Michigan River Bridge Replacement Federal contract opportunity
Solicitation number
1240LT22R0056
Issued by
Department of Agriculture Forest Service

About this file

This solicitation notice seeks proposals for the Michigan River Bridge Replacement project to remove a temporary bridge and install a new bridge on National Forest System Road 792.1 near Gould, Colorado. The project is estimated to cost between $250,000 and $500,000, and will be conducted by the USDA Forest Service Medicine Bow-Routt National Forests and Thunder Basin National Grassland. Interested contractors must be registered in the System for Award Management to be considered for award. Proposals are due as outlined in the solicitation, which is accessible on the provided website. The project location, scope of work, and technical specifications are further defined in the attachments.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1063090

USDA-FS CSA INTERMOUNTAIN 8

ATTN PEGGY DOBIE

216 NORTH COLORADO STREET

GUNNISON CO 81230

40LT

Peggy Dobie ann.dobie@usda.gov

ANN DOBIE 970-901-7292

1x 05/31/2022

1240LT22R0056

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Medicine Bow and Routt National Forests

Project Name: Michigan River Bridge Replacement

Project Location: Project Vicinity Map included with Attachment 2 -Plans and Drawings. Refer to Section J. The Michigan River Bridge located on National Forest System Road 792.1, south of Highway 14 near Gould, Colorado.

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 455 calendar days and complete it within ________________ ________________ calendar days after receiving

06/21/2022

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA-FS CSA INTERMOUNTAIN 8

ATTN PEGGY DOBIE

216 NORTH COLORADO STREET

GUNNISON CO 81230

40LT

ANN DOBIE

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 56

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

1240LT22R0056

Delivery Location Code: 82BF

USDA FS

PARKS RANGER DISTRICT

P O BOX 158

WALDEN CO 80480 US

Period of Performance: 07/05/2022 to 09/30/2023

0001 Michigan River Bridge Replacement

Product/Service Code: Y1LB

Product/Service Description: CONSTRUCTION OF

HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation No: 1240LT22R0056 Page 4 of 56 Project Name: Michigan River Bridge Replacement

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

B.2 SCHEDULE NOTES

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATION

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

C.4 TECHNICAL SPECIFICATIONS

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

452.215-73 Post Award Conference (NOV 1996)

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

H.2 OTHER REQUIREMENTS

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND

OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

Solicitation No: 1240LT22R0056 Page 5 of 56

K.1 PROVISIONS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS...49

L.1 PROVISIONS

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 PROPOSAL EVALUATION

Solicitation No: 1240LT22R0056 Page 6 of 56

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

ITEM

NO. DESCRIPTION PAY UNIT EST.

QTY

UNIT

PRICE

TOTAL

PRICE

15101 Mobilization Lump Sum 1 $ $ 15201 Construction Survey and Staking Lump Sum 1 $ $ 15401 Contractor Testing Lump Sum 1 $ $

15713 Dewatering And Soil Erosion and Pollution Control Lump Sum 1 $ $

20301 Removal Of Existing Bridge and Salvage, Disassemble, Transport and Unload Government-Furnished ACROW Work Bridge

Lump Sum 1 $ $

20801 Structure Backfill Cubic Yard 85 $ $ 20804 Structure Excavation Lump Sum 1 $ $ 25101 Placed Riprap, Class 3 Cubic Yard 156 $ $

30208 Crushed Aggregate, Surfacing, Compaction Method 1 Cubic Yard 29 $ $

55220A Precast Concrete Member, Backwall Cubic Yard 2 $ $ 55220B Precast Concrete Member, Wingwall Each 4 $ $ 55220C Precast Concrete Member, Pile Cap Each 2 $ $ 56702 Micropiles Each 12 $ $ 56703 Micropile Load Verification Test Each 1 $ $ 56704 Micropile Proof Load Test Each 2 $ $

57101 Steel Prefabricated Bridge Superstructure, Furnish, Fabricate, Transport and Install

Lump Sum 1 $ $

62504 Seeding, Dry Method With Mulch Lump Sum 1 $ $

63306 Posts, Wood Linear Feet 40 $ $

63307 Object Marker, Type 3 Each 4 $ $

TOTAL $

B.2 SCHEDULE NOTES

a) Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

Include bond payments under 151.01 Mobilization.

b) Payment will be made on actual work performed as described in FP-14 109.01 unless otherwise noted.

c) One award will be made from this solicitation, contractors must submit pricing for all items.

