Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A.1_Drawings.pdf | ||
| A.2_Wage_rate.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 SOLICITATION NUMBER 2 TYPE OF SOLICITATION 3. DATE ISSUED
SOLICITATION, OFFER,
0 SEALED BID (IFB) AND AWARD
(Construction, Alteration, or Repair) 1263A918R0009 181 NEGOTIATED (RFP) 04/19/2018 IMPORT ANT - The "offer" section on the reverse must be fully completed by offeror.
4 CONTRACT NUMBER
7 ISSUED BY
USDA FOREST SERVICE
SUPERIOR NATIONAL FOREST
8901 GRAND AVENUE PLACE
DULUTH MN 55808-1102
5 REQUISITION/PURCHASE REQUEST NUMBER
6 PROJECT NUMBER
CODE 63A9 8 ADDRESS OFFER TO
USDA FOREST SERVICE
SUPERIOR NATIONAL FOREST
ATTN: PNEPHEW@FS.FED.US
8901 GRAND AVENUE PLACE
DULUTH MN 55808-1102
PAGE OF
9. FOR INFORMATION la NAME CALL: ► Paul Nephew lb. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
218-626-4360
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title. identifying number, date)
IGF::OT::IGF
Solicitation: 1263A918R0009
Project Title: Superior National Forest Two Island River Culvert and Road Work
PAGES
Description: Replace the existing Two Island River culvert on FR 166 (600 Road) with an 15' 1 O" span x 3' 6" rise open bottom metal box culvert set on concrete footings to improve Aquatic Organism Passage.
Project Location: Project is located approximately 6 miles northwest of Tofte, MN on the Tofte Ranger District.
Project Magnitude: $400,000 to $500,000
Set Aside: Total Small Business
Pre-Bid Conference: To be determined
11. The contractor shall begin performance within 10 calendar days and complete it within 120 calendar days after receiving
181 award, 0 notice to proceed. This performance period is O mandatory 181 negotiable. (See ___________ ).
12a THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE ANO PAYMENT BONDS?
(If "YES", indicate w,thm how many calendar days after award m Item 12b )
181YES □ No
13 ADDITIONAL SOLICITATION REQUIREMENTS:
12b CALENDAR DAYS
10 calendar da s
a. Sealed offers in original and ___ copies to perform the work required are due at the place specified in Item 8 by 2:00PM CST (hour) local time 05/18/2018 (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
b. An offer guarantee 181 is, 0 is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference .
d. Offers providing less than ____ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
STANDARD FORM 1442 (REV 8/2014)
Prescribed by GSA- FAR (48 CFR) 53 236-1(d)
Solicitation No. 1263A9R180009 Superior National Forest Two Island River Culvert and Road Work
NOTE Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.
Payment will be made on actual work performed as described in FP-14
109.01 unless otherwise noted.
1. The Standard Specifications for Construction of Roads and Bridges on Federal Highway Project FP-14 edition has been used for this contract. Copies of this book are available at the USFS engineering office in Ely or Grand Marais.
2. Contract will only be awarded if funds are available. All or none of the optional bid items may or may not be awarded based on bids and funds available.
3. All clearing, grubbing, bedding, borrow, backfill, detours, diversions, signing, and other miscellaneous items not listed above with unique bid items shall be considered incidental to the contract. See 109.05
4. Quantities for crushed aggregate are loose volumes.
Proposals are to be submitted to the following address: Facsimile offers are NOT authorized. When submitting Mail or Email Offeror please put the Solicitation number on the envelope or in the email and send to ATTENTION of Paul Nephew. Email offers may to: pnephew@fs.fed.us
USDA FOREST SERVICE
ATTN PAUL NEPHEW
8901 GRAND AVENUE PLACE
DULUTH MN 55808-1122
To be considered responsive, bidders must submit a completed SF1442, Section B, Section K, and response to the evaluation criteria in Section M and complete Technical Proposal Forms.
CONTRACT TIME: See Section F.
REPRESENTATIONS AND CERTIFICATIONS:
SUCCESSFUL AWARDEE: To be awarded a contract with the Federal Government, the successful firm must be actively registered in the Systems for Awards Management (SAM) and the Invoice Processing Platform (IPP).
mailto:pnephew@fs.fed.us
PART I - SCHEDULE OF ITEMS
SECTION B – SERVICES AND PRICES
Two Island River Crossing and FR 166 Improvements
FR 166
Superior National Forest
Cook County
B- 1 - SCHEDULE OF ITEMS
ITEM
NO.
