This document is a bid tabulation for the Chippewa National Forest Stony Point Campground Upgrades project. The solicitation (No. 12445525B0001) includes bid submissions from seven contractors with varying prices for project components: Mobilization, General Requirements, Pumphouse Building, Electric System Replacement, Water System Replacement, and Wellhouse Demolition and Water Well Abandonment. Total bid prices range from $748,700.77 to $1,514,331.19, with contractors including Frontier Services, R B National LTD, Black Ridge Construction, Tunheim Mckenzie Construction, and Twin Pines Construction. Each contractor's bid includes a breakdown of unit prices for different project elements, with most submitting "Yes" for various bid requirements and some leaving certain fields blank.
The bid tabulation reveals significant price variations across contractors, with the lowest total bid at $748,700.77 and the highest at $1,514,331.19. Key project components include infrastructure upgrades such as electric and water system replacements, pumphouse building work, and wellhouse demolition. The solicitation appears to be for comprehensive campground improvements, with multiple line items allowing for detailed cost comparisons between potential contractors. While most bidders submitted complete responses, one contractor (Offeror No. 5) shows $0.00 for several line items, which may indicate an incomplete or non-responsive bid.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Well Log_AsBuilt_ProductData.pdf | ||
| Sol_12445525B0001_Amd_0001.pdf | ||
| 2025-05-12 Bid Questions (002).pdf | ||
| 12445525B0001 Stony Point Campground QA.pdf | ||
| StonyPt-ElecWater_Specs_v4.pdf | ||
| 2. StonyPt-ElecWater_Drawings_v2.pdf | ||
| DBA_WD_CASS.pdf | ||
| Sol_12445525B0001.pdf | ||
| 1. StonyPt-ElecWater_BidSched.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO.: 12445525B0001
PROJECT: CPF Stony Point Campground OFFEROR NO. 1 OFFEROR NO. 2 OFFEROR NO. 3 OFFEROR NO. 4 OFFEROR NO. 5 OFFEROR NO. 6 OFFEROR NO. 7
Vendor Name: Frontier Services Gustav & Rudy Vendor City/State:
Amendments Acknowledged:
Acceptance Time
DUNS #
Business Size
Bid Guarantee:
Government Estimate
ITEM EST. UNIT EST. UNIT UNIT UNIT UNIT UNIT UNIT UNIT
NO. DESCRIPTION QTY. UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
Mobiliazation 1 LS $85,860.01
$85,860.01 $19,534.00 $19,534.00 $58,181.95 $58,181.95 $6,430.00 $6,430.00 $65,000.00 $65,000.00 $0.00 $0.00 $121,355.05 $121,355.05 $80,000.00 $80,000.00
DIVISION 1 - GENERAL
REQUIREMENTS 1 LS $34,779.45 $34,779.45 $162,083.00 $162,083.00 $217,437.84 $217,437.84 $104,957.00 $104,957.00 $123,394.00 $123,394.00 $0.00 $0.00 $249,757.48 $249,757.48 $126,865.00 $126,865.00
PUMPHOUSE BUILDING 1 LS
$148,925.00
$148,925.00 $57,455.00 $57,455.00 $88,222.95 $88,222.95 $268,878.00 $268,878.00 $186,730.00 $186,730.00 $0.00 $0.00 $272,070.48 $272,070.48 $260,338.00 $260,338.00
ELECTRIC SYSTEM
REPLACEMENT
1 LS
$347,712.56
$347,712.56 $341,462.00 $341,462.00 $378,145.10 $378,145.10 $371,417.00 $371,417.00 $280,700.00 $280,700.00 $0.00 $0.00 $391,655.48 $391,655.48 $235,592.00 $235,592.00
WATER SYSTEM REPLACEMENT
1 LS
$349,657.50
$349,657.50 $533,177.00 $533,177.00 $679,859.13 $679,859.13 $335,906.00 $335,906.00 $68,376.77 $68,376.77 $0.00 $0.00 $458,656.24 $458,656.24 $275,000.00 $275,000.00
WELLHOUSE DEMO & WATER
WELL ABANDONMENT 1 LS
$12,305.00 $12,305.00 $13,630.00 $13,630.00 $17,620.97 $17,620.97 $155,681.00 $155,681.00 $24,500.00 $24,500.00 $0.00 $0.00 $20,836.46 $20,836.46 $28,500.00 $28,500.00
Total $979,239.52 $1,127,341.00 $1,439,467.94 $1,243,269.00 $748,700.77 $0.00 $1,514,331.19 $1,006,295.00
TOTAL Bid $979,239.52 $1,127,341.00 $1,439,467.93 $1,243,269.00 $748,700.77 $887,480.00 $1,514,331.09 $1,006,295.00
Yes Yes
R B National LTD Company
YesYes
Yes No
Black Ridge Construction
Yes Yes
Twin Pines Construction
Tunheim Mckenzie Construction
Yes Yes Yes
Yes YesNo
File details come from the government source that posted it. Updated .