12010919Q0042_2019_JRD_Couverden_Road_Mtc..pdf
PDF 1 MB Posted
- Attached to
- 2019 JRD Couverden Road Mtc. Federal contract opportunity
- Solicitation number
- 12010919Q0042
About this file
Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q&A_for_2019_JRD_Couverden_Road_Mtc.pdf | ||
| 12010919Q0042_0002_AMD.pdf | ||
| 12010919Q0042_0001_AMD.pdf | ||
| Wage_Determination_AK20190006_Dated_Jan_03,2019.pdf | ||
| Daily_Activity_Report.pdf | ||
| FY19_JRD_Rd_Mtce_FSSS.pdf | ||
| JRD_2019_RD_MTCE_MAP.pdf | ||
| JRD_RD_MTCE_FY19.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
951590
ALASKA REGIONAL OFFICE
709 WEST 9TH STREET
JUNEAU AK 99802
MICHAEL MCCARTHY 907-586-7903
105/22/2019
12010919Q0042
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
2019 JRD Couverden Road Mtc.12010919Q0042
The work in this contract is covered by the Davis Bacon Act.
Magnitude of the construction project is between $100,000. and $250,000.
Quotes are due by: 14:00hrs (AS), June 5, 2019
Email Quotes to:
michael.t.mccarthy@usda.gov
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 152 calendar days and complete it within ________________ ________________ calendar days after receiving
06/05/2019
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
12010919Q0042_2019 JRD Couverden Road Mtc.
HUBZone set aside
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
ALASKA REGIONAL OFFICE
709 WEST 9TH STREET
JUNEAU AK 99802
DELLA KOELLING
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
12010919Q0042_2019 JRD Couverden Road Mtc.
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 24
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12010919Q0042
2019 JRD Couverden Road Mtc
Delivery: 05/06/2019
Delivery Location Code: 0116
USDA FOREST SERVICE
TONGASS NF KETCHIKAN AREA FED BLDG
648 MISSION STREET
KETCHIKAN AK 99901 US
FOB: Destination
Period of Performance: 07/01/2019 to 11/30/2019
001 2019 JRD Couverden Road Mtc
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SCHEDULE OF SUPPLIES/SERVICES
Base Items:
Surface Maintenance Item No. Description Quantity Unit Unit Price Amount
20404 - Unclassified borrow, placement method 4, finish method C 150
Cubic Yard $ $
2 20424 – Haul 341.25 Cubic Yard-Mile $ $
3 20204 – Selective clearing, log out 4.55 Mile $ $
4 86101 – Resurface bridge 4,700 Square Foot $ $
80703 – Equipment rental, medium sized excavator w/operator 10 Hour $ $
6 15101 – Mobilization 1 Lump Sum $ $
Total Base $
Option Items: 1 Item No. Description Quantity Unit Unit Price Amount
7.1 20301- Removal of native log stringer bridge 2 Each $ $
7.2 62501 - Seeding, dry method without mulch .07 Acre $ $
Option Items: 2
8 60804 – Construct Hardened stream crossing 2 Each $ $ Total of All Options $
Quoter’s must submit pricing for all items.
This will be a firm fixed price contract.
Vendor Information
Point of Contact: Phone:
Vendor Name: DUNS:
SAM Expiration date: Email:
JUNEAU ROAD MAINTENANCE 2019
1. DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Project Scope: The intent of this contract is to perform specified road maintenance on National Forest System Roads, located on the Couverden Road System, Juneau Ranger District. Work includes but is not limited to: bridge resurfacing, replacement of bridge object markers, ditch cleaning, borrow rock haul, placement, and compaction, tree blowdown removal, vegetation clearing, log bridge removal, and mobilization of equipment/personnel to accomplish all work under this contract. The Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies, and perform all work required in accordance with the typical drawings and specifications found in this contract.
**Note to Quoter’s: Mobilization to the Couverden Road System will be by barge to the USFS Marine Access Facility (MAF). The floating dock previously installed at this site has been removed, and will not be available for contractor’s use.
The Contractor shall assume all risk, loss, damage, or expense arising out of prosecution of the work, except as otherwise provided in the contract.
Description and Location: The project is located on the Couverden road system of the Juneau Ranger District, and is situated approximately 30 air miles west of Juneau, Alaska. The site is accessible by boat, fixed wing aircraft, and barge.
