1_NIFC_100-ADM_Repairs_DRAFT_SPECS_1.pdf
PDF 6 MB Posted
- Attached to
- NIFC 100-ADM Repairs Federal contract opportunity
- Solicitation number
- 140L0626R0002
About this file
This file is a comprehensive set of draft specifications for the NIFC 100 Administrative Building repairs and renovations located at the National Interagency Fire Center in Boise, Idaho. The project, identified under Contract Number 140L0622D0002, involves demolition and renovation of portions of Building 100 with new office and support spaces, plus the addition of two external stair towers. Work is scheduled for completion during FY 2022 under GAOA funding.
The specifications cover all divisions of construction work including general requirements, selective demolition, cutting and patching, construction waste management with a 50 percent salvage/recycling goal, gypsum board and metal framing systems, fire suppression sprinkler systems, HVAC systems including variable refrigerant flow (VRF) units, plumbing, electrical, communications, and electronic safety and security systems. Key requirements include: submission of detailed working plans for fire sprinkler systems by a NICET Level III/IV technician or registered professional engineer; installation of seismic bracing compliant with IBC standards; testing, adjusting, and balancing (TAB) of HVAC systems by a NEBB-certified firm; operation and maintenance manuals and training for all systems; all equipment and materials to be new unless otherwise specified; thermal insulation for hot and cold piping systems; identification labeling of all mechanical systems per ASME A13.1; coordination with the Government's continuous building occupancy requiring minimum 72-hour advance notice for disruptive activities; and compliance with all federal, state, and local building codes including NFPA standards for fire protection. The project requires extensive coordination among trades, with the contractor responsible for resolving interferences between mechanical, electrical, and structural systems at no additional cost to the Government.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Industry_Day_Invite_1.pdf | ||
| 2_NIFC_100-ADM_Repairs_DRAFT_DWGS_1.pdf | ||
| NIFC_PUBLIC_PARKING_Map_1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT
U.S. Department of the Interior Specifications 95% Design Development
October 2025
Project Name: NIFC 100 Admin Additional Repairs Location: Boise, ID Project Number: 070117.028 Contract Number: 140L0622D0002
LBYD Federal, LLC
THIS PAGE HAS BEEN LEFT INTENTIONALLY BLANK.
Division Section Title Pages
SPECIFICATIONS GROUP
General Requirements Subgroup
DIVISION 01 - GENERAL REQUIREMENTS
011000 SUMMARY 4
012200 UNIT PRICES 4
013100 PROJECT MANAGEMENT AND COORDINATION 7
013200 CONSTRUCTION PROGRESS DOCUMENTATION 4
013300 SUBMITTAL PROCEDURES 10
014000 QUALITY REQUIREMENTS 7
014200 REFERENCES 4
015000 TEMPORARY FACILITIES AND CONTROLS 8
016000 PRODUCT REQUIREMENTS 8
017300 EXECUTION REQUIREMENTS 5
017320 SELECTIVE DEMOLITION 6
017329 CUTTING AND PATCHING 5
017419 CONSTRUCTION WASTE MANAGEMENT 6
017700 CLOSEOUT PROCEDURES 5
017823 OPERATION AND MAINTENANCE DATA 5
017839 PROJECT RECORD DOCUMENTS 3
017900 DEMONSTRATION AND TRAINING 2
Facility Construction Subgroup
DIVISION 02 - EXISTING CONDITIONS
024200 REMOVAL AND SALVAGE OF CONSTRUCTION MATERIALS 3
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
061000 ROUGH CARPENTRY 6
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