DESCRIPTION PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
15101 Mobilization Lump Sum 1 $_________ $__________ 15201 Construction survey and staking, tolerance A Lump Sum 1 $_________ $__________ 15401 Contractor Testing Lump Sum 1 $_________ $__________ 15713 Soil Erosion & Pollution Control Lump Sum 1 $_________ $__________ 20301 Removal of Existing Culverts, disposal method A Lump Sum 1 $_________ $__________ 20305 Removal of Boulder Each 25 $_________ $__________ 20426 Ditch Excavation, Ditch Construction/Reconstruction Foot 3105 $_________ $__________
25101a Placed riprap, class III Cubic Yard 8 $_________ $__________ 25101b Placed riprap, class IV Cubic Yard 30 $_________ $__________ 30207a 4” Aggregate Surfacing, grading P (MnDOT Class 1 Modified), Lake Cty 7 to FR 343 (Temp Rvr Road) Loose Vol., method 3 Cubic Yard 6830 $_________ $__________
30207b Additional Aggregate Surfacing, Grading P, method 3 Cubic Yard 1460 $_________ $__________ 30210 Pit run maximum size 3”, compaction method 3 Cubic Yard 2165 $_________ $__________
30302a Ditch Reconditioning – Cleaning Lk Cty 7 – FR 343 Foot 11195 $_________ $__________ 31403 Development of government furnished source Lump Sum 1 $_________ $__________ 60103 Contractor Designed Concrete Footings Each 2 $_________ $__________
60201a 18” diam polymer-coated pipe culvert, 14 ga (no bands) Foot 24 $_________ $__________ 60201b 21” diam polymer-coated pipe culvert, 14 ga (no bands) Foot 28 $_________ $__________ 60201c 24” diam polymer-coated pipe culvert, 14 ga (no bands) Foot 86 $_________ $__________ 60201d 30” diam polymer-coated pipe culvert, 12 ga (no bands) Foot 28 $_________ $__________ 60202a 17” x 13”, polymer-coated pipe culvert, 14 ga (no bands) Foot 52 $_________ $__________ 60202b 21” x 15”, polymer-coated pipe culvert, 14 ga (no bands) Foot 406 $_________ $__________ 60202c 24” x 18”, polymer-coated pipe culvert, 14 ga (no bands) Foot 30 $_________ $__________ 60202d 28” x 20”, polymer-coated pipe culvert, 14 ga (no bands) Foot 98 $_________ $__________ 60202e 71” x 42”, polymer-coated pipe culvert, 10 ga (no bands) Foot 34 $_________ $__________ 60302 HL 93 Aluminum or Steel Open Bottom Culvert 14’-5” span
(min.), 3’-3” rise (min), structural plate box Foot 45 $_________ $__________
62403 Furnishing and Placing Topsoil Cubic Yard 12 $_________ $__________ 62550 Turf establishment Lump Sum 1 $_________ $__________ 62701 Sod Square Yard 100 $_________ $__________ 63501 Temporary Traffic Control Lump Sum 1 $_________ $__________ 64801 Placed Fish Rest Stop Channel Rock, FRS class 4, method A Each 20 $_________ $__________ 64805 Placed Streambed simulation rock, bed class 10, methods A&C Cubic Yard 125 $_________ $__________
Total: $__ ______
Option Items 31203a Calcium Chloride, .3gal./s.y., method A – Lk Cty 7 – FR 343 (12’) Gallons 11000 $_________ $__________ 31203b Calcium Chloride, .3gal./s.y., method A – FR 343 – Sawbill Trail Gallons 10000 $_________ $__________ 31401a Stockpiled Aggregate, grading P (MnDOT Class 1 modified) (LV) Cubic Yards 2500 $_________ $__________ 31401b Stockpiled Aggregate, grading P (MnDOT Class 1 modified) (LV) Cubic Yards 5000 $_________ $__________ 30207c 4” Aggregate surface course, grading P (MnDOT Class 1
Modified), FR 343 to Sawbill Trail, Loose Volume, method 3 Cubic Yard 6450 $_________ $__________
30302a Ditch Reconditioning – Cleaning FR 343 - Sawbill Trail Foot 2200 $_________ $__________
Solicitation No. 126392R18005 Chippewa National Forest Pigeon River Bridge Replacement
Two Island River Crossing Replacement Forest Road 166
Tofte Ranger District, Superior National Forest
Table of Contents Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04
104.06 Use of Roads by Contractor
105 - Control of Material
105.02(a) Government-provided sources
105.02 (a) Government-provided sources
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.02 Visual Inspection
107 - Legal Relations and Responsibility to the Public
Delete Subsection 107.05
108 - Prosecution and Progress
Delete Section 108
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09
109.02 Measurement Terms and Definitions
152 - Construction Survey and Staking
152.04 General
152.05 Survey and Staking Requirements
Table 152-1 Construction Survey and Staking Tolerances
153 - Contractor Quality Control
153.02 Qualifications
153.03 Quality Control Plan
Tofte Ranger District, Superior National Forest
153.07 Records and control charts
