Attachment 1 Statement of Work (Revised).pdf
PDF 1 MB Posted
- Attached to
- (Amended) Septic Drain Pump and Drain Field Installation for USDA ARS in Pullman, WA Federal contract opportunity
- Solicitation number
- 1232SA25Q0645
About this file
This Statement of Work (SOW) details the replacement of the septic system drain field for the USDA Agricultural Research Service's Palouse Conservation Field Station (PCFS) Building 103 located at 4153 Albion Rd in Pullman, Washington. The project requires a contractor to excavate and install a new drain field in compliance with Whitman County Health Department soil test evaluations, including a licensed on-site sewage (OSS) assessor's tank assessment and a professional engineer's calculations for daily flow rate based on a commercial building with 4 staff, one toilet, two sinks, and one washing machine.
The project scope includes designing and installing a septic pump, pump chamber, and electrical circuit, with all work to be completed within 180 calendar days from the Notice to Proceed. The contractor is responsible for obtaining all necessary permits, protecting existing utilities, maintaining site cleanliness, and providing a minimum one-year warranty on workmanship. The project falls under the Davis Bacon Wage Act and must adhere to federal, state, and local code standards, with the Contracting Officer being Michael Sherlock and the Research Program Representative being Dr. David Huggins.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_1232SA25Q06450001.pdf | ||
| SF1442_RFQ_1232SA25Q0645.pdf | ||
| Attachment 3 Wage Determination WA20250042 08082025.pdf | ||
| Attachment 2 Site Evaluation.pdf | ||
| Attachment 5 ARS Form 372 Request for Payment.pdf | ||
| Attachment 4 ARS Form 371 Construction Progress and Payment Schedule.pdf | ||
| Attachment 1 Statement of Work.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
(Revised August 25,2025)
PCFS Building 103:
Replacement of
Septic System Drain Field
USDA-ARS-NSAR
4153 Albion Rd.
Pullman, WA 99163
Date: August 25, 2025
STATEMENT OF WORK
1.0 CONTRACT PROJECT:
a. Project Title:
PCFS Building 103: Replacement of Septic System Drain Field
b. Project Location:
USDA-ARS-NSAR Unit Palouse Conservation Field Station (PCFS) Building 103 4153 Albion Rd., Pullman, WA 99163
2.0 PROJECT CONTACT PERSONS:
a. CONTRACTING OFFICER (CO):
Michael Sherlock Email: Michael.Sherlock@usda.gov
b. RESEARCH PROGRAM REPRESENTATIVE (RPR):
RL Dr. David Huggins 341 Clark Hall, WSU Pullman, WA 99164-6630 E-mail: david.huggins@usda.gov
c. ADMINISTRATIVE OFFICER (AO):
Richard Partain
USDA/ARS
3 Hulbert Hall, WSU Pullman, WA 99164 Phone: (509) 335-3238 E-mail: richard.partain@usda.gov
d. LOCATION CONTRACTING OFFICER REPRESENTATIVE (COR):
TBD
e. SAFETY OFFICER (SOHS) Ian Guest
USDA/ARS
PCFS Building 105 Pullman, WA 99163 Phone: (509) 334-3180 E-mail: ian.guest@usda.gov mailto:richard.partain@usda.gov mailto:ian.guest@usda.gov
3.0 SCOPE OF WORK
The contractor shall provide all professional services necessary for the accomplishment of the contract project and such required service shall be in accordance with the requirements as described herein and on attached contract documents.
3.1 Background: The USDA/ARS/NSAR Unit USDA Shop (Building 103) is located at PCFS at 4153 Albion Rd. Pullman, WA 99163 and requires the replacement of the septic drain field, to accommodate more staff in the building and address long-standing issues with sewage backing up.
3.2 Contractor shall excavate and install a drain field in compliance with Whitman County Health Department soil test evaluation.
3.2.1 New drainage shall be in the area recommended by the soil test evaluation, behind building 103, to avoid being within 100’ of the well, and to use the most favorable soil.
