Trailhead.

2. Installation of three (3) single unit vault toilets (one at each trailhead: Shaelor Lake, Thunder Mountain, and Lake Margaret), along with paved turnouts.

3. Installation of furnishings including a new fee tubes and picnic tables, new trash receptacles, and placement of barrier rock.

4. Installation of three information kiosks with aggregate pads (one at each trailhead).

5. Construction of minor native surface connector trails.

1.2 PROJECT LOCATION

The project is located in the Amador Ranger District of the Eldorado National Forest, Amador and Alpine Counties, California, in Section T10N R17E. The trailheads are located along Highway 88, approximately 50-56 miles Northeast of Jackson, CA.

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. Construction site will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access. The Contractor shall construct a temporary fence with appropriate signing around site during construction to prevent public access.

2. Contractor will provide all materials and labor necessary to protect streams and lakes, wet or dry, during construction activities. The Contractor will be required to submit an erosion control plan and receive approval from the COR, in writing, prior to the beginning of construction.

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2

3. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

4. Dust Abatement: The contractor shall take precautions to prevent unnecessary wind-blown dust. It is especially important to prevent dust from blowing into areas that are in use by the public. Cover or water stockpiles. To the extent possible, construct road subgrades during off-peak recreation periods. Keep all exposed subgrades watered or use other approved method to prevent dust from becoming airborne.

5. Water is not available at the site for construction purposes.

6. Toilet facilities are not available at the site.

1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.

1.5 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site.

1.6 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.7 START DATE

A. July 7, 2025

1.8 CONTRACT TIME

A. Base Bid: 120 days

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3

1.9 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.

Section 010250 – Construction Staking Section 011250 – Measure and Payment with Asphalt Section 011900 – Mobilization Section 013300 – Submittal Procedures Section 014100 – Quality Control Section 020000 – Environmental Concerns Section 020900 – Construction Area Traffic Control Devices Section 023701 – Sediment and Erosion Control Devices Section 024100 – Waste Material Disposal Section 026210 – Paths and Trails Section 033000 – Cast-in-Place Concrete Section 033020 – Concrete from Packaged Dry Mix for Minor Structures Section 061000 – Carpentry and Lumber Section 101110 – Information Kiosk Section 101400 – Signs Section 129300 – Site Furnishings Section 133402 – Precast Concrete Vault Restroom Building Section 311000 – Clearing and Grubbing Section 312000 – Earthwork Section 312010 – Select Borrow Section 312100 – Project Site Preparation and Grading Section 312225 – Excavation and Embankment

Section 313700 – Riprap & Minor Rockery Structures Section 321200 – Warm Mix Asphalt Paving Section 321204 – Crushed Aggregate Base or Surface Course Section 322205 – Barrier Rocks Section 322205 – Precast Concrete Curb Stop Section 322640 – Pavement Marking FP-14 Section 403 – Asphalt Concrete

END OF SECTION C

March 2025

CONSTRUCTION STAKING 010250-1

USDA FOREST SERVICE, ELDORADO NATIONAL FOREST

HWY 88 TRAILHEAD IMPROVEMENTS GAOA PROJECT

SECTION 010250 - CONSTRUCTION STAKING

PART 1 - GENERAL

1.1 SUMMARY

A. This work shall consist of the construction staking of parking areas, paths, roads, and toilet in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.

1.2 QUALITY CONTROL

A. Construction staking shall be accomplished under the direction of a Civil Engineer, Engineering Technician, or Land Surveyor closely associated and familiar with construction staking; periodic visits to the project site are required.

1.3 MEASUREMENT AND PAYMENT

A. Measurement shall be lump sum for surveying and staking the project through all phases of construction.

PART 2 - PRODUCTS

2.1 GOVERNMENT-FURNISHED SURVEY CONTROL SHEETS

A. The Government will provide the contractor with a set of survey control sheets showing horizontal and vertical control for site to be staked. The Government will provide the Contractor with layout information that will include the Northing, Easting, and Elevations for centerline of roads, spurs and parking areas, edge of parking areas, and corners of buildings and other structures.