155 - Schedules for Construction Contracts
Delete Section 155
156 - Public Traffic
Section 156. – PUBLIC TRAFIC
157 - Soil Erosion and Sediment Control
157.04 General
203 - Removal of Structures and Obstructions
203.04 (b) General
203.05 Disposing of Material
204 - Excavation and Embankment
Section 204. — EXCAVATION AND EMBANKMENT
209 - Structure Excavation and Backfill
209.09 Backfill
209.10 Compacting
302 - Minor Crushed Aggregate
302.04 Placing Crushed Aggregate
314 - Stockpiled Aggregates
314.01 Description
314.04 Stockpile Site
602 - Culverts and Drains
602.05 Laying Metal Pipe
603 - Structural Plate Structures
603.03 General
603.04 Erecting
625 - Turf Establishment
Section 625. — TURF ESTABLISHMENT
648 - Stream Simulation
Section 648. — STREAM SIMULATION
703 - Aggregate
703.05 (c) Surface course aggregate. (3) Plastic Index
703.05 Subbase, Base, Surface Course, and Screened Aggregate
704 - Soil
Tofte Ranger District, Superior National Forest
704.02 Bedding Material
704.08 Select Granular Backfill
704.08 Select Granular Backfill. (a) Quality requirements. (2)
704.08 Select Granular Backfill. Table 704-2
705 - Rock
705.02 Riprap. Table 705-1
705.08 Streambed Simulation Rock
Preface Preface_wo_02_08_2018
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.
Tofte Ranger District, Superior National Forest
101 - Terms¸ Format¸ and Definitions 101.01_National_9_15_2016
Add the following paragraph to Subsection 101.01:
101.01 Meaning of Terms.
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_National_4_7_2015
Add the following to Subsection 101.03:
101.03 Abbreviations.
(a) Acronyms.
AGAR — Agriculture Acquisition Regulations
AFPA — American Forest and Paper Association
FSAR — Forest Service Acquisition Regulations
MSHA — Mine Safety and Health Administration
NESC — National Electrical Safety Code
WCLIB — West Coast Lumber Inspection Bureau
(f) Miscellaneous unit abbreviations.
MP — milepost location ppm — parts per million volume
STA station location
101.04_National_10_23_2016
Make the following changes to Subsection 101.04:
Tofte Ranger District, Superior National Forest
101.04 Definitions.
Delete these definitions and replace the following:
Bid Schedule — The Schedule of Items.
Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.
Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.
Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.
Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.
Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.
Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.
Add the following definitions:
Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line — A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road — Temporary construction access built along the route of the project.
Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Tofte Ranger District, Superior National Forest
Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.
Utilization Standards — The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Tofte Ranger District, Superior National Forest
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid¸ Award¸ and Execution of Contract 102.00_National_9_15_2016
Delete Section 102 in its entirety.
Delete Section 102.
Tofte Ranger District, Superior National Forest
103 - Scope of Work 103.00_National_9_15_2016
Delete all of Section 103 except Subsection 103.01 Intent of Contract.
Delete Subsections 103.02, 103.03, 103.04, 103.05.
104 - Control of Work 104.00_National_9_15_2016
Delete Subsections 104.01, 104.02, and 104.04.
Delete Subsections 104.01, 104.02, 104.04.
104.06_National_9_16_2016
Add the following to Subsection 104.06:
104.06 Use of Roads by Contractor.
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material 105.02_National_10_23_2016
Add the following to Subsection 105.02(a):
105.02(a) Government-provided sources.
Government-provided sources for this project are identified as follows:
(1) Government-provided mandatory sources.
Pay Item Description Material source number or name
(2) Government-provided optional sources for this project are identified as follows:
Pay Item Description Material source number or name All Crushed Aggregate, Borrow, Riprap Dog Tired Pit - T61nR4wS30
If the Contractor elects to obtain material from from Forest Service approved pits the following applies:
(1) Clearing of vegetation will not be allowed during June and July
(2) Materials may be used free of charge from Forest Service pits.