072100 THERMAL INSULATION 6
079200 JOINT SEALANTS 9
DIVISION 08 - OPENINGS
081113 HOLLOW METAL DOORS AND FRAMES 9
081416 FLUSH WOOD DOORS 7
083113 ACCESS DOORS AND FRAMES 4
087111 DOOR HARDWARE (DESCRIPTIVE SPECIFCATION) 16
088000 GLAZING 11
DIVISION 09 - FINISHES
092216 NON-STRUCTURAL METAL FRAMING 10
092900 GYPSUM BOARD 8
095113 ACOUSTICAL PANEL CEILINGS 8
096513 RESILIENT BASE AND ACCESSORIES 5
096519 RESILIENT TILE FLOORING 5
096813 TILE CARPETING 7
099123 INTERIOR PAINTING 7
099300 STAINING AND TRANSPARENT FINISHING 5
DIVISION 10 - SPECIALTIES
101423.16 ROOM-IDENTIFICATION PANEL SIGNAGE 6
104413 FIRE PROTECTION CABINETS 6
104416 FIRE EXTINGUISHERS 3
Facility Services Subgroup
DIVISION 21 -
211313 FIRE SPRINKLER 18
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
230500 COMMON WORK RESULTS FOR PLUMBING AND HVAC 7
230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT 5
230523 GENERAL-DUTY VALVES FOR PLUMBING AND HVAC PIPING 4
230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 10
230549 SEISMIC CONTROLS FOR PLUMBING AND HVAC 7
230553 IDENTIFICATION FOR PLUMBING AND HVAC PIPING AND EQUIPMENT 4
230593 TESTING, ADJUSTING AND BALANCING FOR HVAC 9
230700 PLUMBING AND HVAC PIPING INSULATION 13
230900 INSTRUMENTATION AND CONTROL FOR HVAC 19
232300 REGRIGERANT PIPING 5
233113 METAL DUCTS 10
233300 AIR DUCT ACCESSORIES 9
233713 DIFFUSERS, REGISTERS, AND GRILLES 3
238129 VARIABLE-REGRIGERANT-FLOW HVAC SYSTEMS 34
DIVISION 26 - ELECTRICAL
260010 SUPPLEMENTAL REQUIREMENTS FOR ELECTRICAL 17
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 8
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 18
260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 6
260533.13 CONDUITS FOR ELECTRICAL SYSTEMS 16
260533.16 BOXES AND COVERS FOR ELECTRICAL SYSTEMS 14
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS 9
260800 ELECTRICAL COMMISSIONING 9
260923 LIGHTING CONTROL DEVICES 10
262726 WIRING DEVICES 7
262813 FUSES 4
262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS 7
262913.03 MANUAL AND MAGNETIC MOTOR CONTROLLERS 8
265119 LED INTERIOR LIGHTING 7
265213 EMERGENCY AND EXIT LIGHTING 5
DIVISION 27 - COMMUNICATIONS
271513 COMMUNICATIONS COPPER HORIZONTAL CABLING 12
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
281000 ACCESS CONTROL 8
283100 ADDRESSABLE FIRE-ALARM SYSTEMS 13
END OF TABLE OF CONTENTS
OCTOBER 2025 SUMMARY
NIFC 100 ADMIN ADDITIONAL REPAIRS 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Access to site.
4. Government Occupancy Requirements.
5. Specification and Drawing conventions.
1.2 PROJECT INFORMATION
A. Project Identification: NIFC 100 – Administration Repairs FY 2022 GAOA
1. Project Location: National Interagency Fire Center, NIFC 100-ADM, 3906 S.
Vista Ave. Boise, ID 83705, on the NIFC Campus at 3833 S Development Ave Boise, ID 83705.
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
B. Work effort includes the demolition and renovation of portions of Building 100 with new office and support spaces, and the addition of two external stair towers. All other work is as delineated within these contract documents.
C. Type of Contract:
1. Project will be constructed under a single prime contract.
1.4 ACCESS TO SITE
A. Contractor shall have limited use of premises for construction operations as indicated by the Work on Drawings.
B. Schedule operations so that Work is conducted during regular office hours which are 8:00 am to 4:30 pm. Work during nights or weekends may be allowed as approved by the Government.