2.2 STAKES

A. Identification stakes and hubs shall be of sufficient length and width to provide and solid set in the ground and to provide space for marking above ground when applicable. Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top 2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:

1. Roads and parking lots -Orange

2. Waterlines and utilities -Blue

3. Paths/Trails -Red

CONSTRUCTION STAKING 010250-2

4. Buildings, excavation and grading -Yellow

2.3 SURVEY NOTE PAPER AND BOOKS

A. Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor.

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract.

The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.

B. Accuracy requirements:

1. Minimum position close; 1/1000

2. Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal)

3. Cross section and slope stake precision:

C. Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.

D. Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross-section points will not exceed: 1.0 ft.

E. Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%.

Clearing limits: 1.0 ft.

3.2 ESTABLISING AND REFERENCING IMPROVEMENT LOCATIONS

A. Access Roads, Turnouts, and Parking lots:

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles as shown on the drawings.

2. Slope stakes shall be set at 50-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points. Slope stakes shall be set at 25 foot intervals around curves having a radius less than 100 feet.

B. Paths and Trails

CONSTRUCTION STAKING 010250-3

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles as shown on the drawings.

2. Slope stakes shall be set at 10-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points.

3.3 DISCREPANCIES

A. The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of bench marks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.

3.4 VERTICAL CONTROL

A. Vertical control for construction shall be as referenced on the Drawings.

3.5 MARKING STAKES

A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;

PI Point of Intersection of tangents

PC Point of curvature

POC Point on curve

Pt Point of tangency

POT Point on tangent

RP Reference point

P P-line (preliminary location line)

L L-line (final location line)

BM Bench mark

TBM Temporary bench mark

BT Begin taper (any)

ET End taper (any)

C Cut

CONSTRUCTION STAKING 010250-4

F Fill

L Centerline

D Ditch

W Width

3.6 SURVEY NOTES

A. All survey data shall be neatly recorded in survey books. All survey notes shall become the property of the Forest Service. Errors shall be deleted by lining out. Date, crew names and positions, instrumentation, and weather shall be recorded in the notes at the beginning of each day’s work. The party chief shall sign or initial each page of the notes immediately after the last entry for each day’s work.

B. Electronically recorded survey notes shall be consecutively numbered and headed to identify the contents. The notes shall be supported and accompanied by a bound book that records the project name and for each day identifies date, crew names and positions, instrumentation, weather, type of survey, stationing of sections between which survey was performed, and survey data or sketched that cannot be electronically recorded. The party chief shall sign or initial the electronically recorded notes and Day Book immediately after the last entry for each day’s work.

END OF SECTION 010250

MOBILIZATION 011900-1

HWY 88 TRAILHEAD IMPROVEMENTS GAOA PROJECT

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 011900

March 2024

SUBMITTAL PROCEDURES 013300-1

HWY 88 TRAILHEAD IMPROVEMENTS GAOA PROJECT

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.

B. See other specification sections within this package for additional requirements on submittal.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

SUBMITTAL PROCEDURES 013300-2

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit electronic copies of each submittal, unless otherwise indicated. CO will return two physical copies or electronic copy. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

SUBMITTAL PROCEDURES 013300-3

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Notation of dimensions established by field measurement.

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit electronic copies, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."

B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

SUBMITTAL PROCEDURES 013300-4

E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

PART 3 - EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, Contractor shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

F. Requests for substitutions will only be considered if contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.

Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.

2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.

3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.

4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required

SUBMITTAL PROCEDURES 013300-5

submittals for the project - the table is to assist the Contractor and may not be all inclusive

– additional submittals may be required by specific specifications:

TABLE 013000-1

Spec.