(3) If specified gradation cannot be met with materials available at Forest Service pit sites it will be the contractors responsibility to provide material from other sources at no additional cost to the Government. Quality and quantity is not guaranteed in Forest Service Pits. Contractor is responsible for providing additional binder at no additional cost to the Government if material available in pit cannot meet specifications.
(4) Contractor may use non Forest Service sources.
105.02_National_10_23_2016
Add the following to Subsection 105.02 (a):
105.02 (a) Government-provided sources.
Complete any pit or quarry development specified for a designated source, even when material is not obtained from the source.
106 - Acceptance of Work 106.01_National_7_18_2017
Delete Subsection 106.01 and replace with the following:
106.01 Conformity with Contract Requirements.
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work; providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
1. Sampling method;
2. Number of samples;
3. Sample transport;
4. Test procedures;
5. Testing laboratories;
6. Reporting;
7. Estimated time and costs; and
8. Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.
If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
1. Have the work accepted at a reduced price; or
2. Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.02_National_10_23_2016
Delete Subsection 106.02 and replace with the following:
Tofte Ranger District, Superior National Forest
106.02 Visual Inspection.
Acceptance is based on visual inspection of the work for compliance with the specific contract requirements.
Use prevailing industry standards in the absence of specific contract requirements or tolerances.
107 - Legal Relations and Responsibility to the Public 107.05_National_7_18_2017
Delete Subsection 107.05.
Delete Subsection 107.05.
108 - Prosecution and Progress 108.00_National_9_16_2016
Delete Section 108 in its entirety.
Delete Section 108.
109 - Measurement and Payment 109.00_National_9_16_2016
Delete Subsections 109.06, 109.07, 109.08, and 109.09:
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.02_National_9_16_2016
Add the following sentence to Subsection 109.02(b):
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
152 - Construction Survey and Staking 152.00_National_12_12_2016
Add the following to Subsection 152.04(c):
152.04 General.
(c) Material.
Use required stake dimensions and materials. Pre-paint the top 2 inches of all stakes and lath, or mark them with plastic flagging. Use designated colors for paint or flagging. Mark all stakes with a stake pencil that leaves a legible imprint, or with waterproof ink.
Do not use aerosol spray paints.
Use moisture-resistant paper for survey notes. Keep notes in books with covers that will protect the contents and retain the pages in numerical sequence.
Make the following changes to Subsection 152.05:
152.05 Survey and Staking Requirements.
Delete Subsection 152.05(d)(2) and replace with the following:
(d) Slope and reference stakes.
(2) Conventional survey methods. When required, locate slope stakes on designated portions of the road. Locate the slope stake catch points and use them to establish clearing limits and slope stake references.
Mark slope stakes with the station, the amount of cut or fill, the horizontal distance to centerline, and the slope ratios.
Place slope reference stakes at least 10 feet outside the clearing limit and mark with the offset distance to the slope stake. Place sight stakes when required.
Prior to clearing and grubbing operations, move the slope stake outside the clearing limit to the slope reference stake. After clearing and grubbing and before excavation, reset the slope stakes in their original position.
Use the designated method to establish the slope stake catchpoint.
Method I—Computed Method. Use the template information shown in the plans or other Government-provided data to calculate the actual location of the catchpoint. The slope stake “catchpoint distance” provided may be used as a trial location to initiate slope staking. Recatch slope stakes on any section that does not match the staking report within the tolerances established in Table 152-2.
Method II—Catchpoint Measurement Method. Determine the location of slope stake catchpoints by measuring the catchpoint distances shown in the plans or other Government-provided data.
Add the following to Subsection 152.05(e):
(e) Clearing and grubbing limits.
Mark the clearing limits with flagging or tags on trees to be left standing, or on lath. Make markings intervisible, and no more than 90 feet apart.
After establishing clearing limits, move the location line stake outside the clearing limits for station identification purposes, and mark it with horizontal distance to location line.
