12405B22Q0445 Construction Clauses and Provisions.pdf

PDF 707 KB Posted

Attached to
Countertop Replacements- USDA, ARS, Byron, GA Federal contract opportunity
Solicitation number
12405B22Q0445
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery

View the file

Other files for this federal contract opportunity

Other files attached to Countertop Replacements- USDA, ARS, Byron, GA, newest first.
File Type Posted
Amendment to Change Contractor Quote Submittal Format.pdf PDF
Wage Determination- BYRON GA- Peach County.pdf PDF
Lab Countertop Replacements SOW.pdf PDF
SF1442- 12405B22Q0445.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION 12405B22Q0445

Byron, GA

REPLACE COUNTERTOPS

REPLACE LAB COUNTERTOPS

B - SECTION B - Supplies or Services and Prices/Costs Schedule of Items Clauses C - SECTION C - Description/Specifications/Statement of Work Clauses D - SECTION D - Packaging and Marking Clauses E - SECTION E - Inspection and Acceptance Clauses F - SECTION F - Deliveries or Performance Clauses G - SECTION G - Contract Administration Data Clauses H - SECTION H - Special Contract Requirements Clauses I - SECTION I - Contract Clauses/Provisions Clauses/Provisions J - SECTION J - List of Documents, Exhibits, and Other Attachments

NOTICES

K - SECTION K - Representations, Certifications, and Other Statements of Offerors Provisions L - SECTION L - Instructions, Conditions, and Notices to Offerors or Respondents Provisions M - SECTION M - Evaluation Factors for Award

M. 1 CRITERIA FOR EVALUATING QUOTES

B - SECTION B - Supplies or Services and Prices/Costs Schedule of Items Clauses

B.1 SCOPE OF CONTRACT

The USDA, Agricultural Research Service (ARS) Southeast Area (SEA) Southeastern Fruit & Tree Nut Research Laboratory in Byron, GA has a requirement for Countertop Replacements to include all labor, materials, and supplies to perform the following work to replace countertops in Lab 226, Lab 228, Lab 224, Lab 229, Lab 232 and Lab 233 per the attached SOW. This will be a phased project to minimize research interruption. Due to the extent of deterioration of countertops in Lab 226, this is where work will start.

B.2 SCHEDULE OF ITEMS

CLIN # Description Price/Cost

0001 REPLACE COUNTERTOPS IN LABS 226, 224, 228 229, 232 & 233 $______________________

B.3 PERFORMANCE TIME

Base Item: 60 calendar days after Notice to Proceed is issued.

End of this section

C - SECTION C - Description/Specifications/Statement of Work

C.1 Description of work:

The contractor shall provide all material, personnel, equipment, tools, fuel and other items or services necessary to INSTALL NEW COUNTER TOPS IN LABS 226, 224, 228, 229, 232 & 233 at the USDA, Agricultural Research Service (ARS) Southeast Area (SEA) Southeastern Fruit & Tree Nut Research Laboratory in Byron, GA.

C.2.1 Bonding.

For any award between $35,000 and $150,000 (FAR 28.102-2 (2)(c)) a Payment Bond will be required – SF-25A form available from GSA website in Section J. Payment for bond premiums in accordance with Clause 52.232-5, Payment under Fixed-Price construction contracts, shall not be in addition to the contract price. Proof of ability to obtain a payment bond is a required part of the quote submission. For any award exceeding $150,000, Payment Security shall be provided in accordance with Clause 52.228-15.

C.2.2 Permits and Licenses.

Pursuant to FAR 52.236-7 Permits and Responsibilities, the Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state, and local laws and regulations.

C.2.3 Directives, Instructions and References Only the Contracting Officer shall issue directives/instructions defining the roles and responsibilities and appointment of a Contracting Officer Representative (COR); Location Monitor (LM); Project Manager (PM); Occupational Health & Safety Manager and/or any other functional appointment as deemed necessary for the scope of work.

C.2.4 The Contractor shall manage the total work effort associated with the services required to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality control. The Contractor shall provide a staff with the necessary management expertise to assure performance objectives and standards are met.

The Contracting Officer may at any time require Samples, Material Safety Data Sheets (MSDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.