Solicitation No: 1240LT22R0056 Page 7 of 56

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

Project Summary:

The Medicine Bow-Routt National Forests and Thunder Basin National Grassland intends to issue a solicitation for the removing of temporary ACROW bridge single reinforced single land truss bridge and install a single span steel beam superstructure with timber running planks and micropile foundation on National Forest System Road (NFSR) 792.1 -0.1 over South Fork Michigan River near Gould in Jackson County, Colorado (latitude 40.501970°, longitude - 106.022007°).

This visit is being conducted prior to solicitation as the site is expected to be inaccessible prior to the actual solicitation and award of the project. This is not a solicitation and in no way commits the Government to award a contract. The Government does not intend to award a contract(s) based solely on this site visit nor does it intend to pay for any costs incurred in response to this announcement. The intent of this notice is to ensure that prospective vendors may see the site and proposed work prior to heavy snowfall and issuing the solicitation.

Michigan River Bridge Project:

The work anticipated but is not limited to traffic control; dewatering and rewatering of the channel; culvert removal; clearing and grubbing; soil erosion and sediment control; installation of a single span steel beam superstructure with timber running planks and micropile foundation; construction of minor channel structures and bank protection. This project will be installing construction waring (traffic control) signs. The road will be closed during construction.

The delivery location for temporary ACROW bridge is located at the Forest Service Yard in Steamboat Spring, Colorado (latitude 40.489571, longitude -106.847317). The contractor will be responsible for the transport and delivery of the existing bridge to the Forest Service Yard.

The work anticipated under any contract resulting from the solicitation will be started as soon as conditions on-the-ground are favorable for the prosecution of the work next spring (estimate early June 2022 starting date).

C.2 PROJECT LOCATION

Project Vicinity Map included with Attachment 2 – Drawings -Plans. Refer to Section J. The Michigan River Bridge located on National Forest System Road 792.1, south of Highway 14 near Gould, Colorado.

The Parks Ranger District office is located at: 100 Main Street, Walden, CO 80480.

Solicitation No: 1240LT22R0056 Page 8 of 56

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

Between $250,000 and $500,000

C.4 PERIOD OF PERFORMANCE

The project contract duration is estimated to have period of performance [POP] of 365 calendar days from the issuance of the Notice to Proceed [NTP].

Contract time includes delays for weather, locating and transporting supplies and materials, and final site cleanup.

Construction shall be completed by September 2023.

C.5 TECHNICAL SPECIFICATIONS

A. Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects. FP-14 U.S. Department of Transportation, “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects: FP-14 U.S. Customary Units,” hereafter referred to as FP-14, are included by reference and are applicable to this project and are hereby made a part of this solicitation and any resultant contract. The specifications are included by reference and the full specifications are available at the following website:

http://flh.fhwa.dot.gov/resources/pse/specs/fp-14.htm.

B. Forest Service Supplemental Specifications [FSSS] Forest Service Supplemental Specifications [FSSS] that augment and/or amend FP-14 is included in this solicitation and resulting contract. Included as Attachment 1. Refer to Section J.

C. Drawings-Plans Project Plans for MICHIGAN RIVER BRIDGE REPLACEMENT sheets 1-17. Includes as Attachment 2. Refer to Section J.

The requirements contained in these listed specifications are hereby made a part of this solicitation and any resultant contract.

Note that the specification list includes the major specifications applicable to this project. Other specifications referred to within these specifications (even though not specifically listed herein) are also fully applicable to this request for proposals and any resultant contract/task order.

