1) Schedule of Items.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- Kamiah SO Sound Absorbing Panels AMENDMENT 1 Federal contract opportunity
- Solicitation number
- 1240LU23Q0063
- Issued by
- Department of Agriculture Forest Service
About this file
This document contains a schedule of sound absorbing wall panels and related items required for a federal construction project. The Forest Service is soliciting bids to install soundproofing in meeting rooms, huddle rooms, and hallways at the Kamiah Ranger District office, including 365 square feet of wall panels on the first floor and 465 square feet on the south and east walls, with options to also soundproof the north wall and ductwork. Bids are due by January 23, 2023 under solicitation number 1240LU23Q0063. The schedule specifies the locations, quantities, and specifications of various acoustic wall panels and accessories needed and provides an area to include pricing. Labor, overhead, profit, and mobilization costs should also be included. Payment will be made on a lump sum basis for mobilization, and per square foot of installed soundproofing for the remaining phases and options.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 7) TERO Compliance Plan and Agreement.pdf | ||
| 6) Tribal Employment Rights Office Requirements.pdf | ||
| 4) AS2 Panels A415B.pdf | ||
| 0) Solicitation.pdf | ||
| 2) Specifications.pdf | ||
| 3) White Boards and AS2 Acoustic Wall Panels.pdf | ||
| 5- Relative Experience Questionnaire.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Schedule of Items | |||||||
| Matierals | |||||||
| Drawing Number and Spec Number | Item Description | Typeof wal lpannels | Mmeas | Units | Quanitiy | Cost/SF | |
| AS2 Wall pennels | |||||||
| 5 North wall 4'0"x11'8" | AS2 | AQ | SF | 235 | 0 | ||
| North Wall 4'0" x 7 and 4'0" x 5 and 4'x11'8" | AS2 | AQ | SF | 95 | 0 | ||
| North Wall 3'2" x 6' | AS2 | AQ | SF | 19 | 0 | ||
| A 602 | West wall 3'2"x36' | AS2 | AQ | SF | 114 | 0 | |
| south wall 3'2" X 62'9"3/8" | AS2? | AQ | SF | 198 | 5 | ||
| south wall 2'0"x 100' | AS2? | AQ | SF | 200 | 0 | ||
| east wall 3'2"x 20' | AS2 | AQ | SF | 63 | 0 | ||
| A(412) | SM MTG room 4'x16' | AS2 | AQ | SF | 64 | 0 | |
| A(412) | Med MTG room 8.5'x4' and 4' x 18' | AS2 | AQ | SF | 106 | 0 | |
| A(412) | 2x Huddel Room 9'X4' | AS2 | AQ | SF | 36 | 0 | |
| A(412) | AS1 wall pannels | NONE | AQ | SF | 0 | ||
| A(412) | Mail room ( 4'2" 3' 0" and 1'8"x4' and 6'x4') | AQ | SF | 44 | 0 | ||
| Endcaps on the Ductwork Sound dampening. | 4 18" round |
AQ SF 1175 $ - 0
Hanging acessories and Adhesive Incidental SF 1175 0.00
| Item Number | Item Description | Mmeas | Units | Quanitiy | |
| White Boards | |||||
| A(412) | SM MTG Room White Board '6'x4' | 2 | |||
| Done | Med MTG Room | none | 0 |
| Materials | Total: See above | $ - 0 | |||
| Labor Costs | 4 persons 3 weeks | 35.47 plus 16.88 fring | hours | 480 | $ - 0 |
| Overhead | 2 person 1 week | Utilize Same Rate for Purchaing | hours | 80 | $ - 0 |
| Profit | Total Supplies and Labor Times 8% | $ - 0 | |||
| Mobilization | Need Mob plus TERO using 30% Total Profit Costs, and Labor | $ - 0 |
TOTAL COST $ - 0
| Item Number | Description | Method of | Pay Unit | Est. Quantity |
| Meas. | ||||
| 15101 | Mobilization | LSQ | LS | 1 |
| Phase 1 | Sound Proofing and White board installation: Meeting rooms, Huddle rooms, Mail room, and Second floor | AQ | SF | 365 |
| Phase 2 | Wall Sound proofing South and East walls | AQ | SF | 465 |
| Option1 | Phase 3: Wall sound proofing North Wall | AQ | LS | 350 |
| Option 2 | Phase 4: Sound dampening materials applied to ends of exposed heating ducts | LSQ | EA | 4 |