The project involves the following work:
Base Item Road BMP EMP Total Remarks
8553 0.0 11.9 11.9 Resurface bridges (4), furnish and install type 3 object markers at each bridge (4) at MP 0.214, 3.092, 3.896, 11.917
8553 0.0 11.9 11.9 Equipment rental, perform ditch excavation at bridge sites MP 0.214, 3.092 and vegetation clearing at Marine Access facility (MAF) as staked by engineer.
8563 0.0 4.55 4.55 Remove tree blow down from roadway, scatter below toe of fill slope on downhill side of road. Do not scatter removed blow down within 100’ of live streams.
8563 0.0 4.55 4.55 Haul and place 150 CY unclassified borrow, placement method 4, finish method c, as staked by engineer.
**Note to Quoter’s: Furnishing and installation of bridge object markers shall be considered incidental work under pay item 86101. No separate payment will be made.
Option Item 1 Road BMP EMP Total Remarks
8554 0.0 0.18 0.18
Remove log stringer bridge at MP 0.163 and MP 0.18 within fish timing window June 15 – Sept 1. See section H.3(c) Place logs adjacent to site. Apply grass seed & fertilizer as shown on drawings sheet 4.
Option Item 2 Road BMP EMP Total Remarks
8554 0.0 0.18 0.18 Construct a rubble rock hardened surface at the water crossings at MP 0.163 and MP 0.18 within timing window June 15- Sept1 See section H.3 (c)
Potential quoters are encouraged to examine the work sites prior to bidding on this project.
Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects, FP-14.
The Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects, FP-14, are included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.
ISBN 0-16-051430-4
The FP-14 U.S. Customary version is only available through the Federal Lands Highway Headquarters office:
Headquarters Washington DC David K. Green Construction Standards Engineer Internet: David.Green@fhwa.dot.gov Mail: Federal Highway Administration
HFPD-3
400 Seventh Street, SW Washington D.C. 20590
Or available on line at https://flh.fhwa.dot.gov/resources/specs/
Price Range The magnitude of construction is estimated to be between $100,000 and $250,000
Special Project Specifications and Forest Service Supplement to F-14 101 - Terms, Format, and Definitions (as supplemented herein) 102 - Bid, Award, and Execution of Contract (as supplemented herein) 103 - Scope of Work (as supplemented herein) 104 - Control of Work (as supplemented herein) 105 - Control of Material (as supplemented herein) 106 - Acceptance of Work (as supplemented herein) 107 - Legal Relations and Responsibility to the Public (as supplemented herein) 108 - Prosecution and Progress (as supplemented herein) 109 - Measurement and Payment (as supplemented herein) 155 - Schedules for Construction Contracts (as supplemented herein) 156 – Public Traffic 202 – Additional Clearing and Grubbing 203 – Removal of Structures and Obstructions 204 - Excavation and Embankment (as supplemented herein) 625 – Turf Establishment 807 – Equipment Rental 861 – Minor bridge Repair SPECIAL NOTE: The above is a list of major specifications applicable to this contract. Other specifications referred to within these specifications (even though not specifically listed) are also fully applicable to the solicitation and any resultant contract.
AGAR 452.211-72 Statement of Work/Specifications (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications listed.
AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988) The attachments to the Statement of Work/Specifications listed and are hereby made part of this solicitation and any resultant contract.
Signing and Safety
(a) A reflectorized SLOW MOVING VEHICLE emblem shall be attached to any equipment not designed to maintain a safe travel rate or that will be moving at a slow rate while performing maintenance.
(b) It shall be the Contractor’s responsibility to furnish black and orange reflectorized maintenance warning signs to alert motorists of maintenance operations. A minimum of (1) sign at each end of the road sections being maintained shall be kept in place at all times and shall be moved as work progresses.
12010919Q0042_2019 JRD Couverden Road Mtc.
https://flh.fhwa.dot.gov/resources/specs/
(c) If a berm is left in the roadway overnight or weekends due to weather conditions or breakdowns, it shall be properly signed as a hazard and visibly illuminated at night by Type B High-Intensity Flashing Warning Lights with a minimum mounting height of 36 inches to bottom of lens as required by the Manual of Uniform Traffic Control Devices.
Damage to Structures The Contractor shall be held liable and is responsible for any damage caused by Contractor’s personnel or equipment to any bridges, guardrails, culverts, signs, and riprap-protecting culvert inverts. Repair to these structures shall be at the Contractor’s expense and at no additional cost to the Government.
Activity Report The Contractor shall maintain and furnish a Daily Activity Report reporting maintenance activity performed. Reports shall be furnished to Contracting Officer on a weekly basis. A sample form is attached.
Abbreviations Whenever in these specifications, or in other contract documents, the following terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted as follows: (Reference to a specific standard or specification shall mean the latest addition or amendment thereto in effect on date of Invitation for Bids.)
(a) AASHTO – American Association of State Highway and Transportation Officials.
(b) CS – Commercial Standard Issued by U.S. Department of Commerce.
(c) EPA – Environmental Protection Agency.
(d) FAR – Federal Acquisition Regulation System.
(e) FED SPEC – Federal Specifications.
(f) FSS – Federal Specifications and Standards.
(g) MSHA – Mine Safety Health Administration.
(h) MUTCD – Manual of Uniform Traffic Control Devices.\
(i) NBS – National Bureau of Standards.
(j) OSHA – Occupational Safety and Health Act.
(k) PS – Product Standard issued by the U.S. Department of Commerce.
(l) UL – Underwriter’s Laboratories, Inc.
Quantity Measurement Terms
(a) Measurement under the contract shall be according to the United States standard measure.
(b) The methods of measurement and computation will be those necessary to accurately determine the quantities of materials furnished and work performed.
(c) Miles will, in the absence of known distances from existing plans or surveys, be determined by the Government using calibrated survey odometer or equal substitute operated on the traveled way at or parallel to road centerline.
(d) Linear mile measurement will mean the sum of the road length parallel to the centerline.
(e) Measurement will be made of each item or unit of work, as shown in the Schedule of Items, completed and accepted in accordance with the contract.
2. PACKAGING AND MARKING
Project Labeling for Official Correspondence The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.
3. INSPECTION AND ACCEPTANCE
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
CONTRACTOR’S QUALITY CONTROL PLAN
(a) The Contractor shall provide a quality control plan, which is mutually agreed upon with the Contracting Officer. This plan shall describe the Contractor’s method for ensuring all work meets the contract requirements. At minimum, the Quality Control Plan shall outline how the quality of work will be monitored, how the crew will be supervised, and who will perform the quality control function. Contractor shall provide the Contracting Officer with documentation of quality control inspections.
(b) The Contractor shall, within 5 days from receipt of a request from the Contracting Officer, submit a progress schedule to complete all work ordered within the time stated in the Task Order. If the Contractor falls behind schedule, the Contractor shall take such action as necessary to recover. The Contracting Officer may require the Contractor to submit a revised schedule and proposed plan of work to ensure completion of the work within the time stated in the Task Order.
4. DELIVERIES OR PERFORMANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998 This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984) 52.242-17 Government Delay of Work (APR 1984)
AGAR 452.211-74 Period of Performance (FEB 1988) The period of performance of this contract is from date of award through November 30, 2019
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than November 30, 2019. The time stated for completion shall include final cleanup of the premises.
5. CONTRACT ADMINISTRATION DATA
AGAR 452.215-73 Post Award Conference (NOV 1996) A post award or pre-work conference with the successful offeror is required. It will be scheduled and held within a reasonable time after award and prior to the issuing of a Notice to Proceed.
Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP)
(a) Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform
(IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract. The IPP website address is: https://www.ipp.gov
The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fms.treas.gov or phone (866) 973-3131.
(b) Final Payment. The final invoice must be accompanied by a release of claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically accepted from the operation of the release. Final payment will not be approved without a properly executed Contract Release, Form 6300-16.
(c) In addition, when submitting the invoice, the Contractor shall submit payrolls, subcontractor payment information and a spreadsheet detailing the payment breakdown in accordance with the Pay Items in the Schedule of Items, Section B.1 (either electronically in IPP, hard copy, or via fax) to the Contracting Officer (see FAR 52.232-5 Payments Under Fixed Price Construction Contracts).
Contract Administration This contract will be administered by the Contract Specialist located at:
Alaska Region Attn: Michael McCarthy
PO Box 21628 Juneau, AK 99801
All matters related to the performance of this contract shall be coordinated through the Contracting Officer.
http://www.arnet.gov/far/ https://www.ipp.gov/ mailto:IPPCustomerSupport@fms.treas.gov
Designation of Contracting Officer's Representative The Contracting Officer designates the Contracting Officer's Representative(s) (COR). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly.