Tofte Ranger District, Superior National Forest
Replace Table 152-1 with the following:
Table 152-1 Construction Survey and Staking Tolerances Table 152-1
Construction Survey and Staking Tolerances (1)
Staking Phase Horizontal Vertical
Control points set from existing Government control points- Tolerance Class A
±0.03 feet (±10 millimeters)
±0.01 feet × N
(±3 millimeters × N )(2)
Mapping, topography, and cross-section Points- Tolerance Class A
±0.16 feet (±50 millimeters)
±0.16 feet (±50 millimeters)
Centerline points (3) including (PC), (PT), (POT),(POC), and references- Tolerance Class A
±0.06 feet (±20 millimeters)
±0.06 feet (±20 millimeters)
Slope-stake and slope-stake references- Tolerance Class A (4)
±0.16 feet (±50 millimeters)
±0.16 feet ±50 millimeters)
Culverts, ditches, and minor drainage structures stakes- Tolerance Class A
±0.16 feet (±50 millimeters)
±0.06 feet (±20 millimeters)
Retaining walls stakes ±0.06 feet (±20 millimeters)
±0.03 feet (±10 millimeters)
Curb and gutter stakes ±0.06 feet (±20 millimeters)
±0.03 feet (±10 millimeters)
Bridge substructures stakes ±0.03 feet (±10 millimeters)(5)
±0.03 feet (±10 millimeters)
Bridge superstructures stakes ±0.03 feet (±10 millimeters)(5)
±0.03 feet (±10 millimeters)
Clearing and grubbing limit stakes- Tolerance Class A
±1.00 feet (±300 millimeters)
Roadway subgrade finish stakes- Tolerance Class A (6)
±0.16 feet (±50 millimeters)
±0.03 feet (±10 millimeters)
Roadway finish grade stakes (6) ±0.16 feet (±50 millimeters)
±0.03 feet (±10 millimeters)
Table 152-1 Construction Survey and Staking Tolerances (continued) (1)
Staking Phase Horizontal Vertical
Control points set from existing Government control points –Tolerance Class B (7)
±0.16 feet (±20 millimeters)
±0.16 feet ×
(±20 millimeters × )(2)
Mapping, topography, and cross-section points–Tolerance Class B (7)
±1.00 feet (±300 millimeters)
±0.50 feet (±150 millimeters)
Centerline points including (PC), (PT), (POT),(POC), and references–Tolerance Class B (7)
±0.16 feet (±20 millimeters)
±0.16 feet (±20 millimeters)
Slope-stake and slope-stake references– Tolerance Class B (7)
±0.50 feet (±50 millimeters)
±0.16 feet ±50 millimeters)
Culverts, ditches, and minor drainage structures stakes–Tolerance Class B (7)
±0.50 feet (±150 millimeters)
±0.16 feet (±20 millimeters)
Clearing and grubbing limit stakes–Tolerance Class B (7)
±2.00 feet (±600 millimeters)
Roadway subgrade finish stakes–Tolerance Class B (7)
±0.50 feet (±50 millimeters)
±0.16 feet (±10 millimeters)
Roadway finish grade stakes–Tolerance Class B (7)
±0.50 feet (±50 millimeters)
±0.16 feet (±10 millimeters)
(1) At statistical 95 percent confidence level. Tolerances are relative to existing Government control points.
(2) N is the number of instrument setups.
(3) Centerline points: PC - point of curve, PT - point of tangent, POT - point on tangent, POC - point on curve.
(4) Take the cross-sections normal to the centerline ±1 degree.
(5) Bridge control is established as a local network and the tolerances are relative to that network.
(6) Includes paved ditches.
(7) Tolerance Class B for Very Low Volume Roads with an aggregate or native finished surface.
N
N
153 - Contractor Quality Control 153.02_National_9_15_2016
Delete Subsection 153.02 and replace with the following:
153.02 Qualifications.
Submit the following for approval with the quality control plan:
(a) Quality control manager (QCM). Furnish a QCM who has at least 2 years’ experience in construction, inspector, quality control and material testing on construction projects of similar type and scope.
(b) Testers. Provide testers with at least one year experience in the type of sampling and testing required, and with one of the following for the type of sampling and testing performed:
(1) NICET Level II certification in highway material or equivalent state or industry certification;
(2) Certification by a regional certification program (such as Western Alliance for Quality Transportation Construction (WAQTC), Northeast Transportation Technician Certification Program (NETTCP), Southeast Task Force for Technician Training and Qualification (STFTTQ), or Multi Regional Training and Certification (M-TRAC)); or
(3) At least one year employment by an AASHTO accredited laboratory performing equivalent sampling and testing.
153.03_National_9_15_2016
Add the following paragraph to the end of Subsection 153.03(b):
153.03 Quality Control Plan.
(b) Quality Control Procedures.