Section

Section Title Subsec tion Required Submittal

010250 Construction Staking 3.6 A Survey Notes

014130 Quality Control 1.3A Contractor quality control plan

014130 Quality Control 1.3B Permits, Licenses and Certificates

014130 Quality Control 1.3C Test and Inspection Reports

014130 Quality Control 1.2D As-Built Drawings

020900 Traffic Control 3.1A Traffic Control Plan

023701 Sediment & Erosion Control Measures 1.2A Sediment & Erosion Control Plan

033540 Concrete Walkway 1.3A Product Data

033540 Concrete Walkway 1.3B Design Mixtures

033540 Concrete Walkway 1.3C Reinforcement

033540 Concrete Walkway 1.3D Material Test Reports

033540 Concrete Walkway 1.3E Contraction/Expansion Joint Layouts

101110 Information Kiosk 1.2A Manufacturer’s Literature

129300 Site Furnishings 1.2A Product Data

133400 Precast Concrete Vault Restroom Building

1.3D Finish Samples

133400 Precast Concrete Vault Restroom Building

1.3E Final Plans

313700 Riprap & Minor Rockery Structures 1.3A Material Samples, Source, Properties

313700 Riprap & Minor Rockery Structures 1.3B Material Samples, Source, Properties

312000 Earthwork 1.3A Source and Analysis

312225 Excavation and Embankment 1.3A Density Tests

312225 Excavation and Embankment 1.3B Repeat Tests

321200 Warm Mix Asphalt Paving 1.3A Product Data

321200 Warm Mix Asphalt Paving 1.3B Mix Designs

SUBMITTAL PROCEDURES 013300-6

Spec.

Section

Section Title Subsec tion Required Submittal

321200 Warm Mix Asphalt Paving 1.3C Material Certificates

321204 Crushed Aggregate Base or Surface Course

1.2A Source

321204 Crushed Aggregate Base or Surface Course

1.2B Compaction Test Results and Proctor

321204 Crushed Aggregate Base or Surface Course

1.2C Material Properties

322622 Precast Concrete Curb

2.1B Certificate of Conformance – Concrete Curb

322640 Pavement Markings 1.3A Product Data

END OF SECTION 013300

QUALITY CONTROL 014100-1

HWY 88 TRAILHEAD IMPROVEMENTS PROJECT

SECTION 014100 - QUALITY CONTROL

PART 1 - GENERAL

1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.

1.2 QUALITY CONTROL

A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.

B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:

1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.

2. Testing agency will re-test and re-inspect corrected work.

C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.

1.3 SUBMITTALS

A. Contractor Quality Control Plan

B. Permits, Licenses, and Certificates

C. Test and Inspection Reports

D. As-Built Drawings

1.4 MEASUREMENT AND PAYMENT

A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.

QUALITY CONTROL 014100-2

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 QUALITY CONTROL SYSTEM

A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.

3.2 CONTRACTOR QUALITY CONTROL PLAN

A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.

1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.

2. The Government reserves the right to require changes in the plan during the contract period as necessary.

3. No change in the approved plan may be made without written concurrence by the Contracting Officer.

4. At a minimum, the plan shall include the following:

a. A list of personnel responsible for quality control and assigned duties.

Include each person's qualifications.

b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.

c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

d. Methods of performing, documenting, and enforcing quality control of all work.

e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.

3.3 TEST AND INSPECTION REPORTS

A. Submit three copies of complete test results no later than three calendar days after the test was performed.

B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.

C. Testing and Inspection Reports shall include the following:

1. Date of issue.

2. Project title and number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples, tests, or inspections.

5. Names of individuals performing tests and inspections.

QUALITY CONTROL 014100-3

6. Reference Specification Section(s).

7. Complete test or inspection data.

8. Test and inspection results and an interpretation of test results.

9. Ambient conditions at time sample was taken, tested, or inspected.

10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.

11. Name and signature of laboratory inspector.

12. Recommendations on retesting and reinspecting.

3.4 PERMITS, LICENSES, AND CERTIFICATES

A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.

3.5 AS-BUILT DRAWINGS

A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.

These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.