C.2.5 Management The Contractor shall manage the total work effort associated with the services required to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality control. The Contractor shall provide a staff with the necessary management expertise to assure performance objectives and standards are met.

C.2.6 Service Interruptions/Utility Outages If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the Contracting Officer Representative ten calendar days in advance to allow notification of affected tenants and customers. If the discontinued service is due to an emergency breakdown the Contractor shall notify the Contracting Officer Representative as soon as practicable.

At a minimum, include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.

C.2.7 Key Personnel The Contractor shall confirm to the Contracting Officer the List of Key Personnel and their qualifications provided as part of the quote. The contractor will provide any additional information requested by the Contracting Officer to certify their qualifications.

C.2.8 Employee Requirements The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety and environmental requirements associated with the work they perform. Competent personnel shall be provided as required.

C.2.8.1 OSHA Compliance Contractor must maintain a workplace and ensure that workplace conditions conform to applicable OSHA standards.

C.2.8.3 Employee Conduct Contractor employees and Subcontractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.

C.2.8.4 Employee Appearance The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The Contracting Officer reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for required passes or badges.

C.2.8.5 Removal of Employees The Contractor shall remove from the site any individual whose continued employment is deemed by the Contracting Officer to be contrary to the public interest or inconsistent with the best interests of Agricultural Research Service.

C.3 BioPreferred requirements The Contractor must comply with Sections 9002 of the Farm Security and Rural Investment Act of 2002; the Food Conservation and Energy Act of 2008; and the Agricultural Act of 2014; and the Federal Acquisition Regulation to provide biobased products. The Contractor shall also comply with the clause at FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts contained in Section I. The Contractor shall also comply with the provision at FAR 52.223-1, Biobased Product Certification contained in Section K.

The Contractor shall utilize products and material made from biobased materials (e.g., biobased erosion control materials, biobased composite panels, biobased roof coatings, biobased insulating foam, biobased interior paints and coatings, and biobased wood and concrete sealers). All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR).

The following is an example list of products that may be used in this minor construction contract for which biobased products are available and the designated biobased content. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.

Adhesive and Mastic Removers – 58 percent Asphalt and Tar Removers - 80 percent Asphalt Restorers – 68 percent Carpet – 7 percent Carpet and Upholstery Cleaners – 54 percent and Spot Removers – 7 percent Composite Panels – Acoustical – 37 percent; Interior Panels – 55 percent; Plastic Lumber – 23 percent; Structural Interior Panels – 89 percent; Structural Wall Panels – 94 percent and Countertops and Solid Surface -_ 89 percent Concrete and Asphalt Cleaners – 70 percent Concrete and Asphalt Release Fluids – 87 percent Dust Suppressants – 85 percent Erosion Control Materials – 77 percent Floor Coverings (Non-Carpet) – 91 percent General Purpose Cleaners - 54 percent Hand Soaps and Cleaners – 64 percent Industrial Cleaners – 41 percent Insulating Foam – 7 percent

Leather, Vinyl, and Rubber Care Products – 55 percent Paint- Interior Paints and Coatings, Latex – 20 percent and Oil-based – 67 percent Paint Removers – 41 percent Roof Coatings – 20 percent Wastewater Systems Coatings – 47 percent Water Tank Coatings – 59 percent Wood and Concrete Sealers – Membrane Concrete Sealers- 11 percent and Penetrating Liquids – 79 percent Wood and Concrete Stains – 39 percent

Reporting is required by Sections 9002 of the Food Conservation and Energy Act of 2008 and the Agricultural Act of 2014. The Contractor shall provide quantities, product types and dollar value of any USDA-designated biobased product purchased by the Contractor. This important data shall be submitted to the COR for the current quarter and current contract year. A brief explanation shall include the methodology used to calculate the dollar value of USDA-designated products used or supplied.

The Contractor should also note that USDA-designated biobased products are available for purchase through the AbilityOne Program (formerly known as the Javits- Wagner-O’Day (JWOD) Program). Under this program, members of organizations including the National Industries for the Blind (NIB) and the National Institute for the Severely Disabled (SourceAmerica) offer products and services that are mandatory by Federal agencies. A search of the AbilityOne Program’s online catalog (www.ability.gov) indicated biobased products that include but are not limited to cleaners (glass, hand, and multipurpose), graffiti removers, and sorbents.