3.2.2. A licensed OSS assessor shall provide a tank assessment to Whitman County Health Department.
3.2.3 A licensed engineer shall provide calculations of daily flow for the shop building, according to a typical occupancy of a commercial-type building with 4 staff, with one toilet, two sinks, and one washing machine.
3.2.4 New drainage shall be designed to accommodate (by properly designed drainage length and depth) daily flow rate as determined by the calculations of a professional engineer in the soil specified by the Whitman County soil evaluation and tank assessment.
3.2.5 A septic pump, pump chamber, and floats shall be designed and installed to account for change in elevation from main tank to drain field, along with any pump monitoring and filtration required by code. The pump chamber shall be connected to the existing septic tank. The pump chamber shall have a traffic-rated lid. A new electrical circuit shall be installed in Building 103 to power the septic pump. Design shall be submitted to Whitman County Health Department for approval prior to construction.
3.2.6 Utilities shall be located prior to work to avoid damage. Work shall be conducted during normal daily working hours between 8 am and 4:30 pm.
3.2.7 Contractor shall pay any processing/permitting fees required by Whitman County Health Department.
Photos of Building 103 Drain Field Area-
Aerial view of site evaluation. Test Pit #2 is appropriate for OSS.
Upslope area for drain field.
Soil evaluation.
3.3 Contractor will provide materials, labor, equipment and all associated services, including recycling and removal of debris necessary to complete project.
4.0 PROJECT REQUIREMENTS:
a. The Contractor will work with site personnel to ensure project is accomplished in a timely manner.
b. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction and services shall comply with applicable federal, state, and local code requirements as well as current industry standards, (ie: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
c. All work to meet all pertinent Unified Facilities Guide Specifications (UFGS) and ARS 242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.
ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/.
d. This project falls under the DAVIS BACON Wage Act.
4.1 Background & Site Description:
The project site is located at the Palouse Conservation Field Station (PCFS), USDA Building 103, 4153 Albion Rd Pullman, WA 99163.
4.3 Description of Work:
a. The Contractor will provide a turn-key project satisfying all Local, State, and Federal requirements.
b. The Contractor will provide all the necessary materials and labor per
Section 3.0 and properly dispose of all material being replaced.
c. Contractor is responsible for any damage to adjacent equipment and miscellaneous objects that may become damaged during construction. The Contractor is responsible for making repairs to meet or exceed conditions prior to damage.
d. The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided for conditions that would be visible during an on-site visit for persons experienced performing this type of work.
4.4 Government Furnished Equipment\Services
a. The Government does not anticipate the need in this project, but the Government will be available to assist with the identification/location of utilities as necessary.
b. The Government will furnish a reasonable amount of electricity and water.
http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/ https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/
5.0 GENERAL REQUIREMENTS:
5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disturbances that might jeopardize on-going operations and research. Owner reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Owner prior to starting demolition operations. Contractor shall legally dispose all any materials removed that will not be retained.
5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.
5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the COR for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.
5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.
5.6 Protection of Work and Property/Safety Requirements:
a. Contractor shall furnish a Site Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) upon request,10 days after contract award. SSSP / APP shall be reviewed by the Government before construction work commences.
b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.
c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
d. Contractor is responsible for verifying location of any underground utility and is responsible for any damaged caused to such utilities.
5.7 Temporary Facilities:
a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.
b. Should the Contractor require any power or utility shutdowns during construction, the Contractor shall obtain approval for such shutdown from the COR 21 working days prior to the need.
5.8 Materials and Equipment:
a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/COR.
c. Government will not furnish any labor or equipment to unload or move materials or supplies.
5.9 Cleanup: The construction site shall be kept clean and free of debris at all times. Disposal of the old equipment is required. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
5.10 Warranty:
a. Submit data concerning the standard one year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.
b. Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.
5.11 Final Payment/Contract Closeout: The following documents are REQUIRED
PRIOR TO FINAL PAYMENT (other documents may also be required):
a. General contractors minimum one (1) year warranty on work.
b. Operation and Maintenance Data
c. Release of liens.
d. Final Invoice
6.0 PROJECT SCHEDULE: The Contract time for this project is 180 calendar days from Notice to Proceed.