3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS

A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:

TABLE 014100-1

Item

Subsection Certification or Test Required

Frequency

033000 2.13 Mixing and Delivery Each Truck

033000 3.13 Concrete – Slump, Air, Temperature 1 composite per truck load delivered

033000 3.13 Concrete - Compression Test Specimens at 7 days and 28 days (see spec)

312000 3.18B Fill and Backfill Compaction Each fill or backfill layer

QUALITY CONTROL 014100-4

TABLE 014100-1

Item

Subsection Certification or Test Required

Frequency

312000 3.18D Compaction of Soils in Place At subgrade and each compacted fill and backfill layer (see spec)

321200 3.9B Gradation and Asphalt Content One per 700 tons or Min. of 1 per Project

321200 3.8C Field Density Tests – Asphalt One test for every 300

sq. yd. of pavement

321204 3.4A Compaction Tests – Road Base and Surface Course

One test for every 300

sq. yd. of aggregate

END OF SECTION 014100

ENVIRONMENTAL CONDITIONS 020000-1

HWY 88 TRAILHEAD IMPROVEMENTS GAOA PROJECT

SECTION 020000 – ENVIRONMENTAL CONCERNS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Coordinates

2. Weather Conditions

3. Elevation

1.2 APPROXIMATE COORDINATES

A. Shaelor Lake Trailhead Lat/Long: 38.6554, -120.1348

B. Thunder Mountain Trailhead Lat/Long: 38.7058, -120.1073

C. Lake Margaret Trailhead Lat/Long: 38.7042, -120.0697

1.3 WEATHER CONDITIONS

A. Freezing conditions exist during the winter months.

B. 90 degree plus temperatures exist during the summer months.

1.4 ELEVATION

A. Shaelor Lake Trailhead: 7,435 +/- ft

B. Thunder Mountain Trailhead: 7,945 +/- ft

C. Lake Margaret Trailhead: 7,745 +/- ft

1.5 DESIGN WIND SPEED

A. Per CBC requirements.

END OF SECTION 020000

CONSTRUCTION AREA TRAFFIC CONTROL DEVICES 020900-1

HWY 88 TRAILHEAD IMPROVEMENTS GAOA PROJECT

SECTION 020900 – CONSTRUCTION AREA TRAFFIC CONTROL DEVICES

PART 1 - GENERAL

1.1 This section sets forth requirements concerning possible flagging (if traffic volume dictates) and traffic handling equipment and devices used in carrying out the Contractor’s responsibilities for public convenience and public safety. This section applies to all work associated within each project site and hauling of materials & equipment into and out of each site, waste area, and borrow site.

1.2 Attention is directed to the Manual on Uniform Traffic Control Devices (MUTCD) for Streets and Highways, latest edition, published by the U.S. Department of Transportation, Federal Highway Administration. The contents of this manual are incorporated by reference in its entirety into this specification.

PART 2 - PRODUCTS

2.1 BARRICADES

1. Appropriate barricades and construction area signs shall be furnished, installed, maintained, and removed when no longer required.

PART 3 - EXECUTION

3.1 TRAFFIC CONTROL PLAN

A. The Contractor shall develop a Traffic Control Plan. The plan shall be developed, submitted to the Contracting Officer, and approved by the Contracting Officer before commencing construction activities. The plan shall show and describe how traffic will be provided for during the construction activities. The Traffic Control Plan shall include necessary and required construction area signs and conform to the provisions of the latest edition of the MUTCD. The Contractor shall be responsible for coordination with the onsite inspector.

B. During any blasting, hauling, and excavation operations, road may be closed and public traffic stopped for periods not to exceed ½ hours. After each closure, all accumulated traffic shall be allowed to pass through the work before another closure.

C. Should the Contractor decide to use the provisions in the previous paragraph they shall place signs advising the public of the possible delays. The signs shall be commercial quality and of sufficient size to be easily read by passing motorists.

END OF SECTION 026210

SEDIMENT AND EROSION CONTROL MEASURES 023701-1

HWY 88 TRAILHEAD IMPROVEMENTS GAOA PROJECT

SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES

PART 1 - GENERAL

1.1 The work under this section consists of furnishing all necessary labor, equipment, materials, and performing all operations in connection with construction sediment and control measures.

A. General

1. All erosion and sediment control measures are to be placed prior to any disturbance caused by grading and or excavation and shall conform to the requirements of the appropriate regulatory agency for the State.

2. The Contractor shall be solely responsible for ensuring that erosion and sediment control measures are implemented and maintained at the site.

3. Soil disturbing activities include but are not limited to: Clearing and grubbing, roadway and parking area construction, construction or modification of site drainage, and grading.