C.4 Tools And Equipment.

This is a representative listing of tools and equipment that apply to the various trades. These items are indicative of, but not limited to, those that the Contractor is expected to provide as part of normal overhead cost.

Airlines (drop line) All hand tools Awl Axes Brushes Barricades, Safety Bolt cutters Barrier tape Broom Cable cutters Cable pulling equipment (handheld) Cable pullers/Hoist (handheld) Can Opener Caulking/Yarning Irons Calking Gun Chalk line Chain Saw Chisels Clamps Cleaning Equipment (handheld) Compressor (sized as required to run tools) Conduit bender Crow Bars Dividers Drift Pins Drill, pneumatic Drill, pneumatic bits (up to 1 ¼ dia.)

Drill, Motors (handheld) Drill, Bits Drill, Hole Saw Drill, Rotary hammer (up to 1 ¼ dia.)

Extension Cords Files Fish tapes Gloves Flashlights Floats (handheld) Groover, Pipe (handheld) Hacksaws Hot Tap (handheld) Hammers, hand Hammers, chipping Hammer, Jack Industrial Vacuum and HEPA Vac Jack, Hydraulic (12 tons or less) Knives Ladders (step to 12’ and extension to 24’) Lead Pot and Ladle Levels Levels, Builders Level, laser Lighting, Temporary (up to 6 each) Nailer, Pneumatic Nail Sets Picks Planes (handheld) Planes, Electric (handheld) Pliers Power Actuated Fastening Tools Plumb Bob Pot Hook Personal Protective Equipment Punches Rake Rasps (files) Reinforcing steel, Shear and Bender (handheld) Rivet Sets (Light, handheld) Rollers-Flooring Rules Safety Equipment (Personal Protective Equipment) Safety fencing (orange plastic) Sanders (handheld) Saws, Hand Saws, Electric Hand, Circular Saws, Electric Hand, Reciprocating Saws, Backsaws and Miter Box Saws, Power Miter Box Sawhorses Scaffolding, Portable, (8’table height) Scrapers (handheld) Screw Drivers Screw Drivers, Electric Scribers Shears (handheld) Shovels Sledgehammers Squares Staplers, Air/Hand Steel Framing Tools, Lightweight Steel Framing Tampers (handheld, non-powered) Tapelines Tarpaulins (12’ X 24”, maximum of 5 each) Temporary lighting (400 square feet) Tin Snips Torch, hand Torch Igniters Trash Receptacles (35/gallon, 4 each) Trowels (non-powered, handheld) Toolboxes (personal) Traffic cones

Tubing Cutters (handheld, non-powered) Vacuum, wet/dry (5 gal) Vehicles (up to 1.5 ton) Vice Voltmeter, volt/ohm meter Wheelbarrow (non-powered) Wire Strippers Wrenches

Materials and equipment may not be stored at the jobsite lay down area after work hours unless approved in advance by the Contracting Officer. There will not be office space available at any location. All job site lay down areas are dependent upon the location of the work.

C.4 CONTRACT CLAUSES INCLUDED BY FULL TEXT:

AGAR 452.211-72 Statement of Work/Specifications As prescribed in 411.171, insert the following clause:

Statement of Work/Specifications (Feb 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

(End of Clause)

AGAR 452.211-73 Attachments to Statements of Work/Specifications As prescribed in 411.171, insert the following clause:

Attachments to Statements of Work/Specifications (Feb 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

AGAR452.211-74 Period of Performance.