Submit written proposals for approval of alternate AASHTO or State approved test methods. Alternate methods may be allowed based on documented equivalence to the specified method.
153.07_National_9_15_2016
Delete Subsection 153.07 and replace with the following:
153.07 Records and control charts.
Maintain complete testing and inspection records by pay item number and make them accessible to the CO.
155 - Schedules for Construction Contracts 155.00_National_9_14_2016
Delete Section 155 in its entirety.
Delete Section 155.
156 - Public Traffic 156.00_National_9_14_2016
Delete Section 156 in its entirety and replace with the following:
Section 156. – PUBLIC TRAFIC Description
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
Permanent Traffic Control 633
Traffic Signing and Marking Material 718
Concrete Barriers and Precast Guardwalls 618
Temporary plastic fence 710.11
Construction Requirements
156.03 General. Accommodate traffic according to MUTCD, approved traffic control plan and this section.
Perform work in a manner that ensures safety and convenience of the public. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic.
Delays may not exceed 1 week for Two Island River Culvert and 60 minutes at any one time followed by an open period of no less than 15 minutes for other culverts. Accommodate public traffic on roads adjacent to and within the project until the project is accepted according to Subsection 106.07(b).
Submit traffic control plan at least 30 days prior to intended use. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved.
Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM 7100-15.
All required signs will be in place and approved prior to beginning work on project.
Tofte Ranger District, Superior National Forest
If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.
156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations.
(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.
(c) Install only those traffic control devices needed for each stage or phase.
(d) Relocate temporary traffic control devices as necessary.
(e) Remove devices that no longer apply to the existing conditions.
(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(g) Keep temporary traffic control devices clean.
(h) Remove all temporary traffic control devices upon contract completion or when approved.
(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.
156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.
Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.
Table 156-1 Temporary Road Closures
Road Number
From Terminus
To Terminus
Maximum Consecutive Days of Closure
Minimum Consecutive Days Open
156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.07 Do not measure Public Traffic for payment. Payment for contract work is provided indirectly. See Subsection 109.05.
157 - Soil Erosion and Sediment Control 157.04_National_9_14_2016
Delete Subsection 157.04 and replace with the following:
157.04 General.
Thirty (30) days prior to the start of construction, submit a written plan according to subsection 104.03 with all necessary permits that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control without approval.
When erosion control measures are not functioning as intended, take corrective action to eliminate or minimize pollutants in storm water discharges from the project.
203 - Removal of Structures and Obstructions 203.04_National_10_7_2016
Make the following changes to Subsection 203.04(b):
203.04 (b) General.
Delete the fifth paragraph of Subsection 203.04(b) and replace with the following:
Remove structures and obstructions in the roadbed to 12 inches (300 millimeters) below subgrade elevation.
Remove structures and obstructions outside the roadbed to 12 inches (300 millimeters) below finished ground or to the natural stream bottom.
Delete the seventh paragraph of Subsection 203.04(b) and replace with the following:
When abandoning an existing culvert pipe, remove the upstream and downstream portion of the culvert to within 12 inches (300 millimeters) of the subgrade or embankment slope. Ensure the abandoned pipe is at least 48 inches (1200 millimeters) from a new culvert or structure. Seal the abandoned culvert ends with a tight-fitting plug of concrete at least 6 inches (150 millimeters) thick. Ensure the structure does not entrap water.
203.05_National_10_7_2016
Add the following to Subsection 203.05:
203.05 Disposing of Material.
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toe line of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees.
(f) Scattering. Scatter construction slash in designated areas without damaging trees. Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations. When scattering for erosion control, place construction slash as flat as practicable on the completed slope.
(g) Chipping. Use an approved chipping machine to chip slash longer than 3 feet. Deposit chips on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking. Remove brush from designated log deck areas. Limb and top logs.
Tofte Ranger District, Superior National Forest
Logs not meeting the Utilization Standards described in Subsection 201.04(c) shall be cut to lengths less than 16 feet and decked in designated log deck location.
Merchantable timber not associated with an existing timber sale shall be cut to length meeting the Utilization Standards described in Subsection 201.04(c).
Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps.
204 - Excavation and Embankment 204.00_National_9_16_2016
Delete Section 204 in its entirety and replace with the following.
Section 204. — EXCAVATION AND EMBANKMENT Description
204.01 This work consists of excavating material and constructing embankments. This work also includes furnishing, hauling, stockpiling, placing, disposing, sloping, shaping, compacting, and finishing earthen and rocky material.