4. The Contractor shall remove temporary sediment and erosion control measures prior to contract closeout, unless determined otherwise.

1.2 SUBMITTALS

A. The Contractor shall be required to submit a sediment and erosion control plan in accordance with this specification for approval by the Contracting Officer 2 weeks prior to start of work.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Synthetic Filter Fabric for silt fences.

1. Pervious sheet of polypropylene, nylon, or polyethylene fabric conforming to the following physical and hydraulic characteristics:

• Physical Properties (Min.) Requirement Test Method

• Grab Tensile, lbs. W120/F100 ASTM-D-4632

SEDIMENT AND EROSION CONTROL MEASURES 023701-2

• Grab Elongation, % 15 ASTM-D-4632

• Mullen Burst, psi 275 ASTM-D-3786

• Puncture, lbs. 65 ASTM-D-4833

• Trapezoidal Tear, lbs. 50 ASTM-D-4533

• UV Resistance, % 80 ASTM-D-4355

• AOS, US Sieve # 30/40 ASTM-D-4751

• Permittivity gal/min-sq. ft. 90 ASTM-D-4491

2. Filter fabric should contain ultraviolet ray inhibitors and stabilizers to provide a minimum of 6 months of expected usable construction life at a temperature range of 0 to 120 F.

3. Support Posts: 4 foot - 2 x 2 wood.

B. Straw Bales.

1. Oat or wheat straw, free from weeds, viable weed seeds, foreign matter detrimental to plant life, and dry.

a. Grass hay bales are not acceptable.

b. In order to prevent deterioration of the bindings, all bales shall be either wire-bound or string-tied so that bindings are oriented around the sides rather than along the tops and bottoms of the bales.

PART 3 - EXECUTION

3.1 CONSTRUCTION

A. Install straw bales at local drainage ways to prevent silt intrusion upon adjacent drainage courses. Remove straw bales following establishment of vegetation cover and utilize as mulch at swales or on steep slopes.

B. Prior to construction, install silt fence along the downhill construction limits to prevent silt intrusion upon adjacent land.

C. Install sediment and erosion control measures on the down slope toe of all topsoil stock piles.

D. Maintain and remove all erosion controls as specified.

3.2 DUST CONTROL

A. In areas subject to surface and air movement of dust, where on-site or off-site damage is likely to occur, one or more of the following preventive measures shall be taken for dust control:

SEDIMENT AND EROSION CONTROL MEASURES 023701-3

1. Minimize the period of soil exposure through the use of temporary ground cover and other temporary stabilization practices.

2. Sprinkle the site with water until surface is wet. Repeat as needed.

3.3 SILT FENCE

A. Silt fences are appropriate for the following general locations:

1. Immediately upstream of the point(s) of runoff discharge from a site before flow becomes concentrated. Below disturbed areas where runoff may occur in the form of overland flow.

2. Along the down slope toe of all topsoil stock piles.

B. Materials.

1. Utilize standard strength synthetic filter fabric for sediment barriers. The filter fabric shall be purchased in a continuous roll cut to the length of the barrier to avoid the use of joints. When joints are necessary, filter cloth shall be spliced together only at a support post, with a minimum 6 inch overlap, and securely sealed.

2. The standard strength filter fabric shall be stapled or wired to the fence and 6 inches of the fabric shall be extended into the ground. Filter fabric shall not be stapled to existing trees.

3. Support posts shall be spaced at a maximum 6 feet and driven securely into the ground a minimum of 24 inches.

4. Filter fabric shall be buried a minimum of 12 inches.

5. The height of a silt fence shall not exceed 36 inches. Higher fences may impound volumes of water sufficient to cause failure of the structure.

C. Maintenance.

1. Silt fences and filter barriers shall be inspected immediately after each rainfall and at least daily during prolonged rainfall.

2. Silt fences shall be inspected for depth of sediment, tears, and to see if the fabric is securely attached to the fence posts, and to see that the fence posts are firmly in the ground. Any deficiencies shall be repaired immediately.

3. Should the fabric on a silt fence of filter barrier decompose or become ineffective prior to the end of the expected usable life and the barrier still be necessary, the fabric shall be replaced promptly.