As prescribed in 411.404(a), insert the following clause:

PERIOD OF PERFORMANCE (FEB 1988)

The period of performance of this contract is as noted in the purchase order.

http://www.dm.usda.gov/procurement/policy/docs/AGAR_Updated_5May2016.pdf

D - SECTION D - Packaging and Marking

(For this Solicitation, there are NO Clauses in this Section)

E - SECTION E - Inspection and Acceptance

E.1 CONTRACT CLAUSES INCLUDED BY FULL TEXT:

AGAR 452.246-70 -- Inspection and Acceptance As prescribed in 446.370, insert the following clause:

INSPECTION AND ACCEPTANCE (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at: Southeastern Fruit and Tree Nut Research Laboratory, 21 Dunbar Road, Byron, Georgia 31008, building 1 (End of clause)

E.2 CONTRACT CLAUSES INCLUDED BY REFERENCE:

FAR 52.246-12 -- Inspection of Construction (Aug 1996)

E.3 FINAL INSPECTION

(a) A final inspection shall be made only when all the materials have been furnished, all the work has been performed, and all the construction provided for by the contract in accordance with the terms has been completed. If, upon examination by the Contracting Officer and/or Government inspection personnel, the project is determined not sufficiently completed to have warranted a final inspection, the contractor may be charged with any additional cost of re-inspection when material and workmanship are not ready at the time specified by the Contractor for its inspection.

(b) The contractor shall give the Contracting Officer ten (10) calendar days advance notice, in writing, of the date the work will be fully completed and ready for final inspection.

(c) The Contractor's request for final inspection will not be approved unless all documentation required below, and all other contract requirements have been provided to the Contracting Officer:

-Guarantees and warranty schedule and contacts -Certified payroll records for all prime and subcontractor employees

(d) As soon as practicable, following final inspection, the Contracting Officer will inform the contractor, in writing, of any discrepancies and/or omissions noted at the final inspection. The Contracting Officer shall also state the time allowable for replacement of material and performance or re-performance of any unsatisfactory work necessary for final acceptance.

E.4 FINAL ACCEPTANCE

Upon written notification that all deficiencies identified during the final inspection have been corrected, the Contracting Officer will schedule a final acceptance inspection of the work. If all construction required by the contract is determined to be complete and all requisite contract deliverables (e.g., certified payroll records, as-built drawings, warranty documents, etc.) have been submitted and approved by the Government, the Contracting Officer shall notify the Contractor in writing of such acceptance. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee

F - SECTION F - Deliveries or Performance

F.1 CONTRACT CLAUSES INCLUDED BY FULL TEXT:

52.211-10 -- Commencement, Prosecution, and Completion of Work.

As prescribed in 11.404(b), insert the following clause in solicitations and contracts when a fixed-price construction contract is contemplated. The clause may be changed to accommodate the issuance of orders under indefinite-delivery contracts for construction.

Commencement, Prosecution, and Completion of Work (Apr 1984) The Contractor shall be required to

(a) commence work under this contract within 14 days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 60 days from notice to proceed. The time stated for completion shall include final cleanup of the premises.

F.2 CONTRACT CLAUSES INCLUDED BY REFERENCE:

FAR 52.242-14 -- Suspension of Work (Apr 1984) http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/11.htm#P198_30162

G - SECTION G - Contract Administration Data

G.1 INVOICE PREPARATION AND SUBMISSION

Based upon acceptance of required contract deliverables, the contractor shall submit an original invoice to the following address:

Email to shalunda.mix@usda.gov The contractor shall include the following information on each invoice in order to be considered a proper invoice:

1. Name and address of contractor.

2. Invoice number and Invoice date.

3. Contract number.

4. Description of work and period of performance.

5. Name, title, phone number, and complete mailing address of official to whom payment is to be sent.

6. Name, title, phone number, and complete mailing address of person to notify in the event of a defective invoice.

7. Taxpayer Identification Number (TIN) and DUNS Number.

8. Invoices must be submitted with ARS-371 and ARS-372, along with certified payroll records, Contractor Certification, and updated CPM Schedule.

Once the paper invoice has been approved by the Contracting Officer, the Contractor shall submit the invoice electronically through the Invoice Processing Platform (IPP) at www.ipp.gov.

mailto:shalunda.mix@usda.gov http://www.ipp.gov/

H - SECTION H - Special Contract Requirements

H.1 CONTRACT CLAUSES INCLUDED BY FULL TEXT:

AGAR 452.236-71 -- PROHIBITION AGAINST THE USE OF LEAD-BASED PAINT

As prescribed in 436.571, insert the following clause:

PROHIBITION AGAINST THE USE OF LEAD-BASED PAINT (NOV 1996)

Neither the Contractor nor any subcontractor performing under this contract shall use paints containing more than 0.06 of 1 percent lead by weight (calculated as lead metal) in the total nonvolatile content of the paint, or the equivalent measure of lead in the dried film of paint already applied, or both.