204.02 Definitions.
(a) Excavation. Excavation consists of the following:
(1) Roadway excavation. Material excavated from within the right-of-way or easement areas, except subexcavation covered in Subsection 204.02(a)(2) and structure excavation covered in Sections 208 and
209. Roadway excavation includes all material encountered regardless of its nature or characteristics.
(2) Subexcavation. Material excavated from below subgrade elevation in cut sections or from below the original ground-line in embankment sections. Subexcavation excludes the work required by Subsection
204.05 or 204.06.
(3) Borrow excavation. Material used for embankment construction that is obtained from outside the roadway prism. Borrow excavation includes unclassified borrow, and topping.
(b) Embankment construction. Embankment construction consists of placing and compacting roadway or borrow excavation. This work includes:
(1) Preparing foundation for embankment;
(2) Constructing roadway embankments;
(3) Benching for side-hill embankments;
(4) Constructing dikes, ramps, mounds, and berms; and
(5) Backfilling subexcavated areas, holes, pits, and other depressions.
(c) Conserved topsoil. Excavated material conserved from the roadway excavation and embankment foundation areas that is suitable for growth of grass, cover crops, or native vegetation.
(d) Waste. Excess and unsuitable roadway excavation and subexcavation that cannot be used.
Material
204.03 Conform to the following Subsections:
Topping 704.05
Unclassified borrow 704.06
Water 725.01(c)
204.04 Preparation for Roadway Excavation and Embankment Construction. Clear the area of vegetation and obstructions according to Sections 201 and 203.
Road pioneering, slash disposal, and grubbing of stumps may proceed concurrently with excavation and embankment. Maintain drainage during pioneering operations.
204.05 Conserved Topsoil. When designated, conserve topsoil from roadway excavation and embankment foundation areas. Stockpile conserved topsoil in low windrows immediately beyond the rounding limits of cut and embankment slopes or in other approved locations. Separate conserved topsoil from other excavated material.
When designated, place conserved topsoil on completed slopes according to Section 624.
204.06 Roadway Excavation. Excavate as follows:
(a) Rock cuts. Blast rock according to Section 205. Excavate rock cuts to 6 inches (150 millimeters) below subgrade within the roadbed limits. Backfill to subgrade with topping or other suitable material. Compact the material according to Subsection 204.11.
(b) Earth cuts. Scarify earth cuts to 6 inches (150 millimeters) below subgrade within the roadbed limits.
Compact the scarified material according to Subsection 204.11.
(c) Pioneer Roads. Conduct excavation and placement operations so material to be treated under Section 201 will not be incorporated into the roadway unless specified in the slash treatment method. Maintain drainage during pioneering operations.
Remove snow and ice in advance of the work and deposit beyond the roadway limits in a manner that will not waste material or generate sediment. Do not incorporate snow and ice into embankments. Place snow or ice in a manner to prevent resource damage.
(d) Drainage Feature. Drainage feature includes construction of all ditches, minor channel changes, drainage dips, catch basins, surface water deflectors, and other minor drainage structures. Compact the material according to Subsection 204.11. Excavate on a uniform grade between control points.
Do not disturb material and vegetation outside the construction limits. Retrieve material deposited outside the construction limits. Dispose of unsuitable or excess excavation material according to Subsection 204.14. Replace shortage of suitable material caused by premature disposal of roadway excavation.
Shape to drain and compact the work area to a uniform cross-section at the end of each day's operations.
204.07 Subexcavation. Excavate material to the required limits. Dispose of unsuitable material according to Subsection 204.14. Take cross-sections according to Section 152. Backfill subexcavated area with suitable material in horizontal layers not exceeding 12 inches (300 millimeters) in compacted thickness and compact according to Subsection 204.11. Prevent unsuitable material from mixing with suitable backfill material.
204.08 Borrow Excavation. Use suitable roadway excavation in embankment construction. Do not use borrow excavation when it results in excess roadway excavation. Deduct excess borrow excavation from the total borrow excavation quantity.
Obtain borrow source approval according to Subsection 105.02. Develop and restore borrow sources according to Subsections 105.03 and 105.06. Do not excavate beyond the established limits. When applicable, shape the borrow source to permit accurate measurements when excavation is complete.
204.09 Preparing Foundation for Embankment Construction. Prepare foundation for embankment construction as follows:
(a) Embankment over natural ground. Remove topsoil and break up the ground surface to a minimum depth of 6 inches (150 millimeters) by plowing or scarifying. Compact the ground surface according to Subsection 204.11.