NIFC 100 ADMIN ADDITIONAL REPAIRS 011000 - 2
C. Schedule and sequence operations necessary to complete the work, including coordination with other crafts relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.
1. A two week pause in construction will be required to enable the Government to install the vertical portions of Government provided modular furniture. Once installed, the contractor may resume work and will need to pull communication lines to modular furniture and wire the electrical portion of power columns.
D. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Government Occupancy: Allow for Government occupancy of Project site.
Government personnel will be continuously occupying areas of the building immediately adjacent to the work area. Conduct work in a manner that will minimize needs for disruption of normal Government operations. Provide minimum 72 hours advance notice to Government of activities that will impact normal Government operations. Secure Government's written approval of activities that will impact normal Government operations to avoid delays in overall construction and permit proper installation or work.
2. Driveways and Entrances: Keep driveways parking areas, loading areas, and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Use of Existing Building: Maintain existing building in a weathertight condition throughout construction period. Repair damage caused by construction operations.
Protect building and its occupants during construction period.
F. Utilities: Service interruptions of mechanical and electrical systems will be allowed for short periods per schedule approved by Government.
1.5 SECURITY
A. NIFC is a secure facility, and all Contractor personnel shall provide an official US Government or State Government issued photo identification at the security gate upon entry.
B. All contracting personnel shall wear NIFC furnished visitor badges in a visible location at all times while on the facility, and return the badge at the end of each day or at the completion of the project.
NIFC 100 ADMIN ADDITIONAL REPAIRS 011000 - 3
C. Contractor shall provide a list of names, to the Government, of all personnel that will be working on the facility.
D. Contractor personnel shall not enter the facility more than 30 minutes prior to the start of scheduled work day and must leave the facility within 30 minutes of the scheduled completion time.
1.6 GOVERNMENT OCCUPANCY REQUIREMENTS
A. Full Government Occupancy: Government will continue to occupy the building during construction. Cooperate with Government during construction operations to minimize conflicts. Perform the Work so as not to interfere with Government day-to-day operations in adjacent spaces in the building and surrounding building site. Maintain existing exits, unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.
1.7 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the 33-Division format and CSI/CSC's "MasterFormat" numbering system.
1. Division 01: Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires.
Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
NIFC 100 ADMIN ADDITIONAL REPAIRS 011000 - 4
C. Terminology: In Divisions 02 through 31 Specification Sections, all references to "Owner" have been replaced with the term "Government" or "Government" (when referring to the person acting for the Government). All references to "Architect" have been replaced with the term "Government".
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
OCTOBER 2025 UNIT PRICES AND SCHEDULE OF VALUES
NIFC 100 ADMIN ADDITIONAL REPAIRS 012200 - 1
SECTION 012200 - UNIT PRICES AND SCHEDULE OF VALUES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for unit prices.
1.2 PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
1.3 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.
1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including Application for Payment and Contractor's Construction Schedule.
2. Submit the Schedule of Values to Government at earliest possible date but no later than 10 calendar days after the Notice to Proceed.
B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.
1. Identification: Include the following Project identification on the Schedule of Values:
a. Project name and location.
b. Name of Government.
c. Contractor's name and address.
d. Date of submittal.
2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate. Include separate line items under required principal subcontracts for operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training in the amount of 5 percent of the Contract Sum.
3. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
NIFC 100 ADMIN ADDITIONAL REPAIRS 012200 - 2
4. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
5. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
6. Each item in the Schedule of Values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.
7. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Modifications result in a change in the Contract Sum.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LUMP SUM PAYMENT ITEMS
A. Payment items for the work of this Contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below.
B. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved.
C. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided. Items will be paid for as a lump sum by percent of item completed in accordance with the accepted Schedule of Values.
D. Mobilization and Demobilization: Preparatory work and operations, including movement of personnel, equipment, supplies and incidentals to the project site; and for other work and operations that must be performed or costs incurred prior to beginning work on the various items on the project site. Does not include moves between project sites.