AGAR 452.236-72 -- USE OF PREMISES

As prescribed in 436.571, insert the following clause

USE OF PREMISES (NOV 1996)

(1) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, written permission shall be obtained through the Contracting Officer. A camp is interpreted to include the camp site or trailer parking area of any employee working on the project for the Contractor.

(b) Unless excepted elsewhere in the contract, the Contractor shall(i)provide and maintain sanitation facilities for the workforce at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.

AGAR 452.236-74 Control of Erosion, Sedimentation, and Pollution.

As prescribed in 436.574, insert the following clause:

CONTROL OF EROSION, SEDIMENTATION, AND POLLUTION (NOV 1996)

(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

(b) Pollutants such as fuels, lubricants, bitumen’s, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

(c) Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.

AGAR 452.237-74 -- KEY PERSONNEL (FEB 1988)

(a) The contractor shall assign to this contract the following key personnel:

Title(s): Name(s):

Site Superintendent

(b) During the first ninety (90) days of performance, the contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-period, the contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the person(s) being replaced. The Contracting Officer will notify the contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

(End of Clause) http://www.dm.usda.gov/procurement/policy/docs/AGAR_Updated_5May2016.pdf

H.2 CONSTRUCTION PROGRESS AND PAYMENT SCHEDULE

(a) Within 14 days after the date of receipt of award, the contractor shall prepare and submit to the Contracting Officer for approval, the original copy of ARS Form 371, Construction Progress and Payment Schedule. This form will serve as a Schedule of Estimates, Progress Schedule, and when used with ARS Form 372, it will be the basis for Requests for Partial Payment. The values employed in making the schedule will be used only for determining partial payments and will not be considered as establishing a basis for additions to or deductions from the contract. A copy of the approved schedule will be returned to the contractor.

(b) Samples of both ARS Forms 371 and 372 are available upon request. A supply of these forms together with instruction for completion of ARS Form 371 will be mailed to the contractor with the Notice of Award.

(c) ARS Form 371 is required even though progress or partial payments are not requested.

(d) The need by an offeror for partial or progress payments, when authorized in the payment provisions of this request for quotes, will not be treated as a handicap in making the award.

H.3 UTILITIES OUTAGE

Any interruption of utilities or services that would interfere with the operation of the facility will be permitted only with prior written approval from the Contracting Officer. Any utilities or service connections made at other than normal working hours will be at no additional cost to the Government.

Permission to make such an interruption shall be requested in writing to the Contracting Officer, at least three (3) days prior to the day of interruption. Failure by the Contractor to comply with this requirement will cause the Contractor to be subject to liability for actual damages.

H.4 COOPERATION WITH OTHER CONTRACTORS

During the period of construction for the work covered by this contract, other contractors performing work for the Government may be operating concurrently at the site. To minimize interference and delay to the construction progress of all concerned, all contractors shall cooperate with each other and coordinate their construction operations to the fullest extent. As far as practicable, all contractors performing work for the Government at the site shall have equal rights to the use of all referenced facilities. In a dispute regarding the use of such facilities, the matter shall be referred to the Contracting Officer.

H.5 SUBMITTALS AND SHOP DRAWINGS

(a) The Contractor shall submit for approval, shop drawings of all manufactured products required in the construction for which such drawings are hereinafter required. When approved, one set will be retained;

one set forwarded to the Government representative on the job and two sets forwarded to the Contractor.

When changes or corrections are necessary, two sets will be returned to the Contractor with such corrections noted thereon, and he shall resubmit revised prints.

(b) Shop drawings shall be marked with the contract number and Work Order Number, project description, name of the Contractor, and accompanied by a letter of transmittal. If the shop drawings show variations from the contract requirements because of standard shop practice or other reason, the Contractor shall make specific mention of such variations in his letter of transmittal.

(c) Approval of shop drawings will be general and will not relieve the Contractor from the responsibility of furnishing material and work required by the contract.