(b) Embankments over an existing asphalt, concrete, or gravel road surface. Scarify gravel roads to a minimum depth of 6 inches (150 millimeters). Scarify or pulverize asphalt and concrete roads to 6 inches (150 millimeters) below the pavement. Reduce particles to a maximum size of 6 inches (150 millimeters) and produce a uniform material. Compact the surface according to Subsection 204.11.
(c) Embankment across ground not capable of supporting equipment. Dump successive loads of embankment material in a uniformly distributed layer to construct the lower portion of the embankment. Limit the layer thickness to the minimum depth necessary to support the equipment.
(d) Embankment on an existing slope steeper than 1V:3H. Cut horizontal steps in the existing slope to a sufficient width to accommodate placement and compaction operations and equipment. Step the slope as the embankment is placed and compacted in layers. Begin each step at the intersection of the original ground and the vertical cut of the previous step.
204.10 Embankment Construction. Incorporate only suitable roadway excavation material into the embankment.
When the supply of suitable roadway excavation is exhausted, furnish unclassified borrow to complete the embankment. Obtain written approval before beginning construction of embankments over 6 feet (2 meters) high at subgrade centerline. Construct embankments as follows:
(a) General. At the end of each day's operations, shape to drain and compact the embankment surface to a uniform cross-section. Eliminate ruts and low spots that could hold water.
During all stages of construction, route and distribute hauling and leveling equipment over the width and length of each layer of material.
Compact embankment side slopes with a tamping foot roller, by walking with a dozer, or by over-building the fill and then removing excess material to the final slope line. For slopes 1V:1¾H or steeper, compact the slopes as embankment construction progresses.
(b) Embankment within the roadway prism. Place embankment material in horizontal layers not exceeding 12 inches (300 millimeters) in compacted thickness. Incorporate oversize boulders or rock fragments into the 12-inch (300-millimeter) layers by reducing them in size or placing them individually as required below.
Compact each layer according to Subsection 204.11 before placing the next layer.
Material composed predominately of boulders or rock fragments too large for 12-inch (300-millimeter) layers may be placed in layers up to 24 inches (600 millimeters) thick. Incorporate oversize boulders or rock fragments into the 24-inch (600-millimeter) layer by reducing them in size or placing individual rock fragments and boulders greater than 24 inches (600 millimeters) in diameter as follows:
(1) Reduce rock to less than 48 inches (1200 millimeters) in the largest dimension;
(2) Distribute rock within the embankment to prevent nesting;
(3) Place layers of embankment material around each rock to a depth not greater than that permitted above. Fill voids between rocks; and
(4) Compact each layer according to Subsection 204.11(a) before placing the next layer.
(c) Embankment outside of roadway prism. When placing embankment outside the staked roadway prism, place material in horizontal layers not exceeding 24 inches (600 millimeters) in compacted thickness. Compact each layer according to Subsection 204.11.
204.11 Compaction. Compact the embankment using one of the following methods as specified.
(a) Placement Method 1. Use AASHTO T 27 to determine the quantity of material retained on a No. 4 (4.75-millimeter) sieve. Compact as follows:
(1) More than 80 percent retained on a No. 4 (4.75-millimeter) sieve. Adjust the moisture content to a level suitable for compaction. Fill the interstices around rock with earth or other fine material as practical.
Use compression-type rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet (1 meter) per second. Compact each layer of material full width with one of the following and until there is no visible evidence of further consolidation:
(a) Four roller passes of a vibratory roller having a minimum dynamic force of 40,000 pounds (180 kilonewtons) impact per vibration and a minimum frequency of 1000 vibrations per minute;
(b) Eight roller passes of a 20-ton (20-metric ton) compression-type roller; or
(c) Eight roller passes of a vibratory roller having a minimum dynamic force of 30,000 pounds (130 kilonewtons) impact per vibration and a minimum frequency of 1000 vibrations per minute.
Increase the compactive effort for layers deeper than 12 inches (300 millimeters) as follows:
• For each additional 6 inches (150 millimeters) or fraction thereof, increase the number of roller passes in Subsection 204.11(a)(1)(a), by four passes; or
• For each additional 6 inches (150 millimeters) or fraction thereof, increase the number of roller passes in Subsection 204.11(a)(1)(b) and (c), by eight passes.
(2) 50 to 80 percent retained on a No. 4 (4.75-millimeter) sieve. Classify the material according to AASHTO M 145.