NIFC 100 ADMIN ADDITIONAL REPAIRS 012200 - 3
1. Payment: Payment will be made for costs associated with mobilization and demobilization, as defined in Special Clause PAYMENT FOR MOBILIZATION AND DEMOBILIZATION. No direct payment for moves between project sites will be made. Include consideration for moves between project sites. Prices and payment will be full compensation for the work described in this Section.
Progress payments will be made as follows:
a. When 5 percent of the original Contract amount is earned from other bid items, 50 percent of the amount bid for mobilization or 5 percent of the original Contract amount, whichever is lesser, will be paid.
b. When 10 percent of the original Contract amount is earned from other bid items, 100 percent of the amount bid for mobilization or 10 percent of the original Contract amount, whichever is lesser, will be paid.
c. Upon completion of work for the project, payment of the amount bid for mobilization in excess of 10 percent of the original Contract amount, will be paid.
d. The total sum of all payments shall not exceed the original Contract amount bid for mobilization, regardless whether Contractor may have shut down the work on the project or moved equipment away from the project and then back again.
2. Unit of Measure: Lump sum.
E. Demolition:
1. Payment: Payment will be made for costs associated with operations necessary for demolition.
2. Unit of Measure: Lump sum.
F. Construction:
1. Payment: Payment will be made for costs associated with operations necessary for the construction.
2. Unit of Measure: Lump sum.
3.2 SUMMARY OF BID ITEMS
A. The intent of the following paragraphs is to explain, in general, what is and what is not included in a bid item, and the limits or cut-off points where one bid item ends and another begins. If no bid item exists for a portion of the work, include the costs in a related bid item. Include separate labor and materials costs for each bid item.
B. BID ITEM 1 - GENERAL REQUIREMENTS (MOBILIZATION AND
CONSTRUCTION MANAGEMENT): This item includes all preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; bonds, work layout; other work and operations which must be performed or costs incurred prior to beginning work on the
NIFC 100 ADMIN ADDITIONAL REPAIRS 012200 - 4
various items on the project site. Construction management includes ongoing tasks such as environmental controls and field office operations.
C. BID ITEM 2 - EXISTING CONDITIONS (DEMOLITION): This item includes all work required for demolition as shown and specified for the new work.
D. BID ITEM 3 - CONCRETE: This item includes all work related to concrete.
E. BID ITEM 4 - MASONRY: This item includes all work related to masonry.
F. BID ITEM 5 - METALS: This item includes all work related to metal components.
G. BID ITEM 6 - WOOD, PLASTICS, AND COMPOSITES: This item includes all work related concrete.
H. BID ITEM 7 - THERMAL AND MOISTURE PROTECTION: This item includes all work related to thermal and moisture protection of the building envelope, including roofing..
I. BID ITEM 8 - OPENINGS: This item includes all work related to doors, windows, and other openings.
J. BID ITEM 9 - FINISHES: This item includes all work related to interior finishes, paints, and coatings.
K. BID ITEM 10 - SPECIALTIES: This item includes all work related to building specialties.
L. BID ITEM 12 - FURNISHINGS: This item includes all work related to furnishings.
M. BID ITEM 21 - FIRE SUPPRESSION: This item includes all work related to fire suppression systems.
N. BID ITEM 22 - PLUMBING: This item includes all work related to plumbing.
O. BID ITEM 23 – HEATING, VENTILATION, AND AIR-CONDITIONING (HVAC):
This item includes all work related to heating, ventilating, and air-conditioning systems.
P. BID ITEM 26 - ELECTRICAL: This item includes all work related to electrical systems.
Q. BID ITEM 27 - COMMUNICATIONS: This item includes all work related to communications systems.
R. BID ITEM 28 – ELECTRONIC SAFETY AND SECURITY: This item includes all work related to electronic safety and security equipment.