(d) Shop drawings shall be submitted for approval in ample time to permit checking of the drawings, allow the Contractor to make any corrections and resubmit drawings prior to the time construction is started on work covered by any drawings.

(e) Non-approval of equipment due to failure to meet specifications, or non-approval of the Contractor’s drawings due to submission of incomplete or incorrect information cannot be considered as a basis for extension of time for completion of the contract.

(f) The quantity of shop drawings required are subject to change. This will occur only when the Government is under contract with an A-E firm to approve shop drawings. In this respect, A-E will coordinate final quantity required between all interested parties.

H.6 LIST OF MATERIALS

(a) The Contractor shall submit for approval a complete list, in duplicate, of brands, type, and make of various equipment and materials proposed to be used. If the Contractor fails to submit such a list, or names of equipment which does not comply with the specifications, or if the manufacturers named are unsatisfactory, the Government reserves the right to reject same and to select satisfactory substitute materials. This selection shall be final and finding upon the Contractor, and the work shall be installed on this basis without change in contract price.

(b) In order to properly identify and to prove compliance with the requirements of the specifications, the Contractor shall give the following data for each product included in the list of materials.

Section heading of the specifications under which material is specified.

Manufacturer’s name and address.

Grade, type, trade or catalog number.

Size, capacity, and other pertinent data.

(c) All materials, fixtures, and equipment furnished and installed under this contract shall be new and of the best quality; shall be standard cataloged products or reputable manufacturers products or of special manufacture, satisfying completely the contract requirements.

(d) Similar items, unless otherwise specified herein or approved by the Contracting Officer, shall be the product of the same manufacturer, and those fulfilling the same requirements as to size and construction shall be identical.

(e) Substitutions and/or Approved Equal: Where particular make, brand or type of material or equipment is mentioned in these specifications, it is to denote quality standard of article desired, but does not restrict contractor to brand specified; however, any substitution must be met with approval of the Contracting Officer. Other products comparable in type, quality, utility, and price are acceptable if approved by the Contracting Officer. Burden of proof of equality shall rest with the Contractor. The Contracting Officer shall be sole judge of paralleled quality.

H.7 PROPERTY DAMAGE LIABILITY INSURANCE

The Contractor shall ensure that the property damage liability insurance policy (or rider) required by FAR 52.228-5, Insurance-Work on a Government Installation, is in full compliance with all the terms and conditions of this contract. The policy shall not contain any exclusions or exceptions that would limit or adversely affect the Government’s rights and remedies under any other clause in this contract or other Federal regulation or law. Should there be any exclusions or exceptions contained in the policy that limits or adversely affects the Government’s rights, the Contractor shall be responsible for the full amount of any damages that occur to the immediate facilities, adjacent facilities/property, and other Government property under the control of the Contractor due to fraud, negligence, vandalism, willful misconduct, or violation of Federal, state, or local safety regulations, building codes and laws. The Contractor shall have full responsibility and is liable for these facilities and properties until the Government has accepted the contract as being completed in full and a release from claims has been received from the Contractor.

For those areas where the Government has taken "beneficial occupancy" prior to completion and acceptance of the whole contract, the contractor shall not be responsible for those specific areas under Government control, except in such instances where damage occurs to those areas as a result of negligence, fraud, vandalism, willful misconduct, or violation of Federal, state, or local safety regulations, building codes, or laws in those areas under the control of the Contractor.

This liability and responsibility includes the activities of all the Contractor’s personnel, their subcontractors and suppliers.

H.8 SUBCONTRACTORS, OUTSIDE ASSOCIATES AND CONSULTANTS

Any subcontractors, outside associates or consultants required by the Contractor in connection with the services covered by the contract will be limited to individuals or firms that were specifically identified at time of award or agreed upon during negotiations. The Contractor shall obtain the Contracting Officer’s written consent before making any substitution for these individuals or firms.

I - SECTION I - Contract Clauses/Provisions Clauses/Provisions

I.1 CONTRACT CLAUSES INCLUDED BY FULL TEXT:

FAR 52.222-36 – Equal Opportunity for Workers With Disabilities

As prescribed in 22.1408(a), insert the following clause:

Equal Opportunity for Workers With Disabilities (Jul 2014)

(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60.741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.