A detailed “Work Schedule Plan” and “Traffic Plan” will be required prior to start of work.

http://flh.fhwa.dot.gov/resources/pse/specs/fp-14.htm

Solicitation No: 1240LT22R0056 Page 9 of 56

C.6 EQUIPMENT AND MATERIALS

All equipment shall be suitable for the purpose intended and shall meet all requirements of the Occupational Safety and Health Act. The Contracting Officer may order the removal or require the replacement of any unsatisfactory equipment.

All vehicles and machinery operating on or from the traveled way or road shoulder shall have flashing lights or rotary beacons operated continuously while work is in progress. All equipment shall be equipped with a standard slow-moving vehicle emblem. Truck headlights shall be on while operated. Backup warning devices shall be required on self-propelled equipment in excess of 8,000 pounds gross vehicular weight. Vehicles and machinery not currently used in maintenance operation shall be parked off the traveled way at the approved location to minimize interference with normal use of the road.

C.6.1 Equipment Cleaning & Weed-Free Certification To prevent the introduction of seeds of noxious weeds onto National Forest land, the Contractor shall ensure all equipment moved onto National Forest land is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Contractor shall employ whatever cleaning methods necessary to ensure compliance with this provision and shall notify the Forest Service prior to moving each piece of equipment onto National Forest land. Upon request of Forest Service, arrangements will be made for Forest Service to inspect each piece of equipment prior to being moved onto National Forest land. If the project area is known to contain noxious weeds, the equipment shall be cleaned before moving to other Forest Service system lands which do not contain noxious weeds.

If operating in areas known to contain noxious weeds, the contractor shall ensure that prior to moving from one on-forest location to another part of the project area, all off-road equipment is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds.

Contractor shall certify in writing to the Contracting Officer that off-road equipment is free of noxious weeds prior to each start-up of operations and for subsequent moves of equipment to other project areas. Measures taken to ensure that off-road equipment is free of noxious weeds will be identified. “Off-road equipment” includes all equipment operating off paved roadways. A Current list of noxious weeks of concern to Forest Service is available at the Forest Supervisor’s office. Contractor shall employ whatever cleaning methods are necessary to ensure that off-road equipment is free of noxious weeds. Equipment shall be considered free of soil, seeds, and other such debris when a visual inspection does not disclose such material.

Disassembly of equipment components or specialized inspection tools is not required.

Contractor shall notify Forest Service at least 24 hours prior to beginning of work in area designated as a noxious weed area, unless otherwise approved by CO. Notification shall include the location of the equipment’s most recent operations. If the prior location of the off-road equipment cannot be identified, Forest Service may assume that it was infested with noxious weed seeds. Upon request by the Contracting Officer, the Contractor must make arrangement for inspection of each piece of off-road equipment prior to it being placed into service. If

Solicitation No: 1240LT22R0056 Page 10 of 56

Contractor desires to clean off-road equipment on National Forest land, such as at the end of a project or prior to moving to a new unit that is free from noxious weeds, Contractor and Contracting Officer shall agree on methods of cleaning, locations for the cleaning, and control of off-site impacts, if any. New infestations of noxious weeds within the project area or on the haul route, shall be promptly reported by the Contractor or Forest Service.

All off-road equipment used on this project shall be washed before moving into the project area so that the equipment is free of soil, seeds, vegetative material, or other debris that could contain or hold seeds of noxious weeds. “Off-road equipment” includes all logging and construction equipment and such brushing equipment as brush hogs, masticators, and chippers; it does not include log trucks, chip vans, service vehicles, water trucks, pickup trucks, and similar vehicles not intended for off-road use.

Contractor shall clean all vehicles and equipment before entry into the District unless Forest Service waives the cleaning requirement in writing. Thereafter, all vehicles and equipment that leave the district must be cleaned prior to their reentry unless waived by the Forest Service. All cleaning of vehicles or equipment shall be done at sites agreed to by Forest Service and the Contractor. Forest Service shall inspect all equipment prior to entry, as appropriate and determined necessary. Cleaning shall include the removal of soil by steam cleaning or use of high-pressure water spray.

Equipment will be considered clean when visual inspection does not reveal soil, seeds, plant material, or other such debris. Disassembly of equipment components or specialized inspection equipment is not required. Contractor shall notify the Contracting Officer at least five days in advance of moving equipment in so that arrangements can be made for inspection.

All heavy equipment shall be cleaned and thoroughly inspected prior to mobilization to the work site. Once on site all equipment shall be inspected daily and all visible oil, grease, and hydraulic fluid will be removed. Needed repairs will be implemented immediately before resuming work.

C.6.2 Storage.

The contractor’s material and equipment storage site shall be determined at the pre-construction meeting. The area shall be kept clean and free of litter.

The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Government is not responsible for loss of or damage to materials or supplies stored on-site during performance of this contract.

C.6.3 Loss, Damage, or Destruction.

Equipment Furnished with Operator. The Government shall not be liable for loss, damage, or

Solicitation No: 1240LT22R0056 Page 11 of 56 destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.

Other. Even though this contract may provide for performing services at the direction of Government personnel, the contract is not for personal services, and neither the Contractor nor his or her personnel are Government employees. The Government assumes no liability for injury occurring to Contractor personnel or to third parties, or for loss, damage, or destruction involving third parties' property as a result of the Contractor's operation. Except that the Government is liable for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) acting within the scope of their employment.

C.7 LANDSCAPE PRESERVATION

The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements.

A. The Contractor shall confine operations to within clearing limits or other areas designated in contract

B. documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the clearing limits shall repaired as directed by the Contracting Officer.

C. Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems and impoundments (lakes, reservoirs, etc.)

D. Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

E. Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

F. Prevention of Oil Spills – If the Contractor maintains storage facilities for oil or oil products on project Area, appropriate preventive measures shall be taken to ensure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual States.

G. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

Solicitation No: 1240LT22R0056 Page 12 of 56

C.8 SPECIAL CONDITIONS OR RESTRICTIONS AFFECTING THE WORK

C.8.1 Local Disposal Site Excess or unsuitable material excavated can be disposed at locations identified by the COR in the field.

C.8.2 Existing Physical Conditions The indications of physical conditions on the drawings and in the specifications are the result of site investigations and surveys performed by the Government. It is the Contractor’s responsibility to verify all dimensions and conditions related to this project/contract before proceeding with the work. All dimensions must be verified and/or determined in the field.

Protect all improvements including existing culverts, signs, and roadway from damage during construction.

C.8.3 Weather.

Low temperatures at the project sites range from temperatures of less than 5 ºF in December and January to lows of 45 ºF in July and August. High temperatures range from 25 ºF in December and January to over 70 ºF in July and August. The annual precipitation at the project sites varies from less than 12 inches per year including snow fall in the valley to several feet of snow in the mountains. Winter snowstorms and freezing temperatures will occur during the winter months that result in a winter project shutdown at higher elevations. Icy conditions on local roads and highways can occur during the fall, winter, and spring. Highway curves in shaded areas will remain covered with ice or frost for weeks. The project location may have a winter shutdown.

Adverse Weather. When the Contracting Officer or Contracting Officer’s Representative [COR] determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable damage.

Weather conditions suitable for road access are normally expected from June through October. Snow, sometimes heavy, is normal throughout the winter, with periods of rain during warmer weather.

C.8.4 Hours of Operation / Work Hour Limits.

Construction activity / contractor’s hours of operation shall be limited to Sunrise to Sunset No work will be allowed on federal holidays without written approval by the COR and CO. Dogs and pets are not allowed on the project site at any time.

C.8.5 Permits, Notifications, and Approvals.

The Contractor shall apply for and obtain all required permits and approvals from state or local authorities having jurisdiction over the work to be performed under this Statement of Work and associated task order award.

Solicitation No: 1240LT22R0056 Page 13 of 56

Highway Permits. Contractor is responsible for securing any overload or over width limit permits required for the transport of materials or equipment to the project site. The Contractor is responsible for conducting a thorough reconnaissance of all routes leading to the site.

Burning Permits. Contractor is subject to all rules and regulations governing the onsite burning of slash and other debris. Contractor shall obtain a burning permit from the jurisdiction having control over burning.

C.8.6 Archaeological or Historical Sites Location of known archaeological, historic, or pre-historic materials--such as Amerind artifacts and/or historic mining, logging, or fur trapping remains protected by the American Antiquities Act (l6 USC 433) --will be identified for the contractor before work commences.

C.8.7 Project Site Clean-up Project site cleanup includes the removal and proper disposal of all construction trash, debris, and residue off of National Forest Land.

All spills of petroleum products including leak spots from parked vehicles shall be removed and properly disposed according to all Local, State, and Federal rules, regulations, and laws governing such disposal.

During the work, the Contractor is required to furnish dumpsters or other trash receptacles and to empty such containers either as they become full or weekly, whichever is more frequent. The Contractor shall not place materials of any kind into private or Government trash bins or dumpsters.

All non-salvageable items and trash shall be hauled off the grounds and disposed of in accordance with applicable state and local regulations. Items shall be transported in tarp-covered and closed vehicles.

C.8.8 Other / General.

Water. TBD.

Toilets. No toilet or shower facilities are available on site. Contractor shall provide toilet facilities for its employees.

Camping. Camping is not permitted in US Forest Service campgrounds. Contractor may be permitted to camp elsewhere on US Forest Service land. Contractor must request a permit from the Ranger District Office. Camping on Forest Service land is not a right; permission may be revoked for failure to comply with the terms of the permit.

Contractor may use a self-contained travel trailer or recreational vehicle to camp on National

Solicitation No: 1240LT22R0056 Page 14 of 56

Forest System lands near the project sites subject to the approval of the Contracting Officer. All waste material must be transported off-site to a station equipped to handle such waste.

Site Security. Contractor is responsible for the Contractor's equipment and materials supplied to the site. All equipment not equipped with a key lock system shall be secured in such a manner as to make it inoperable to the average person at the end of each working day. All hand tools and other equipment shall be secured at the end of each working day. On Fridays all construction debris, trash, and refuse shall be properly stored in dumpsters or trash bins or removed from the site.

Protection of Resources. Contractor shall thoroughly clean all equipment prior to delivery to the project site to remove weeds, mud, grease and oil buildup from the tires, wheels, tracks, engines and engine compartments, and other surfaces. Spills of petroleum products and other hazardous substances shall be reported, contained, and removed in accordance with all applicable rules, regulations, and laws. Contractor shall submit a project spill response plan at the pre-work meeting for review by the Contracting Officer.

Protection of Existing Improvements. Contractor shall repair any roads damaged by their operations in accordance with FAR 52.236-9, and at the direction of the Contracting Officer.

Safety, Emergency Communications and Evacuation. Contractor is responsible for the safety of the Contractor's employees including Subcontractors employees, Government employees associated with the project, and any visitors to the site both Government and private. The Contractor shall submit a project safety plan to the Contracting Officer for review prior to commencement of Work. The project safety plan shall comply with the appropriate California OSHA and Federal OSHA rules and regulations and must include a medical evacuation and emergency communications plan.

Solicitation No: 1240LT22R0056 Page 15 of 56

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award.

The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

Solicitation No: 1240LT22R0056 Page 16 of 56

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

Solicitation No: 1240LT22R0056 Page 17 of 56

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

52.211-18 Variation in Estimated Quantity (APR 1984) 52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than August 30, 2023. The time stated for completion shall include final cleanup of the premises.

Solicitation No: 1240LT22R0056 Page 18 of 56

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held on: MS TEAMS

G.2 FOREST SERVICE REPRESENTATIVES

Contract Specialist (CO) Name: Peggy Dobie Address: 216 North Colorado Street, Gunnison, CO 81230 Email: ann.dobie@usda.gov Phone: 970-901-7292

Contracting Officers Representative (COR) Name: Rebekah Dodez Address: 2468 Jackson Street, Laramie, WY 82070 Email: rebekah.dodez@usda.gov Phone: 307-745-2413 Cell: 909-453-7216

G.3 INVOICES & PAYMENTS

All invoices are to be submitted via the electronic Invoice Processing Platform (IPP) System.

https://www.ipp.gov/index.htm

Register: https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account.

These items must be uploaded as Attachments:

Itemized invoice (must include) Name and address of the Contractor (include phone number, mailing address, person to notify if there are issues with the invoice.)

Invoice date and invoice number Contract number Taxpayer Identification number Description, unit, and price of items being invoiced, Date of services or completion.

Shipping and Payment Terms

Certified payrolls for Construction: Contractor and all subcontractors.

Final Payment - Following completion and acceptance of the work (including return of mailto:ann.dobie@usda.gov mailto:rebekah.dodez@usda.gov https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollment-vendors.htm

Solicitation No: 1240LT22R0056 Page 19 of 56

Government-furnished property and site cleanup), Final payment will made within 30 calendar days after presentation of a properly executed invoice. Final payrolls shall be marked “Final”.

Contractor Notification & Release of Claims (FS-6300-16) for Final Payment A contractor notification and release of all claims form shall be completed by the COR and the contractor. The completed form shall be uploaded as an attachment with the Final Payment.

Solicitation No: 1240LT22R0056 Page 20 of 56

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

452.228-71 INSURANCE COVERAGE (NOV 1996)

Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance.

Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

452.236-72 USE OF PREMISES (NOV 1996)

(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.

Solicitation No: 1240LT22R0056 Page 21 of 56

(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.

452.236-73 ARCHAEOLOGICAL OR HISTORIC SITES (FEB 1988)

If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.

452.237-74 KEY PERSONNEL (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel: Project Foreman, or On-Site Supervisor

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

H.2 OTHER REQUIREMENTS

CONTROL OF EROSION, SEDIMENTATION, AND POLLUTION

(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

(b) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other

Solicitation No: 1240LT22R0056 Page 22 of 56 means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

(c) Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.

Solicitation No: 1240LT22R0056 Page 23 of 56

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses:

https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:

https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to clauses may be viewed at:

https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity

(MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform

Employees of Whistleblower Rights (JUN 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY

2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment (NOV 2021) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

Solicitation No: 1240LT22R0056 Page 24 of 56

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (NOV 2021)

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-9 Small Business Subcontracting Plan (NOV 2021) 52.219-10 Incentive Subcontracting Program (OCT 2014) 52.219-14 Limitations on Subcontracting (SEP 2021)

☐ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.

52.219-16 Liquidated Damages --Subcontracting Plan (SEP 2021) 52.219-28 Post Award Small Business Program Representation (SEP 2021) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY

2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-54 Employment Eligibility Verification (NOV 2021) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN

2022)

Solicitation No: 1240LT22R0056 Page 25 of 56

52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction

Contracts (SEP 2013) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT

2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)

Alternate I (NOV 1991) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.242-5 Payments to Small Business Subcontractors (JAN 2017) 52.242-13 Bankruptcy (JUL 1995)

Solicitation No: 1240LT22R0056 Page 26 of 56

52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Products and Commercial Services (JAN 2022)

(DEVIATION APR 2020)

52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)

Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984)

Alternate I (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

52.225-9 Buy American Act-Construction Materials (NOV 2021)

(a) Definitions. As used in this clause-

Commercially available off-the-shelf (COTS) item-

(1) Means any item of supply (including construction material) that is-

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace;

and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work.

The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means-

Solicitation No: 1240LT22R0056 Page 27 of 56

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Domestic construction material means-

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States;

or

(ii) A construction material manufactured in the United States, if-

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Solicitation No: 1240LT22R0056 Page 28 of 56

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States.

Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50…