END OF SECTION 012200
OCTOBER 2025 PROJECT MANAGEMENT AND COORDINATION
NIFC 100 ADMIN ADDITIONAL REPAIRS 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Coordination Drawings.
2. Project meetings.
3. Requests for Interpretation (RFIs).
B. See Division 01 Section "Execution Requirements" for procedures for coordinating general installation and field-engineering services.
1.2 DEFINITIONS
A. RFI: Request from Contractor seeking interpretation or clarification of the Contract Documents.
1.3 COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.
Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013100 - 2
1. Prepare similar memoranda for Government and separate contractors if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
9. Project closeout activities.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Government for resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 30 by 40 inches.
3. Number of Copies: Submit two copies of each submittal. Government will return one copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those Sections.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013100 - 3
1.5 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Government of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Government, within three days of the meeting.
B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Government, but no later than 15 days after execution of the Agreement. Hold the conference at Project site or another convenient location. Conduct the meeting to review responsibilities and personnel assignments, review required work, project drawings, specifications, construction schedules, payroll, payments, and administrative provisions of the Contract. Be prepared to summarize and explain procedures planned for the project and present specified preconstruction submittals.
1. Attendees: Authorized representatives of Government and their consultants;
Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work. The mechanical and electrical subcontractors attendance will be required.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Phasing.
c. Critical work sequencing and long-lead items.
d. Designation of key personnel and their duties.
e. Procedures for processing field decisions and Modifications.
f. Procedures for RFIs.
g. Procedures for testing and inspecting.
h. Procedures for processing Applications for Payment.
i. Distribution of the Contract Documents.
j. Submittal procedures.
k. Preparation of Record Documents.
l. Use of the premises and existing building.
m. Work restrictions.
n. Government occupancy requirements.
o. Responsibility for temporary facilities and controls.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013100 - 4
p. Construction waste management and recycling.
q. Parking availability.
r. Office, work, and storage areas.
s. Equipment deliveries and priorities.
t. First aid.
u. Security.
v. Progress cleaning.
w. Working hours.
3. Minutes: Record and distribute meeting minutes.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Government of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. The Contract Documents.
b. Related RFIs.
c. Related Modifications.
d. Purchases.
e. Deliveries.
f. Submittals.
g. Possible conflicts.
h. Compatibility problems.
i. Time schedules.
j. Weather limitations.
k. Manufacturer's written recommendations.
l. Warranty requirements.
m. Compatibility of materials.
n. Acceptability of substrates.
o. Temporary facilities and controls.
p. Space and access limitations.
q. Regulations of authorities having jurisdiction.
r. Testing and inspecting requirements.
s. Installation procedures.
t. Coordination with other work.
u. Required performance results.
v. Protection of adjacent work.
w. Protection of construction and personnel.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013100 - 5
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.
5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Progress Meetings: Conduct progress meetings at regular intervals. Hold the meetings at the project site. Coordinate dates of meetings with preparation of payment requests.
Additional progress meetings may be requested by either the Government or Contractor.
1. Attendees: In addition to representatives of Government, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Work hours.
10) Hazards and risks.
11) Progress cleaning.
12) Quality and work standards.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013100 - 6
13) Status of correction of deficient items.
14) Field observations.
15) RFIs.
16) Status of proposal requests.
17) Pending changes.
18) Status of Modifications.
19) Pending claims and disputes.
20) Documentation of information for payment requests.
3. Minutes: Record the meeting minutes.
4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.
a. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
1.6 REQUESTS FOR INTERPRETATION (RFIs)
A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form specified.
1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be returned with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following:
1. Project name.
2. Date.
3. Name of Contractor.
4. Name of Government.
5. RFI number, numbered sequentially.
6. Specification Section number and title and related paragraphs, as appropriate.
7. Drawing number and detail references, as appropriate.
8. Field dimensions and conditions, as appropriate.
9. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract
Time or the Contract Sum, Contractor shall state impact in the RFI.