(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of $15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.

FAR 52.223-20 – Aerosols.

As prescribed in 23.804(a)(3), insert the following clause:

Aerosols (Jun 2016)

(a) Definitions. As used in this clause-- “Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide’s global warming potential is defined as 1.0.

“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G. with supplemental tables of alternatives available at http://www.epa.gov/snap/).

“Hydrofluorocarbons” means compounds that contain only hydrogen, fluorine, and carbon.

(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, or emissions of high global warming potential hydrofluorocarbons, when feasible, from aerosol propellants or solvents under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as--

(1) In-use emission rates, energy efficiency;

(2) Safety, such as flammability or toxicity;

(3) Ability to meet technical performance requirements; and

(4) Commercial availability at a reasonable cost.

(c) The Contractor shall refer to EPA’s SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap/.

FAR 52.223-21 Foams.

As prescribed in 23.804(a)(4), insert the following clause:

Foams (Jun 2016)

(a) Definitions. As used in this clause– “Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide's global warming potential is defined as 1.0.

“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82 subpart G with supplemental tables of alternatives available at http://www.epa.gov/snap/.

“Hydrofluorocarbons” means compounds that contain only hydrogen, fluorine, and carbon.

(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, and emissions of high global warming potential hydrofluorocarbons and refrigerant blends containing hydrofluorocarbons, https://www.acquisition.gov/?q=/browse/far/22 http://farsite.hill.af.mil/reghtml/Regs/far2afmcfars/fardfars/Far/23.htm#P364_49080 http://www.epa.gov/snap/ http://www.epa.gov/snap/ https://www.acquisition.gov/far/html/Subpart%2023_8.html#wp1073926 http://www.epa.gov/snap/ when feasible, from foam blowing agents, under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as–

(1) In-use emission rates, energy efficiency, and safety;

(2) Ability to meet performance requirements; and

(3) Commercial availability at a reasonable cost.

(c) The Contractor shall refer to EPA’s SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82 subpart G with supplemental tables available at http://www.epa.gov/snap/.

http://www.epa.gov/snap/

52.225-9 Buy American-Construction Materials.

(Feb 2021)

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial item (as defined in paragraph (1) of the definition at Federal Acquisition

Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the

Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together.

Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the

United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

https://www.acquisition.gov/far/2.101#FAR_2_101

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

[Contracting Officer to list applicable excepted materials or indicate "none"]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

http://uscode.house.gov/browse.xhtml%3Bjsessionid%3D114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml%3Bjsessionid%3D114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/12.505#FAR_12_505

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description

Unit of Measure

Quantity

Item1:

Foreign construction material

Domestic construction material

Item2:

Foreign construction material

Domestic construction material

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]

AGAR 452.228-71 -- INSURANCE COVERAGE - ALT 1 (NOV 1996)

As prescribed in 428.310, insert the following clause:

Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage.

Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability.

(1) The contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(2) The Contractor shall have property damage liability insurance in the amount of $500,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage covering the operations of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury.

Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

AGAR 452.236-70 Additive or Deductive Items.

As prescribed in 436.205, insert the following provision:

ADDITIVE OR DEDUCTIVE ITEMS (FEB 1988)

The low bidder for purposes of award shall be the conforming responsible bidder offering the low aggregate amount for the first or base bid item, plus or minus (in the order of priority listed in the schedule) those additive or deductive bid items providing the most features of the work within the funds determined by the government to be available before bids are opened. If addition of another bid item in the listed order of priority would make the award exceed such funds for all bidders, it shall be skipped and the next subsequent additive bid item in a lower amount shall be added if award therein can be made within such funds. For example, when the amount available is $100,000 and a bidder's base bid and four successive additives are $85,000, $10,000, $8,000, $6,000, and $4,000, the aggregate amount of the bid for purposes of award would be $99,000 for the base bid plus the first and fourth additives, the second and third additives being skipped because of each of them would cause the aggregate bid to exceed $100,000. In any case all bids shall be evaluated on the basis of the same additive or deductive bid items, determined as above provided.

This is the start of the file's text. The full file is on GovTribe.