(This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)
On all matters that pertain to the contract terms, the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
Contractor’s Designated Representative It is required that the Contractor have a designated representative available on the project during the entire project and that the representative be able to speak and understand English. When designating a representative, the Contractor shall furnish a copy of the designation in writing to the Contracting Officer. Such designation shall clearly indicate the name and limitations (if any) of authority of the representative. If the Contractor intends to designate a representative prior to the pre-work meeting, the representative is strongly encouraged to attend that meeting.
6. SPECIAL CONTRACT REQUIREMENTS
Landscape Preservation
(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which fall outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the clearing limits shall be repaired as directed by the Contracting Officer.
(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
(c) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be dischargeed of into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce sediment content to not more than that of the stream into which it is discharged. Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.
(d) Prevention of Oil Spills – If the Contractor maintains storage facilities for oil or oil products on Project Area, appropriate preventive measure shall be taken to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual States.
(e) If the total oil or oil products storage exceeds 1320 gallons or if any single container exceed a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.
(f) CREEK CROSSINGS: Schedule and conduct bridge and instream work to minimize disturbance to streams.
NFSR 8554 MP 0.163 June 15- September 1 Dolly Varden & Cutthroat NFSR 8554 MP 0.18 June 15- September 1 Dolly Varden & Cutthroat
1. Do not cross streams without Contracting Officer approval.
2. Submit a written equipment crossing plan to the Contracting Officer for approval 14 calendar days before creek crossing is planned. Two machine crossings will be permitted for all streams designated on the drawings as fish streams. Outside of this time period, no machine crossings will be permitted if fish eggs are present in the gravel or adult fish are present in the stream;
otherwise two machine crossings will be permitted.
3. Limit machine crossings to two times for all live streams not designated on the drawings as fish streams with pipes 48” and larger to be installed.
4. Do not leave temporary bridges in place between September 15 and March 15, unless approved in advance in writing by the Contracting Officer.
In stream work will only be allowed only at low flows.
Obtain necessary permits for floating camps, floats, shore ramps, and other appurtenances associated with project operations from the following State of Alaska and Federal Agencies:
1. ADNR – Alaska Department of Natural Resources.
2. ADEC – Alaska Department of Environmental Conservation.
3. ADGC – Alaska Department of Governmental Coordination.
4. EPA – US Environmental Protection Agency.
5. DA, COE – US Army Corps of Engineers.
6. USCG – US Coast Guard.
Use of premises
(a) Obtain written approval from the Contracting Officer before opening or operating on National Forest land or lands administered by the Forest Service any camp, quarry, borrow pit, storage area, detour, or bypass site, other than SHOWN ON THE DRAWINGS. A camp is interpreted to include the camp site or trailer parking area of any employee working on the project for the Contractor. Such approval, if granted, will be without charge to the Contractor.
(b) Sanitation Facilities: Provide and maintain the following facilities for the work force at the camp, unless provided otherwise.
1. Meet State of Alaska drinking water regulations 18 AAC 80 regarding potable water supplies for drinking, washing and cooking.
2. Comply with State of Alaska wastewater disposal regulations 18 AAC 72 for domestic sewage.
3. Ensure that the design, operation, and maintenance of all solid waste systems under Forest Service jurisdiction meet all Federal, State, and local requirements. Meet State of Alaska solid waste management regulations (18 AAC 60) and Federal regulations contained in 40 CFR 243, 40 CFR 245, 40 CFR 257, and 40 CFR 258. Remove solid wastes and/or residues and dispose of in approved commercial landfills.
4. Meet the requirements of 40 CFR 112 (Oil Pollution Prevention) for fuel storage.
Meet the requirements of 33 CFR 150 and 33 CFR 154 for facilities transferring oil or hazardous materials in bulk.
(c) Do not begin any camp development, either land based or floating, until a plan for development, occupation, and cleanup is submitted and approved by the Contracting Officer. Include the following information on this plan:
1. Location and size of the proposed camp development, including a map.
2. Wastewater system.
3. Number of people who will use the site and proposed dates of occupancy.
4. Power supply system.
5. Water supply system.
6. Building layout, shop area, living quarters.
7. Road and trail layout.
8. Clearing limits and slash disposal locations.
9. Borrow areas.
10. Dock and access location.
11. Equipment and fuel storage area and Spill Prevention Control and Countermeasure (SPCC) plan.
12. Incinerator location and ash disposal plan.
(d) Do not leave temporary bridges in place between September 15 and March 15 unless approved in advance in writing by the Contracting Officer.