10. Contractor's signature.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013100 - 7
11. Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop Drawings, and other information necessary to fully describe items needing interpretation.
C. Government's Action: Government will review each RFI, determine action required, and return it. Allow 7 calendar days for Government's response for each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day.
1. The following RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for coordination information already indicated in the Contract
Documents.
d. Requests for adjustments in the Contract Time or the Contract Sum.
e. Requests for interpretation of Government's actions on submittals.
f. Incomplete RFIs or RFIs with numerous errors.
2. Government's action may include a request for additional information, in which case Government's time for response will start again.
D. On receipt of Government's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Government within seven days if Contractor disagrees with response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log monthly. Include the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Government.
4. RFI number including RFIs that were dropped and not submitted.
5. RFI description.
6. Date the RFI was submitted.
7. Date Government's response was received.
8. Identification of related bilateral or unilateral modifications, extensions, and changes in scope, as appropriate.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013100
OCTOBER 2025 CONSTRUCTION PROGRESS DOCUMENTS
NIFC 100 ADMIN ADDITIONAL REPAIRS 013200 - 1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule.
2. Daily construction reports.
3. Field condition reports.
B. See Division 01 Section "Unit Prices and Schedule of Values" for submitting the Schedule of Values.
1.2 SUBMITTALS
A. Contractor's Construction Schedule: Submit one electronic copy of initial schedule, large enough to show entire schedule for entire construction period.
B. Daily Construction Reports: Submit one electronic copy at weekly intervals.
C. Field Condition Reports: Submit one electronic copy at time of discovery of differing conditions.
1.3 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013200 - 2
PART 2 - PRODUCTS
2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Modification.
B. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Government.
2. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
3. Submittal Review Time: Include review and resubmittal times indicated in Division 01 Section "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.
4. Startup and Testing Time: Include not less than two days for startup and testing.
5. Substantial Completion: Indicate completion in advance of date established for
Substantial Completion, and allow time for Government's administrative procedures necessary for certification of Substantial Completion.
C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
1. Work Restrictions: Show the effect of the following items on the schedule:
a. Coordination with existing construction.
b. Limitations of continued occupancies.
c. Uninterruptible services.
d. Use of premises restrictions.
e. Seasonal variations.
f. Environmental control.
2. Work Stages: Indicate important stages of construction for each major portion of the Work.
D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013200 - 3
E. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.
2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART)
A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule within 15 days of date established for the Notice to Proceed. Base schedule on the Preliminary Construction Schedule and whatever updating and feedback was received since the start of Project.
B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line. Indicate critical path method from start to finish of project, including contractor float times, if any.
1. For construction activities that require 3 months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar.
2.3 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:
1. Contract name and number.
2. Contractor representative onsite.
3. Date.
4. High and low temperatures and general weather conditions.
5. List of subcontractors at Project site and work location/classification.
6. Equipment at Project site.
7. Material deliveries.
8. Accidents.
9. Stoppages, delays, shortages, and losses.
10. Meter readings and similar recordings.
11. Orders and requests of authorities having jurisdiction.
12. Services connected and disconnected.
13. Equipment or system tests and startups.
B. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013200 - 4
PART 3 - EXECUTION
3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate Actual Completion percentage for each activity.
B. Distribution: Distribute copies of approved schedule to Government, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
END OF SECTION 013200
OCTOBER 2025 SUBMITTAL PROCEDURE
NIFC 100 ADMIN ADDITIONAL REPAIRS 013300 - 1
SECTION 013300 - SUBMITTAL PROCEDURES
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, Design Computations, and other submittals.
B. See Division 01 Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's Construction Schedule.
C. See Division 01 Section "Quality Requirements" for submitting test and inspection reports.
D. See Division 01 Section "Closeout Procedures" for submitting warranties.
E. See Division 01 Section "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data.
F. See Division 01 Section "Operation and Maintenance Data" for submitting operation and maintenance manuals.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Government's responsive action.