4. Sediment deposits should be removed after each storm event and/or when deposits reach approximately 1/3 the height of the barrier or when the sediments limit or prevent the flow of water through the fabric hydraulic.

5. Any sediment deposits remaining in place after the silt fence or filter barrier is no longer required shall be dressed to conform with the existing grade, prepared, and seeded.

3.4 STRAW BALE EROSION CONTROL FENCE

A. Straw bale erosion control fences are appropriate for the following general locations:

SEDIMENT AND EROSION CONTROL MEASURES 023701-4

1. Sheet flow applications: Straw bales shall be placed in a single row, lengthwise on the contour with ends of adjacent bales tightly abutting one another.

2. Channel flow applications: Straw bales shall be placed in a single row, lengthwise and oriented perpendicular to the direction of flow with ends of adjacent bales tightly abutting one another. The barrier shall be extended to such a length that the bottoms of the end bales are higher in elevation than the top of the lowest middle bale to assure that sediment laden runoff will flow either through or over the barrier but not around it.

B. The barrier shall be entrenched and backfilled. A trench shall be excavated the width of a bale and the length of the proposed barrier to a minimum depth of 4 inches. After the bales are staked and chinked, the excavated soil shall be backfilled against the barrier.

Backfill shall conform to the ground level of the downhill side and shall be built up to 4 inches against the uphill side of the barrier.

C. Each bale shall be securely anchored by at least 2 stakes or rebar driven through the bale.

The first stake in each bale shall be driven toward the previously laid bale to force the bales together. Stakes or rebar shall be driven a minimum of 12 inches into the ground or deep enough into the ground to securely anchor the bales, whichever is greater.

D. The gaps between bales shall be chinked (filled by wedging with straw to prevent water from escaping between the bales). Loose straw scattered over the area immediately uphill from a straw bale barrier tends to increase barrier efficiency.

3.5 MAINTENANCE

A. Inspection shall be frequent and repair or replacement shall be made promptly as needed.

Straw bale carriers shall be removed when they have served their usefulness, but not before the upslope areas have been permanently stabilized.

END OF SECTION 023701

WASTE MATERIAL DISPOSAL 024100-1

HWY 88 TRAILHEAD IMPROVEMENTS GAOA PROJECT

SECTION 024100 - WASTE MATERIAL DISPOSAL

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the loading, handling, hauling, and placing of excess excavation material, unsuitable excavation material, clearing and grubbing debris, and construction and demolition debris.

1.2 MEASUREMENT AND PAYMENT

A. There will be no separate measurement or payment for work in this Section. Waste material disposal is considered incidental to other items of work shown in the Schedule of Items.

PART 2 - PRODUCTS – NOT APPLICABLE

PART 3 - EXECUTION

3.1 WASTE MATERIAL TO BE HAULED TO A DISPOSAL AREA

A. All excavated material not used in the construction of embankments or backfilling of trenches, or other excess material resulting from the excavation and embankment operation shall be hauled to a disposal area or spread onsite as designated by the Contracting Officer.

B. All unsuitable excavated material and oversize boulders shall be hauled to a disposal area.

1. Oversized boulders may be broken into sizes small enough to incorporate into the embankment according to Specification 312225.

C. All stumps, slash and other clearing and grubbing debris shall be hauled to a disposal area.

D. Disposal Area: All waste material above shall be hauled to the designated disposal area on Government property as designated by the Contracting Officer.

1. Waste material shall be piled and compacted to form a dense layer.

2. The size and shape of the piled waste material shall be designated by the

Contracting Officer.

3. The piled material shall be covered with soil to a uniform depth of six inches minimum and sloped to 2:1 or flatter.

4. The disposal site shall be left suitable for seeding.

3.2 WASTE MATERIAL TO BE HAULED TO A LANDFILL

WASTE MATERIAL DISPOSAL 024100-2

A. All demolition materials, garbage, and other refuse generated shall be removed from the project site and legally disposed off of Government property in an approved landfill.

B. The Contractor is responsible for all costs and permits associated with landfill disposal.

C. The Government is not responsible for waste material upon its departure from the project site.

END OF SECTION 024100

PATHS AND TRAILS 026210-1

HWY 88 TRAILHEAD IMPROVEMENTS GAOA PROJECT

SECTION 026210 – PATHS AND TRAILS

PART 1 - GENERAL

1.1 NATIVE SOIL TRAIL or ORAR: Outdoor Recreation Access Routes, as defined by the Forest Service Outdoor Recreation Accessibility Guidelines (FSORAG). All paths shall comply with FSORAG guidelines. This work consists of constructing paths and trails in accordance with the plans and these specifications.

PART 2 - MATERIALS

2.1 TRAIL SURFACING MATERIALS

A. Native materials:

1. Native materials excavated from other work on site may be used to construct and surface new trails.

2. Native materials shall be cleaned of organic and other deleterious material.

3. Native materials are preferred.

B. Import materials

1. Shall have low clay content so trails do not deform when wet.

2. Shall have no organic content.

C. All trail surfacing materials, native or import, shall comply with the following:

1. Sieve analysis:

a. 3/8-inch sieve – 100% passing

b. 1/4-inch sieve – 65% passing

c. 3/16-inch sieve – 50% passing

d. 1/8-inch sieve – 35% passing

e. 1/16-inch sieve – 25% passing

2. Colors shall be similar to existing soils.

PART 3 - EXECUTION

3.1 EXCAVATION

A. Excavations for paths and steps shall be to the depths, grades and widths necessary to permit construction to the finish grades and elevations shown on the plans. All excavations shall be in accordance with SECTION 312000 EARTHWORK.

3.2 SUBGRADE PREPARATION

PATHS AND TRAILS 026210-2

A. Compacted subgrade shall be prepared for all paths and steps in accordance with

SECTION 312000 EARTHWORK.

B. Relative compaction of the subgrade shall be not less than 95%. Any soft and yielding or otherwise unacceptable materials shall be removed and replaced with approved fill material.

C. The subgrade must be approved by the Forest Service before placement of surfacing materials.

3.3 PATH SLOPES

A. Construction shall be in accordance with the plans and these specifications. The path surface shall not exceed a 10 percent slope in the direction of travel, and a 2 percent cross-slope.

3.4 GRADING

A. All backfill and finish grading shall be in accordance with SECTION 312225 EXCAVATION AND EMBANKMENT and SECTION 312000 EARTHWORK.

B. Where paths meet the top of wood steps, there shall be no greater than 1/2” difference in elevation after final compaction. Where paths meet the bottom of a wood step, there shall be no void between the wood and walkway. A maximum build-up on to the lower step of 1/2” after final compaction will be allowed.

END OF SECTION 026210

CAST-IN-PLACE CONCRETE 033000-1

HWY 88 TRAILHEAD IMPROVEMENTS GAOA PROJECT

SECTION 033000 - CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section specifies cast-in place concrete, including formwork, reinforcement, concrete materials, mixture design, vapor barrier, placement procedures, and finishes.

1.2 DEFINITIONS

A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace slag, and silica fume; subject to compliance with requirements.

1.3 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Design Mixtures: For each concrete mixture. Indicate amounts of mixing water to be withheld for later addition at Project site.

C. Steel Reinforcement Shop Drawings when project design requires special consideration.

D. Field quality-control test reports.

E. Contraction and Expansion Joint Layout.

1.4 MEASUREMENT AND PAYMENT

A. There will be no separate measurement or payment for work in this section. Payment will be included at the contract unit price for items shown on the Schedule of Items.

PART 2 - PRODUCTS

2.1 FORM-FACING MATERIALS

A. Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true, and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of joints.

1. Plywood, metal, or other approved panel materials.

2. Exterior-grade plywood panels, suitable for concrete forms, complying with

DOC PS 1, and as follows:

a. Structural 1, B-B or better; mill oiled and edge sealed.

b. B-B (Concrete Form), Class 1 or better; mill oiled and edge sealed.

CAST-IN-PLACE CONCRETE 033000-2

B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material. Provide lumber dressed on at least two edges and one side for tight fit.

C. Forms for Cylindrical Columns, Pedestals, and…

This is the start of the file's text. The full file is on GovTribe.