Forest Service will review plan as submitted for completeness and applicability. Proposed modifications of Contractor's plans will be discussed with the Contractor prior to approval. Any modifications agreed upon will be incorporated in a revised set of plans.
Contractor’s Use and Maintenance of Existing Roads The Contractor is authorized to use roads in the immediate construction project area for performance of work under this contract.
Such roads are those which are necessary for direct access to designated borrow sites, quarries, stockpile sites, waste areas, campsites, equipment unloading ramps, and other approved work areas. The roads authorized for use will be subject to the following general conditions:
(a) Federal Regulations contained in 36 CFR 261.12; except vehicle weight will not exceed that of AASHTO HS20-44 and/or U80 Loading. Submit written requests to the CO for approval to use L90 and U102 overload Loadings on roads authorized for use. Regulations prohibit damaging a road or blocking a road open to use by others, except as otherwise provided in Special Project Specification 104.
(b) The Government will not snowplow roads for the Contractor's use. The Contractor may snowplow any road designated for his use. A permit defining snowplowing requirements is required and will be issued by the District Ranger, upon request by the Contractor. Repair any damage to the road structure caused by snow removal operations. Vehicles, other than conventional over-the-snow vehicles (snowmobiles), will not be permitted to use roads when there is an average of more than 4” of snow unless the road has been snowplowed.
(c) The Contractor is responsible for and will perform road maintenance on Forest Service roads in the construction area commensurate with his use. Perform road maintenance at such intervals that prevent deterioration of the roadway, or as directed by the Contracting Officer.
Road Maintenance Requirements Perform road maintenance work on the required roads in accordance with the following:
(a) Maintain existing roadbed by blading and shaping the traveled way and shoulders. Do not undercut banks. Maintain established drainage structures and/or berms, and place additional drainage structures/berms where necessary to protect embankments.
(b) Perform all seasonal weather cleanup, including removal of bank sloughs, minor slides and fallen timber, which can be accomplished by a motor patrol grader equipped with a front end blade, or comparable equipment, and by the use of hand tools.
Replace material eroded from fill slopes and clean out drainage ditches and culverts subject to the above equipment limitations.
(c) Deposit the material removed from slides or other sources in locations approved by the Contracting Officer.
Emergency Control Immediately extinguish without expense to the Government all fires on or in the vicinity of the project which are caused by the Contractor's employees, whether set directly or indirectly as a result of construction operations, with or without direction by the Forest Service. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation deemed necessary by the Government resulting from fires set or caused by Contractor's employees or resulting from construction operations.
Contractor's Responsibility for Controlling Other Emergencies - When requested by the Contracting Officer, allow the Forest Service to temporarily use employees and equipment for emergency control work. Payment will be made at not less than the current area rate established by the Forest Service.
Firefighting equipment will be required during the fire season from May 10 to August 31, and during any other period of fire danger designated by the Contracting Officer.
Furnish rust-free fire tools to equip all workers employed in Contractor's operations at each separate work site. Maintain tools in serviceable condition and keep tools in one or more weather-tight fire tools boxes. Paint fire tools boxes red, mark "tools for Fire Only" with letters at least 3” high, and keep sealed. Post a list of the contents inside each fire tool box so as to be visible when opened.
Kind of Tool No. of People Working in Area 1-4 5-9 10-15 16-20 Axe, d.b chopping, 32-inch min. handle 1 1 2 3 Shovels, L.H. R.P., No. 0 or larger 1 3 6 7 Pulaski, 32-inch min. handle 2 3 7 10 File, 10-inch mill bastard 1 1 1 2 Pumps, backpack cans, 5-gal filled with water 1 2 2 3
Equip each internal combustion engine with a spark arrester qualified and rated USDA-Forest Service, Standard 5100-1, unless it is:
(a) Equipped with a turbine-driven exhaust supercharger such as the turbocharger. There shall be no exhaust bypass.
(b) A multi-position engine, such as on a chain saw, which is equipped with screen arrester, as described in the Forest
Service Spark Arrester guide.
A spark arrester, which does not meet the requirements in this guide may be approved upon submission of acceptable proof that the arrester is at least 80 percent efficient in retention, attrition, or destruction of carbon particles. Such arrester may be required to meet higher standards as improvements in design and efficiency are discovered.