B. Informational Submittals: Written information that does not require Government's responsive action. Submittals may be rejected for not complying with requirements.
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Government reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013300 - 2
B. Submittals Schedule: Comply with requirements in Division 01 Section "Construction Progress Documentation" for list of submittals and time requirements for scheduled performance of related construction activities.
C. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Government's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 14 calendar days for initial review of each submittal.
Allow additional time if coordination with subsequent submittals is required.
Government will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 14 calendar days for review of each resubmittal.
D. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately 6 by 8 inches on label or beside title block to record Contractor's review and approval markings and action taken by Government.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Government.
d. Name and address of Contractor.
e. Name and address of subcontractor.
f. Name and address of supplier.
g. Name of manufacturer.
h. Submittal number or other unique identifier, including revision identifier.
1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 06100.01).
Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 06100.01.A). Work schedule and value schedules shall be numbers 01000.01 and 01000.02.
i. Number and title of appropriate Specification Section.
j. Drawing number and detail references, as appropriate.
k. Location(s) where product is to be installed, as appropriate.
l. Other necessary identification.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013300 - 3
E. Cover Sheet:
1. Ensure that cover sheet includes following information:
a. Submittal Number
b. Contract Number
c. Specification Section number and title, paragraph, and complete description of item being submitted. Be specific and clearly identify what is being submitted. When appropriate, reference a specific sheet and detail of the Drawings. Note multiple items individually.
d. Signature and date.
e. Name and telephone number of individual to contact for further information, if other than Contractor.
2. Submitted Information: Link submittal to cover sheet by contract number, project name, and submittal number. Stamp is recommended, but may be hand-written on each copy; ensure submittal stamp includes project name and contract number and blank space in which to write submittal number. Stamp or write this information on all copies.
F. Mechanical and Electrical: Deliver catalogs or pages and tables for mechanical and electrical items in one complete mechanical package and one complete electrical package. Incomplete packages will be retained until all items are received. Shop drawings may be submitted separately. Submit the following additional data:
1. Rough-in data and dimensions.
2. Motor characteristics and wiring diagrams.
3. Performance curves and rated capacities.
4. Operation characteristics.
G. Deviations: Highlight, encircle, or otherwise specifically identify deviations from the Contract Documents on submittals.
H. Additional Copies: Unless additional copies are required for final submittal, and unless Government observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.
I. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Government will return submittals, without review received from sources other than Contractor.
J. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013300 - 4
3. Resubmit submittals until they are marked "APPROVED."
K. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
L. Use for Construction: Use only final submittals with mark indicating "APPROVED" taken by Government.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. Prepare and submit Action Submittals required by individual Specification Sections.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Printed performance curves.
g. Operational range diagrams.
h. Compliance with specified referenced standards.
i. Testing by recognized testing agency.
4. Number of Copies: Submit two copies of Product Data, unless otherwise indicated. Government will return one copies. Mark up and retain one returned copy as a Project Record Document.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Dimensions.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013300 - 5
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Shopwork manufacturing instructions.
g. Templates and patterns.
h. Schedules.
i. Notation of coordination requirements.
j. Notation of dimensions established by field measurement.
k. Relationship to adjoining construction clearly indicated.
l. Seal and signature of professional engineer if specified.
m. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 22 by 34 inches.
3. Number of Copies: Submit two copies of each submittal. Government will return one copy.
D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Lot.
e. Style.
f. Color.
g. Locations of use.
h. Number and title of appropriate Specification Section.
3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity.
Sample sets may be used to determine final acceptance of construction associated with each set.
4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available. Color selections will be made only after all related color samples have been received.
NIFC 100 ADMIN ADDITIONAL REPAIRS 013300 - 6
a. Number of Samples: Submit one full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Government will return submittal with options selected.
5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected.