This federal solicitation seeks proposals for a new greenhouse construction project. Contractors must provide all labor, supervision, tools, and materials to complete the construction at the USDA Agricultural Research Service facilities in Florence, South Carolina. A mandatory site visit will be held on June 17, 2020, with registration required by June 15. Proposals are due no later than July 7, 2020 and must be emailed to the contracting officer at the specified address. Proposals should include a detailed price breakdown. All questions must be submitted to the contracting officer in writing by June 22. The amendment provides answers to initial questions about specifications such as framing materials, controls, lighting, and other requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Request for Proposal 12405B20R0016.pdf | ||
| Davis Bacon Wage Determination - Florence County.pdf | ||
| Past Performance Questionnaire.docx | DOCX document | |
| SOW New Greenhouse Construction Florence SC.pdf | ||
| Construction RFP Provisions.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12405B20R0016 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ARS-12405B-1
COLLEGE STATION TX 77845
2775 F&B ROAD
USDA ARS SEA AAO ACQ/PER PROP
06/05/20200001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/05/2020
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to provide answers for questions received by the cutoff date.
All applicable, provisions, clauses, terms and conditions remain unchanged.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
NICHOLAS LANGLEY
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
TEL: EMAIL: Nicholas.Langley@usda.gov
New Greenhouse Construction Florence, SC Questions and Answers
1) Is there a process to be an approved manufacturer? (i.e. alternate to Atlas Greenhouse?).
Answer: The SOW states Atlas, or equal, so your proposal should clearly show that the alternate you are proposing is equal.
2) What are the wind and snow load requirements for Florence? (I think it is 12-130 mph wind load now)
Answer: The greenhouse manufacturer is required to provide stamped/sealed drawings that have been evaluated and determined to meet the wind and snow loads for South Carolina.
3) In the greenhouse description it states that the frame is to be "square aluminum tubing" however, in the detailed greenhouse description galvanized steel framing is discussed. Is the greenhouse frame to be structural steel tubing or aluminum?
Answer: The framing should be galvanized steel and not aluminum
4) If an "equal" greenhouse frame is substituted and is provided with structural plans sealed by a registered SC engineer to meet the required code can the size and gauge of frame members vary from spec?
Answer: Yes
5) Greenhouse controls - Is a Wadsworth Enviro-Step controller required for each zone (2 controllers required)? Will CO2 sensors be required for each zone? Will a software package that allows for remote monitoring be required?
Answer: One controller should provide independent control of both bays of the greenhouse, but sensors should be installed throughout both bays. Software needs would depend on the controller.
6) Hanging basket rails - Drippers for hanging baskets are described in irrigation system. Are suspended hanging basket rails required and if so how many and where are they to be located?
Answer: Hanging basket rails are not required in the SOW.
7) Irrigation System - A Sterling 12-zone irrigation controller is specified. Is one controller sufficient to control both zones?
Answer: Independent controller for each bay.
8) Fertilizer Injector - One fertilizer injector is specified. Is one injector sufficient for both zones?
Answer: A fertilizer injection system and irrigation system are to be provided for each bay.
9) LED grow lights are specified as Zelion HL300. How many lights are required?
Answer: 4 lights per bench for a total of 24.
New Greenhouse Construction Florence, SC Questions and Answers
10) Do you have specifications for the list station required for the drain line? Would it be possible to run the drain line parallel to the current water line and tie into the drain for the pre-existing building shown in attached picture?
Answer: No, if the lift station is required, it should be designed by the contractor. The line that you propose to connect to is 4”. If that is sufficient capacity to tie into, the contractor is free to use it.
11) Do you have a wattage requirement for the emergency backup generator?
Answer: The SOW states that the emergency backup generator should be designed by the contractor to operate 100% of all system components for this greenhouse project.
12) Will the due date/time for proposals be extended?
Answer: No, the due date/time will not be extended.