(c) A passenger-carrying vehicle or light truck intended primarily for use on roads, and equipped with a factory designed muffler and exhaust system.
(d) A heavy duty truck, such as a dump or log truck, or other vehicle used for commercial hauling, used only on roads and equipped with a factory designed muffler and with a vertical stack exhaust system extending above the cab.
Properly install and constantly maintain in serviceable condition all exhaust equipment described in this Subsection, including spark arresters and mufflers.
Equip each unit of mobile or stationary power equipment, including trucks, with one shovel, and at least one fire extinguisher meeting one of the following specifications:
1. 2-1/2 pound size or larger dry chemical type.
2. 4-pound size or larger carbon dioxide type.
Test or check each extinguisher for proper functioning prior to the beginning of fire precautionary period.
Provide each gasoline power saw with one chemical-pressurized fire extinguisher of not less than 8-ounce capacity by weight.
Maintain the extinguisher in good working order at all times.
Do not burn camp refuse, brush, slash, or debris such as that resulting from clearing around camps or on rights-of-way, without the written approval of the Contracting Officer. Submit written requests for burning to the Contracting Officer at least 48 hours in advance of intended burning. The Contracting Officer will approve routine camp refuse disposal incineration in the camp development proposal.
Prosecution of Work Areas of weak ground are crossed on this project. The initial embankment depth shall be as SHOWN ON THE DRAWINGS or determined by the Contracting Officer. Reestablish design centerline grade and alignment in accordance with Section 152 as construction progresses, and prior to the placement of borrow excavation. Reestablished design grades may be re-staked by the Contracting Officer to meet local conditions. Final grades may be at elevations other than those SHOWN ON THE DRAWINGS, but in no instance will they be lower than that of the surrounding ground elevations. When directed by the CO, return to previously constructed road or trail embankments and place additional borrow material where subsidence has occurred as a result of construction traffic displacing unstable or weak soil underlying the roadway.
Disposal of Merchantable Timber
(a) All timber meeting Forest Service merchantability standards logged during prosecution of this contract, remains the property of the Government. Deck logs in the immediate vicinity in accordance with Section 201 of the specifications.
(b) Buck trees in various lengths to obtain the greatest utilization of material meeting the following utilization standards. The Minimum merchantable piece shall be 6” in diameter inside bark at small end, 12 feet in length, have a net scale of 33 1/3 percent of its gross scale for a sawlog or produce not less than 50 percent of its gross volume in firm usable pulp chips.
(c) Trim allowance shall be a maximum of 12” for log lengths up to 40 foot. An additional 2” of trim shall be allowed for each 10 foot of log length over 40 foot.
(d) Use humbolt undercut in felling merchantable timber. Buck all limbs flush with merchantable logs.
(e) All dead trees which are sufficiently tall to reach the roadbed are designated for cutting. Fell other fire-dangerous dead trees or unstable live trees within 200 foot slope distance of the center line of the road, when marked by the Forest Service. Treat all timber under this subsection meeting utilization standards in accordance with Specification 201 Subsection 201.04, unless relieved in writing.
(f) Cut and use timber designated by the Contracting Officer for construction, without charge.
Construction Stakes, Lines, and Grades
(a) Contractor will perform all construction staking necessary for completion of contract:
(b) The Government will provide initial location staking for all proposed work.
Local Material Sources Government provided material sources are listed as follows:
Road #8553 MP 2.09 Road #8563 MP 1.51 Road #8563 MP 3.14 See Forest Service Supplemental Specification 105 – Control of Material for additional information.
Designated waste material sites will be staked on the ground by engineer.
Government Furnished Materials The contractor is to provide all labor, transportation, and facilities for work on this project. The government is not furnishing any materials, labor, transportation, or facilities under this contract, except for material sources as listed.
Other Contracts The Government may undertake or award other contracts for additional work at or near the site of the work under this contract.
The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work on this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Government employees.
Contractor Responsibility to Notify Government The Contractor will notify the COR when leaving the project area of any task orders for 3 or more days and within 24 hours before returning to the project area.
Worker’s Compensation Laws
Alaska state law requires that all employers have Worker’s Compensation Insurance for their employees. The Forest Service furnishes contract award information to the Alaska Department of Labor. Failure to comply with the state worker’s compensation laws can be a felony offense in Alaska. The Alaska Workers’ Compensation Division can also fine employers up to $1,000 per employee for each day they are conducting business with employee labor without the required insurance. For the definitions of “employer”, “employee”, and “subcontractor”, and other pertinent information contact:
Alaska Department of Labor Workers Compensation Division Special Investigations Unit P.O. Box 115512 Juneau, AK 99802-5521
907.465.5875 (Direct) 1-888-372-8330 (toll free), 907.465-2797 (FAX)
Product Substitution Request A. When submitted within 30 days after contract award, the Contracting Officer will consider formal requests for substitution of products, equipment and methods, in place of those specified. Requests submitted after 30 days will be considered only in case of product unavailability or other conditions beyond the control of Contractor. Requests shall provide the information and be in the format as specified in paragraph B below.
B. Submit separate request for each substitution. Support each request with:
1. Complete data substantiating compliance of proposed substitution with requirements stated in contract documents:
a. Product identification, including manufacturer's name and address.
b. Manufacturer's literature; identify:
1) Product description
2) Reference standards
3) Performance and test data
c. Samples, as applicable
d. Name and address of similar projects on which product has been used, and date of each installation.
e. Comparative data of item to be deleted by proposed substitution. Include drawings to same (or larger) scale as pertinent portion of contract documents and marked to show how differences will be accommodated.
f. Show complete system/assembly as revised to accommodate proposed alternate for difference in performance, size, configuration, connections, service, accessibility, or any other significant characteristics.
g. Show complete layout of system except that which is identical to contract documents unless unchanged portion must be shown to indicate clearances, etc.
h. Include complete detail drawings of supports for all substitute equipment and complete load calculations for adequacy of support prepared and signed by a registered structural engineer.
1. Itemized comparison of the proposed substitution with product specified; list significant variations.
2. Data relating to changes in construction schedule.
3. Any effect of substitution on separate contracts.
4. List of changes required in other work or products.
5. Accurate cost data comparing proposed substitution with product specified.
6. Proposed amount of change to the contract.
7. Designation of required license fees or royalties.
8. Designation of availability of maintenance services, sources of replacement materials.
C. Substitutions will NOT be considered for acceptance when:
1. They are merely indicated or implied on shop drawings or product data submittals without a formal request from Contractor.
2. They are requested directly by a subcontractor or supplier.
3. Acceptance will require substantial revision of contract documents.
4. Substitution has not been requested in accordance with this and related clauses.
D. Substitute products shall not be ordered or installed without written acceptance of the Contracting Officer.
E. Contracting Officer will determine acceptability of proposed substitutions.
F. Number of Substitution Submittals: Only one proposed alternative will be considered for each item. Provide specified item if substitution proposal is rejected.
Contractor’s Representation and Responsibility A. In making formal request for substitution the Contractor represents he/she:
1. Have investigated proposed product and determined that it is equal to or superior in all respects to that originally specified.
2. Will provide same warranties and bond for substitute as for originally specified product.
3. Will coordinate installation of accepted substitution into the work, and will make such changes as may be required for the work to be complete in all respects.
4. Will waive claims for additional costs caused by substitution, which may subsequently become apparent.
5. Cost data is complete and includes related costs under the contract, but not:
a. Costs under separate contracts.
b. Contracting Officer costs for redesign or revision of contract documents.
B. The Contractor assumes full responsibility that the substitution and/or alternate items or procedures proposed will meet the job requirements.
C. The Contractor is solely responsible for the cost of redesign and modifications to this and other parts of the work caused by the substitutions or alternates furnished.
SIMPLIFIED ACQUISITION TERMS & CONDITIONS: CONSTRUCTION
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.252-2 Clauses Incorporated by Reference. (Feb 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov.
52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.213-4 Terms and Conditions-Simplified Acquisitions (Other Than Commercial Items) (JAN 2019) (c) fill in:
www.acquisition.gov/far/ www.usda.gov/procurement/policy/agar.html 52.219-3 Notice of HUBZone Set-Aside or Sole Source Award (NOV 2011) 52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013) 52.222-6 Construction Wage Rate Requirements (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (AUG 2018) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEP 2015) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.223-2 Affirmative Procurement of Bio-based Products under Service and Construction Contracts (SEP 2013) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (AUG 2018) 52.223-18 Contractor Policy to Ban Text Messaging While Driving (AUG 2011) 52.225-9 Buy American Act-Construction Materials (MAY 2014)
(a) Definitions. As used in this clause-- “Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: ______ [Contracting Officer to list applicable excepted materials or indicate “none”]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation…