This statement of work describes requirements for the Riverine Surface Patrol Platform program. Customs and Border Protection intends to procure up to thirty-three vessels through a combination of new builds and retrofits to standardize its aging fleet of eighteen airboats. Key requirements include vessel design for restricted waterway operations on rivers, lakes, and marshlands; a minimum three-year service life for hulls and trailers; and logistical support, training, and technical data deliverables. The contractor will perform design, engineering, manufacturing, testing, and delivery of the vessels. The anticipated contract type is an indefinite delivery indefinite quantity set-aside for small businesses.

RSPP Solicitation Attachment 1

View the file

Other files for this federal contract opportunity

Other files attached to Riverine Surface Patrol Platform (RSPP), newest first.
File Type Posted
70B02C19R00000028-A0001_6.20.19.pdf PDF
70B02C19R00000028-RSPP_RFP_Att(2)_Performance_Spec_6.13.19.pdf PDF
70B02C19R00000028-RSPP_RFP_Att(5)_QASP_6.13.19.pdf PDF
70B02C19R00000028-RSPP_RFP_Att(4)_PPQ_6.13.19.pdf PDF
70B02C19R00000028-RSPP_RFP_Att(3)_Project_Data_Sheet_6.13.19.pdf PDF
70B02C19R00000028-RFP_6.13.19.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SCOPE

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

STATEMENT OF WORK

FOR THE

RIVERINE SURFACE PATROL PLATFORM

This Statement of Work (SOW) describes the installation, integration, performance, test, delivery, and logistical support requirements for the U.S. Customs and Border Protection (CBP), Air and Marine Operations (AMO) Riverine Surface Patrol Platform (RSPP).

The vessel shall be designed to: conduct operations on rivers, lakes, marshlands, and inland waterways including areas of deep moving river waters, small rapids, partially exposed sand and gravel bars, and areas of extremely shallow water where other marine platforms are incapable of navigating. The safety of agents and others is of the highest priority; design and construction of the vessel(s) shall take safety into consideration at all times.

The Contractor shall have total program responsibility for ensuring that the requirements in this SOW and the RSPP Performance Specification are met. The Contractor shall provide program management, engineering, procurement, fabrication, manufacturing, installation, integration, testing, and delivery of the vessel. All standard factory equipment shall be of the manufacturer’s commercial model, unless otherwise noted, and shall be provided as specified herein.

2. BACKGROUND

For over 60 years the U.S. Border Patrol (USBP) has conducted riverine operations (patrolling, surveillance, and deterrence). The USBP conducts active riverine patrolling of border rivers, lakes, marshlands and restricted waterways serving as a deterrent to criminals and illegal entrants attempting to cross the border.

USBP is currently performing these riverine operations using a mix of riverine surface patrol platforms (airboats) obtained over time. The current fleet of 18 vessels is eclectic, aging, non-standardized, and is viewed as inadequate to meet the current and future USBP capability needs to secure the nation’s borders. USBP’s forecasted mission requirements call for a possible total fleet of 33 RSPP vessels to enable border security operations in restricted waterways along the nation’s borders. CBP intends to field the full fleet of RSPP vessels through a combination of the procurement of new vessels and the retrofit and standardization of existing legacy vessels to meet USBP mission requirements. The decision on whether to retrofit or purchase will be based up on a cost analysis performed between the Program Management Office and the National Marine Center.

Currently, USBP conducts riverine operations in restricted waterways along the Southwestern border areas. Future USBP Riverine Operations may be conducted along all portions of the Southern and Northern Border sectors that have border rivers, lakes, marshlands, and restricted waterways depending on USBP determined mission and operational risk assessments.

3. APPLICABLE DOCUMENTS

Throughout this SOW, as well as in the RSPP Performance Specification, the amendment or revision in effect as of the date of release of this solicitation shall apply. Where industry standards such as the American Boat and Yacht Council (ABYC) and the American Society for Testing Materials are referenced, the issue or revision in effect on the date of release of this solicitation shall apply. In case of inconsistency between this specification and the documents referenced herein, the following order of precedence applies:

a. Performance Specification requirements;

b. Statement of Work requirements;

c. Manufacturer equipment installation requirements to retain valid warranties;

d. Government specifications and standards, industry standards, and similar referenced documents.

4. GENERAL REQUIREMENTS

To meet CBP operational requirements, the Contractor shall design, build, integrate, test, and deliver vessels in accordance with the RSPP Performance Specification. All structural installations shall be accomplished in accordance with the Contractor’s technical drawings. The technical drawings will be reviewed and approved by the Contracting Officer (CO) and Contracting Officer’s Representative (COR) before proceeding with manufacturing of the initial vessel. All material and equipment for the construction and outfitting of the vessel shall be new.

The Contractor shall be responsible for procuring and safeguarding the materials and components necessary to construct and equip the vessel. The Contractor shall also safeguard Government Furnished Equipment (GFE) provided to the Contractor, if any. The Contractor shall be responsible for procuring all tooling, test equipment and Contractor-Furnished Equipment (CFE) necessary for ensuring completion as outlined by this SOW. To reduce costs and enhance equipment and machinery availability and support, the Contractor shall utilize Commercial Off the Shelf (COTS) equipment to the maximum extent possible. The following criteria apply to the safeguarding of all parts and equipment:

a. The Contractor shall assume full responsibility for installation, maintenance, and test of CFE.

b. Upon receipt, GFE shall be entered into the Contractor’s asset control process for inventory control prior to delivery.

c. In the event any GFE item does not meet its approved test specifications, the Contractor shall request the disposition of the item from the CO or COR.

Unless otherwise noted, any reference to “days” shall mean “calendar days.”

4.1 Materials

Except as otherwise provided, the Contractor shall furnish all materials, supplies, equipment, and personnel for the performance of this SOW. The Contractor shall ensure that all materials conform to the requirements specified in the RSPP Performance Specification.

4.2 Performance Period

The period of performance for this Indefinite Delivery Indefinite Quantity contract will consist of five Ordering Periods. A minimum of one RSPP will be acquired during the base ordering period of this contract for Operational Test and Evaluation (OT&E). Upon successful completion of the First Article testing and the OT&E, up to 9 additional vessels may be authorized during the base year of this contract.

4.3 Invoices

The Contractor shall submit the invoice upon notification from the COR of vessel delivery at delivery site. COR notification will be provided electronically through the DHS 700-12 form.

The Contractor shall identify the funding "breakout" on invoices by Line Item Number. After a review of the invoice by the COR, the invoice will be approved and sent to the CBP Office of Finance for payment.

4.4 Personnel Resources and Staffing

The Contractor shall provide a list of names and proposed duties of the professional personnel, consultants, and subcontractor employees assigned to the project (CDRL A017). Additionally, resumes for all "key personnel" in Section 6.1 of this SOW shall be provided and shall include information on education, background, recent work experience, and specific scientific or technical accomplishments. The Contractor shall provide an organization chart that clearly depicts the means of communication between its team members, management, and subcontractors. The Contractor shall notify the Government of, and submit to the Government for approval, any changes to key personnel and consultant or subcontractor relationships related to the project within 10 calendar days of the change.

4.5 Workmanship

The Contractor shall ensure that all parts fabricated and installed in connection with the tasks specified in the RSPP Performance Specification conform to good engineering and industry best practices.

4.6 Existing Technical Solution

The proposed hull form and overall vessel design must be similar to an existing technical solution previously produced by the Contractor. The existing technical solution must include at least five or more vessels in production and deployment, and shall have a minimum of two years of successful deployment in commercial, recreational, or government service in a similar manner and environment in which the RSPP is expected to operate.

4.7 Equipment Substitutions and Configuration Management Program

After the vessel baseline configuration has been defined and accepted, modifications, equipment substitutions or relocation of items in subsequent vessels shall be proposed to the Government for approval prior to any changes being made by the Contractor and shall be documented in accordance with the configuration change process defined by the Configuration Management Plan.

The Contractor shall establish and maintain a Configuration Management Program that satisfies project objectives and meets the requirements of ANSI/EIA-649-A 2004 and the RSPP

Performance Specification. The product of the compliant Configuration Management Program shall be a Configuration Management Plan (CDRL A005). Through the Configuration Management Plan, the Contractor shall use Engineering Change Proposals and Request for Deviations to request changes to an approved baseline. The Configuration Management Plan shall provide: configuration identification, control, and status accounting of the vessel, its components, support equipment, and documentation.

If changes are required or requested by the Government, they will be communicated to the Contractor by the CO and shall also be documented in accordance with the Configuration

The Contractor shall notify the Government within five calendar days of becoming aware of equipment obsolescence and shall initiate a change order in accordance with the Configuration

Equipment substitutions and configuration changes shall be documented, and the revised documentation shall be provided to the CBP National Marine Center (NMC) with the delivery of the first RSPP that has been modified according to the changed configuration.

The Contractor will bear all costs associated with substituting any equipment on new vessels where the reason for substitution is component obsolescence . The Contractor will implement an Obsolescence Plan (CDRL A018) to minimize equipment being rendered obsolete during the duration of the vessel acquisition contract.

4.8 Service Life

The hull, hull protection system, and trailer shall have a service life of at least three years before replacement or a service extension is required. The RSPP will be stored uncovered on the trailer when not in operation.

4.9 Risk Management

The purpose of the risk management process is to continuously identify, analyze, mitigate, and monitor the risks to the program. The Contractor shall support the Government’s risk management process and procedures to systematically control the project’s ability to meet cost, schedule, and performance requirements.

4.10 Schedule and Deliverables

The Contractor shall develop and maintain a Production Schedule, which includes task identification, milestone identification, and status for the work to be accomplished under this SOW within 15 calendar days after contract award (CDRL A001). The delivery of the Production Schedule will be considered the program schedule baseline, which may be updated as needed.

The Production Schedule will be used by CBP to develop the program Integrated Master Schedule, which will be validated and shared with the Contractor.

The First Article shall be complete and ready for Government Acceptance Inspections 120 calendar days after receipt of order (ARO). First Article Acceptance Inspection shall commence and be performed by the government on the first vessel produced under this contract at the Contractor’s facility, and will validate the Contractor’s adherence to the RSPP Performance Specification and this SOW. Upon completion of a successful First Article Acceptance Inspection, the vessel shall be delivered to the NMC at 71 Binninger Drive, St. Augustine, Florida 32095. The First Article will undergo Delivery Acceptance, whereupon CBP will take possession of the RSPP. Following delivery and possession, the Government will conduct an Operational Test and Evaluation (OT&E), validating the operational performance of the vessel according to the RSPP Performance Specification. The Government will complete OT&E and the subsequent report will be issued within approximately 60 calendar days from completion of OT&E. The CO shall notify the Contractor in writing of the status of the approval or disapproval of the vessel according to OT&E results. This notification shall state any further action required from the Contractor with regards to the First Article and/or subsequent vessels.

The vessel configuration baseline will be established and certified after OT&E is performed upon the First Article and shall be applied to any subsequent vessels constructed by the Contractor.

The Contractor shall not begin performance on Second Article or further Delivery Orders until issuance of the notice to proceed by the CO.

The Second Article shall incorporate all feedback from OT&E and shall be complete and ready for Government Acceptance Inspections within 90 days after the issuance of the notice to proceed.

With the exception of the 90 days allowed for the Second Article after incorporating OT&E feedback, vessels in subsequent Delivery Orders shall be complete and ready for Government Acceptance Inspections at a rate of not more than 30 days each. Vessels shall be delivered to USBP operational sites to be determined by the COR and provided to the Contractor.

a. Production Progress Reports

After the issuance of the first Delivery Order, and subsequently throughout the life of the contract, the Contractor shall submit monthly Production Progress Reports to the Government (program or project manager (PM, CO, and COR)). The first monthly report is due no later than 30 calendar days after receipt of order and each subsequent report will be due 30 calendar days thereafter until all of the vessels required under the delivery order are delivered to the Government. Monthly Progress Reports shall provide information as to project progress and risks as well as reflect any task that is impacting a critical path against the delivery schedule.

Upon receipt of the report, the Government will determine the sufficiency of the information provided and will provide the Contractor with feedback to incorporate into the report as necessary for acceptance. (CDRL A002).

b. Quality System

The Contractor shall maintain a quality system for the vessel. All deficiencies reported by the Government according to the requirements in the Performance Specification and this SOW shall be corrected prior to Government acceptance. The Contractor shall provide its Quality Assurance Plan to the Government within 30 days ARO the first delivery order (CDRL A003).

The Contractor’s approved Quality Assurance Plan shall be incorporated into contract requirements. Monthly discrepancy reports shall be communicated from the Contractor to the

Government for trend identification.

c. Warranty

1. The workmanship, performance, and operation of each RSPP and all installed systems shall be warranted by the Contractor against defects or failures under the anticipated operating conditions as outlined in the RSPP Performance Specification for a period of one year from the date of Government acceptance (CDRL A004).

2. The hull, structure, and foundations shall be warranted against manufacturer's defects or structural degradation for a minimum of three years.

3. The propulsion system, including the engine, propeller drive, and the propeller(s) shall be warrantied for a minimum of 500 operating hours or 1 year.

4. The RSPP trailer and all of its component parts shall be warranted against failure for three years on materials, parts and service.

5. A complete list of warranties will be included with the Contractor’s proposal and shall be incorporated into any resultant contract. All warranties shall be managed by the NMC.

Details on warranty management will be coordinated between the Contractor and the NMC during the post-award conference.

6. The Contractor shall establish a business relationship with the CBP contract maintenance provider to perform warranty work on the RSPP. This is a third party agreement between the Contractor and the CBP contract maintenance provider. The goal of the warranty services is to minimize operational downtime of each vessel by leveraging the CBP contract maintenance provider to provide the best possible value to CBP and provide the required operational readiness. The Contractor will not void warranties if OEM-certified, CBP-contracted maintenance personnel effect repairs in accordance with OEM direction and in compliance with approved procedures while RSPPs are operational.

d. Warranty Plan

For each warranty claim, the Contractor shall provide a written report to the NMC. The warranty report must include, at a minimum, the following items:

1. Date of report of claim

2. Date of remediation

3. Parts affected, including the vessel fleet number or hull identification number

4. Nature of casualty

5. Actions taken

6. If claim is still open, intended action

In addition, the Contractor shall provide an electronic record containing specific information for each RSPP for the purpose of NMC warranty management. This record includes, but is not limited to, all serial numbers for serialized components installed on a specific hull that apply to the RSPP. Components for which serial numbers are to be provided include:

1. Hull;

2. Engines;

3. Trailer (VIN);

4. All Radios;

5. Navigation System Equipment;

6. Components, equipment, and machinery with an acquisition cost greater than $2,500; and

7. All electronics components (regardless of cost), including electronic systems outfit.

e. System Safety Requirements

The Contractor shall maintain a system safety program that identifies all hazards associated with the design of the vessel. In addition, the Contractor shall provide a methodology to either eliminate or control those hazards. Materials and processes shall, along with other design criteria, minimize environmental impacts from the manufacture, operation, maintenance, and repair of the vessel and its subsystems. To the maximum extent practicable, all vessel structures and systems shall be constructed and installed using materials which prohibit the provision of any nutrients that support fungal growth. However, all vessel structures and systems shall operate as specified after exposure to fungal growth, should it occur. Ozone-depleting substances and any prohibited material listed in the referenced documents shall not be used in constructing the RSPP. This prohibition shall include, but is not limited to, mercury, lead paint, and cadmium-plated washers and fasteners.

5. PROGRAMMATICS

5.1 Logistics

a. General

CBP requires design, testing and logistics support information to verify contract compliance and to support its vessels throughout the life cycle.

Prior to start of construction, the CBP customer representatives and the Contractor shall meet at the Contractor’s factory to review plans and make changes as needed.

b. Program Reviews

The Contractor shall conduct regular program reviews to provide the PM, CO, and COR with the information necessary to assess the Contractor’s progress and performance with respect to the requirements of this SOW and the RSPP Performance Specification.

c. System Requirements Review

The Contractor shall provide facilities for a System Requirements Review (SRR) to accommodate approximately 10 government personnel within 30 calendar days after the first production delivery order is issued. The purpose of the SRR is to allow the Contractor to echo system requirements and present derived requirements (requirements not explicitly stated, but necessary for the fulfillment of a stated requirement) along with testing, validation, and verification methods and to review the supply support requirements for the vessel. The Contractor shall provide a copy of the proposed agenda at least 10 calendar days prior to the review and the minutes and action items from the SRR within 10 calendar days after the review

(CDRL A010).

d. Preliminary Design Review

The Contractor shall provide facilities for a Preliminary Design Review (PDR) to accommodate approximately 10 government personnel within 30 calendar days after the SRR. The Contractor shall present the preliminary design drawings for the system design and shall include, at a minimum, design and performance technical concepts, interfaces, system safety, and training.

The purpose of the PDR is to allow the Contractor to present the methodology and preliminary results of the vessel design and structural analysis to support that design effort and provide preliminary design information for the proposed design. The Contractor shall provide a copy of the proposed agenda at least 10 calendar days prior to the review and the minutes and action items from the PDR within 10 calendar days after the review (CDRL A011).

e. Critical Design Review

If required by the Government, the Contractor shall provide facilities for a Critical Design Review (CDR) to accommodate approximately 10 government personnel within 30 calendar days after the PDR. The purpose of the CDR is to allow the Contractor to present the final design drawings for the vessel design and the engineering approach to any mutually agreed upon changes identified in the PDR, including console design, material and process specifications, and test plans (to include acceptance). The Contractor shall provide a copy of the proposed agenda at least 10 calendar days prior to the review and the minutes and action items from the CDR within 10 calendar days after the review. The approved results of the CDR (to include approval of final design drawings) shall be the final requirements for design, performance, and test. Requirement changes after the CDR shall be treated as subsequent engineering changes (CDRL A012).

f. Logistics Conference

The purpose of the Logistics Conference is to review the support requirements of the vessel and associated documentation and drawings. If requested by the CO, either before or after production begins, the Contractor shall provide facilities for a logistics conference for approximately 10 government personnel for no more than 2 business days. The Contractor shall provide the agenda at least 2 days prior to the conference, and minutes from this conference no more than 15 days after the conference is complete.

g. Technical/Program Reviews

Prior to completion of the PDR and CDR, technical information meetings may be conducted to gain further clarification about the design, construction, and performance of the proposed RSPP.

Those meetings may be conducted telephonically or at the Contractor’s facility.

After completion of the PDR and CDR, the Contractor shall provide facilities for 2-day progress meetings each quarter to accommodate approximately 10 government personnel during the term of the contract to review program status.

5.2 Training

The Contractor shall provide one day of operational training at the delivery location within approximately one week after delivery of the First Article (to be coordinated with CBP). The training shall be designed so that the CBP operators become familiar with the vessel’s performance capabilities and limitations, to include all of the vessel’s onboard operating systems.

The training may include some classroom training followed by actual operation aboard the vessel. At a minimum, the training shall include start-up and shut-down procedures, warnings, casualty control, and emergency procedures. The training shall also address basic maintenance procedures and techniques.

The Contractor shall provide one day of maintenance training at the delivery location of the First Article within approximately one week after delivery for government personnel responsible for maintaining the vessel. The maintenance training shall include organizational-level and depot-level preventive and corrective maintenance for the vessel and all its systems.

6. TECHNICAL SUPPORT REQUIREMENTS

6.1 General

During the production phase, the Contractor shall provide program, technical, manufacturing, and engineering liaison management. Unrestricted access to production facilities, technical records, and vessels shall be granted to government representatives in accordance with the contract terms and conditions or upon mutual agreement of both parties. This is to include; pre-award surveys, in-progress production inspections, and photographs, should the government deem them necessary.

a. Key Personnel

i. The Contractor's Program Manager shall be the primary point of contact for the Government and shall be responsible for the entire vessel program.

The Contractor’s Program Manager shall have a minimum of five years’ experience managing vessel programs similar in scope.

ii. The Contractor’s Quality Assurance Manager shall be independent of the Plant/Production Manager and shall be responsible for implementing the Quality Assurance Plan. The Contractor’s Quality Assurance Manager shall have a minimum of five years’ experience managing a quality assurance program similar in scope. At least one year’s experience shall be within the marine field.

iii. The Contractor’s Plant/Production Manager shall be responsible for vessel manufacturing/production. The Contractor’s Plant/Production Manager shall have a minimum of five years experience managing production of a vessels program similar in scope.

b. Vessel Construction Approach

The Contractor shall describe within their proposal the extent to which their production engineering and construction approach fully supports the transition from the design to fabrication. The Contractor shall provide the following:

1. Describe the production engineering processes for extraction of data from the design model to the complete vessel.

2. Describe the planned build strategy for constructing the initial and subsequent vessels. Describe the construction approach for concurrent construction of multiple vessels at the rate indicated in the contract.

3. Describe the fabrication tolerances and the approach to accuracy control.

4. Provide a weight control plan for monitoring weight and controlling weight growth and margin consumption throughout construction.

5. Describe the approach to quality control, testing, integration testing, vessel testing, builder’s trials, and acceptance trials. Include participation of third party organizations (if applicable).

c. Care of Vessel during Construction

All parts of the vessel including, but not limited to, hull, structure, propulsion, electrical, command and control, auxiliary systems, outfit and furnishings, and weapons stowage shall be maintained in a satisfactory condition during the entire period the vessel is in the Contractor’s possession.

6.2 Engineering

a. Technical Package

1. The RSPP Proposal Technical Package shall consist of both a Narrative and Proposal Design Elements to include drawings, calculations, and analyses demonstrating that the design is sound and provides a well-balanced design that meets the RSPP Performance Specification. The Technical Package must include the following:

i. Arrangement drawings that show the complete outfit of the vessel.

Drawings shall be in plan and profile views. Drawings shall also depict access to equipment for inspection and maintenance.

ii. Hull structure drawings to include shell and deck plating, longitudinal and transverse structural members and bulkheads. It shall also include the interfaces with seat and machinery foundations.

iii. Propulsion system drawings, to include foundation and connections to the hull.

iv. Electrical one-line diagram

v. Auxiliary systems schematics or drawings, to include fuel tank, steering systems, and bilge pumps.

vi. Demonstration of quality control of items to the degree that all components of the vessel can be removed and replaced without resorting to significant additional product design effort, additional design data, or recourse to the original design activity.

2. Also desired, but not required: (these items will receive preferential ratings in the source selection:

i. Stability Analysis – CBP will evaluate the stability of the vessel per the requirements located within the RSPP Performance Specification. Any calculations provided by the Contractor will be considered.

ii. Range analysis– The Contractor may provide if test results are available on a parent craft at a measured weight in a measured water depth.

iii. Structural analysis – If provided, CBP will evaluate the vessel structure to the requirements of International Organization for Standardization BS EN ISO12215-5:2008 design category D.

7. MAINTAINABILITY REQUIREMENTS

7.1 Accessibility Requirements

Access to compartments containing equipment, machinery, or spare parts shall be provided in accordance with the RSPP Performance Specification.

a. Preservation, Packaging, and Packing of Parts and Tools

The Contractor shall inspect all material for damage, proper preservation, packaging, packing, and marking. Preservation, packaging, packing, and marking shall follow OEM requirements.

b. Provisioning Technical Data

The Contractor shall provide provisioning technical data (PTD) (CDRL A006) that is required to purchase maintenance supplies, spare parts, and replacement parts over the lifecycle of the vessel. The Contractor shall notify the COR within five business days of any changes affecting equipment or parts configurations during the performance of the contract. If such changes are required, the Contractor shall provide the Government a revised PTD and drawings, along with a draft engineering change. The PTD shall include:

1. Master Equipment List

The Contractor shall provide a master equipment list that identifies all the parts that can be assembled, re-assembled, or replaced on the RSPP (CDRL A007).

2. Preventive Maintenance and Recommended Spare Parts List

The Contractor shall submit a list of required and recommended preventative or planned maintenance procedures for the vessel to the NMC, including all installed equipment and components and the trailer. The list shall identify all parts and materials required for preventive maintenance for a 3-year maintenance cycle. Procedures shall be based on the information provided by the OEMs, and based on the Contractor’s experience. Each recommended procedure listed shall identify the equipment or component requiring maintenance, identification of any parts required, the maintenance to be performed, the reference to the technical manual, and the frequency of the procedure. (CDRL A008).

3. Special Tools and Test Equipment

If required, the Contractor shall provide a list of special tools and test equipment. Associated software pertaining to the installed equipment is deemed a special tool.

4. Long Lead Time Parts List

The Contractor shall provide a list of long lead time parts that require more than 30 days to acquire (CDRL A009).

8. INSPECTION, TESTING, ACCEPTANCE AND DELIVERY

8.1 Inspection (Government Contract Quality Assurance)

a. General

During the performance of the contract, the Contractor shall provide the Government access to the production facility to perform quality assurance inspections. Quality assurance inspections will be performed to determine conformity to the contract requirements. Quality assurance inspections are in accordance with the inspection clause 52.246-2 of Federal Acquisition Regulation (FAR) Part 46.

The Contractor shall certify to the government the item or items offered for acceptance and delivery comply with the contract and these requirements through process controls, inspections, and vessel trials. Process controls are the preferred method for Contractor quality assurance. The government, at its discretion, may witness such Contractor process controls or inspections.

b. Pre- and Post-Operation Checks

Launch, dock trials, sea trials, and recovery will be performed by Government Acceptance Testcrews and the Contractor’s representative prior to and after each underway period during acceptance trials in accordance with the Contractor-developed and government-approved checklists. (CDRL A019)

1. Pre-Operation Checks may include, but are not limited to: inspection of all outfit and systems; record of engine hours, check all fluid levels, filters, valves, belts and hoses; check engine and control systems; operate bilge pumps; record fuel levels; and check electronics, battery voltages, lights, and drain plugs.

2. Post-Operation Checks may include, but are not limited to: inspecting hull, engines, engine hours, electrical, electronics, bilge pumps, control systems, fuel levels, and above and below decks for loose or broken fittings or gear adrift; and washing vessel with fresh water.

8.2 Builder’s Trials (Developmental Testing and Evaluation) and Documentation

a. General

On completion of the construction of the vessel and prior to the Government’s Acceptance Trials, all tests listed in this section shall be successfully completed by the Contractor on every vessel. All material, fuel, labor, power, equipment, and instruments necessary to conduct all tests shall be furnished by the Contractor.

The Contractor shall inspect and test each vessel in accordance with the RSPP Performance Specification and this SOW to verify that all requirements of the contract are met prior to delivery. Dock and sea trials shall be conducted by the Contractor on all vessels ordered under this contract. Those trials may be witnessed by the program or project manager, COR, or an approved designee to determine that the RSPP and its mission equipment are in conformity with the specification. The Contractor shall submit Dock and Sea Trial Test Plans that include a description of all the tests to be performed and shall confirm the dates with the COR at least 14 calendar days prior to those trials (CDRL A013). The Contractor shall supply all test results in a report that shall be submitted to the CO for review and approval. (CDRL A014).

The Contractor shall prepare a testing check sheet that certifies that each test has been completed.

The check sheet shall indicate the actual weight of the vessel in Light Condition. This check sheet shall be provided as an enclosure to the technical manual. The Contractor shall maintain records of testing for each vessel for a minimum of five years from the date of the test. Records shall be available for review by the Government upon request during the life of the contract. The testing documentation shall be provided to the NMC within 45 days of the end of the contract.

b. Machinery and Systems Test

All machinery systems and equipment shall be operated to demonstrate proper functionality and conformance to requirements. If provided by the OEM, the Contractor shall follow OEM recommendations with regards to engine break-in.

c. Electrical Test

The electrical system shall be inspected and operated to ensure both compliance with the requirements and correct connections of all components.

d. Navigational Lights Test

The navigational light installation shall be inspected and tested to ensure the system conforms to the location and arcs of visibility requirements of the International Regulations for Preventing Collisions at Sea 1972 (COLREGs).

e. Starter and Alternator Tests

In conjunction with a pre-trial test of the propulsion engine, the engine starting and charging systems shall be operated to ensure proper functionality. With the engine running, the alternator and voltage regulator operation shall be inspected to ensure proper operation as specified by the manufacturer.

f. Electrical Equipment Operation Test

Testing shall be accomplished to verify proper voltage and polarity of each circuit and proper distribution through the power panel. Each load shall be tested to confirm correct operation of the load and switches or other controls.

g. Weight Test

Each RSPP shall be scale weighed in Light Condition to verify the actual scale weight of each vessel. The vessel shall be fully complete with all outfitting, including CFE and GFE installed prior to weighing.

h. Communication and Radio Test

The Contractor shall perform testing to verify the proper installation and operation of the communications and radio systems.

8.3 Acceptance Trials Conducted by the Government

a. General

Government Acceptance Trials shall not be performed until the vessel is in all respects ready for delivery (except for final cleaning and preparation for shipment), all Builders Trials have been satisfactorily completed, and the Builder’s Trials test reports have been submitted and approved.

Acceptance Trials shall be completed prior to delivery. The Contractor shall notify the Government whether the vessel is ready for testing not less than 15 days prior to the start date of the Acceptance Trials.

The Government will first perform a visual acceptance inspection of the vessel and trailer, and will provide a detailed list of any discrepancies to the Contractor for resolution. Upon successful completion of the visual acceptance inspection, the government will conduct dock and sea acceptance testing of the vessel. Testing shall be sufficient to determine that the vessels:

1. Meet Key Performance Parameters and other performance requirements as stated in the RSPP Performance Specification and this SOW.

2. Conform to the Contractor’s written proposal.

Acceptance trials may include, but are not limited to, the following:

b. Speed Trials

Speed trials shall be conducted in the Normal Load Condition in water no less than 4 feet over the trial course. Two runs shall be made over the course for each speed, one in each direction with the speeds for the two runs averaged.

c. Steering and Maneuvering Performance

The vessel shall be tested to demonstrate the proper operation of the propulsion and steering systems under all mission representative situations.

Maneuvering tests shall be performed to ensure that the vessel meets the requirements set forth in the Performance Specification. Maneuvering trials shall be conducted in Normal Load Condition and repeated in the Overload Condition.

d. Fuel Consumption Trial

The vessel shall undergo a fuel consumption trial running at the most economical planing speeds in Normal Load Condition for 25 nautical miles in sea state 1. Total fuel consumption shall be recorded and range computed.

e. Electronic Equipment Trials

All electronics and associated equipment shall be operated during acceptance trials. This shall include the satisfactory simultaneous operation of all equipment. During the acceptance trial it shall be demonstrated that all components of the vessel’s systems are integrated and fully operational.

f. Reliability Trials

The Contractor shall monitor and record the reliability of the vessel during all on-water trials.

The Contractor shall report the nature and circumstances of each component failure.

8.4 Other Trials Conducted by the Government

a. Operational Test and Evaluation (OT&E)

OT&E shall commence upon completion of First Article delivery and should end within approximately 60 calendar days after completion. The purpose of the OT&E will be to determine if the RSPP is operationally suitable and ensure that it meets performance criteria outlined in the RSPP Performance Specification.

The Government may, at its discretion, accomplish additional testing during acceptance trials as described herein. Testing may consist of, but is not limited to, the following:

1. Noise Trials - Onboard noise trials will be conducted to establish or verify the baseline noise level.

8.5 Delivery

b. First Article

Upon completion of a successful First Article Acceptance Inspection, the vessel shall be delivered to the NMC at:

71 Binninger Drive St. Augustine, Florida 32095

The First Article will undergo Delivery Acceptance, whereupon CBP will take possession of the RSPP. Following delivery and possession, the Government will conduct an Operational Test and Evaluation (OT&E).

c. Other Orders

After receipt of the findings from the Operational Test and Evaluation and resolution of any issues found during that testing required to be addressed, other vessels shall be delivered to one of three Areas of Operation: Del Rio, Texas; Laredo, Texas; or McAllen, Texas.

9. TRANSPORTATION, SHIPPING, AND STORAGE OF VESSEL

a. Prior to shipping, the vessel shall be cleaned, systems preserved and covered. Bilges shall be dry and free of oil and debris. A disposable shrink wrap cover shall be provided to protect the vessel and engines during shipping to the designated delivery location. The cover shall have vents to prevent moisture and vapor buildup.

b. The propulsion system shall be preserved in accordance with the OEM recommendations for transportation, and must account for storage of up to six months in areas that may be subject to freezing temperatures.

c. All batteries shall be disconnected.

d. Unless specifically requested by the Government, all vessels shall be stored and shipped with all fixed outfit items installed in their normal position. Removable and folding appendages may be lowered, raised, or removed and stored on the vessel during shipping and storage.

e. Each vessel and its trailer shall meet all statutory limits for legal operations on the interstate highway system.

f. The maximum height of the vessel on its trailer shall not exceed 12 feet and 8 inches.

Vertical antennas may be hinged or otherwise lowered to meet height restrictions, provided the antennas may be returned to their operational position within 5 minutes without the use of power tools or special equipment.

g. Upon arrival, vessels shall be examined for quality, damage in transit, and unauthorized equipment substitution.

h. Contractor bears the risk of loss or damage to the vessel during transit to final destination.

10. TECHNICAL MANUALS, REPORTS, DATA, AND DRAWINGS

10.1 General

CBP requires design, testing, and logistics support information to verify contract compliance and to support its vessels throughout the life cycle. The Contractor shall provide to the COR and PM technical manuals and data reports in paper and an electronic copy of the Boat Information Book (BIB) with First Article vessel. 2D plans shall be provided in AutoCad and PDF formats.

The 3D model shall be provided in Rhinoceros format. The Contractor must furnish electronic copies only with follow- on vessels. The electronic format shall allow embedded text and graphics and shall be in Microsoft® Office Word format or Microsoft® Office Excel format (where applicable). COTS manuals from vendors that are not in the above format shall be an unlocked PDF file. (CDRL A015).

10.2 Technical Publications

The following Technical Publications are required to be delivered electronically and in paper copy with First Article vessel and electronic only for subsequent vessels delivered. Updates shall be electronically provided quarterly for each vessel:

a. Boat Information Book (BIB)

The BIB shall provide a complete description of the vessel's capacities and characteristics, including operating instructions for all systems, equipment, and components installed (to include wiring). The BIB shall be delivered in both paper and electronic format for the First Article, and electronic format only for subsequent vessels. The BIB will include all technical publications and manuals with the exception of COTS items. System diagrams shall be included to supplement the written descriptions. Upon approval of the Contracting Officer, system working drawings may be used in lieu of the diagrams. ABYC T-24 “Owner’s Manuals” shall be used as guidance when developing the content of the BIB.

1. Technical Manual: A technical manual shall be included in the BIB (except COTS) and shall be provided for all equipment and accessories of the vessel. It shall provide the requisite information to provide instructions to operate and maintain the equipment at the organizational level. This includes a description of system start up, operation, shutdown, safety, and emergency procedures. The manual shall also contain information concerning checkout, inspection, preventive and corrective maintenance, calibration, adjustment, troubleshooting, replacement of parts, repair, and use of tools and test equipment in accordance with the maintenance concept. At a minimum, the Technical Manual shall include:

i. General Information and Safety Precautions: An introduction to identify the equipment, equipment description, location, associated equipment, general safety instructions, and drawings or diagrams showing general arrangements.

ii. Emergency Procedures: Identify conditions requiring emergency operations and provide procedures to be followed in the event of their occurrence. “Emergency operation” is defined as operation under conditions of system malfunction or failure, such as loss of power, component failure, physical damage, or fire. Detailed step-by-step procedures for dealing with emergencies shall be provided.

iii. Troubleshooting Guide/Aid and Procedures: Identify and provide step-by-step troubleshooting procedures for determining causes of equipment/system malfunction or failure, isolating affected systems, and replacing components.

iv. System Limitations, Precautions, and Set Points: Identify all system operational limitations. State all precautions to be taken during normal operation to prevent potentially unsafe conditions. List system operation and safety set points, which represent the normal operation of the system.

10.3 Technical Manual Update Revisions

If changes to an existing technical manual affect 25 percent or more of the original pages in the manual, or if the scope of the changes are so material as to render the existing technical manual unreliable, as determined by the Government, the manual shall be revised in its entirety.

Format: A revision incorporates the basic manual, previous changes, and new data that would require the issuance of an additional change.

Preparation: Preparation shall conform to the style and format used in the basic manual.

Manual Numbering: The manual shall not be assigned a new Technical Publication Number. It will use the existing Technical Publication Number along with an “alpha” character.

Deliverables: One paper and one electronic copy of the CBP approved Technical Publication Revision shall be provided to the CBP Contracting Officer or his or her representative.

Electronic files shall be prepared as indicated at the beginning of this section. Electronic files include any source files used to produce the Technical Publication.

Data Rights: The Contractor shall provide data rights documentation that allows publication on the CBP Intranet (internal to CBP). See FAR 52.227-14, Rights in Data – General.

10.4 DRAWINGS

The Contractor shall provide structural and systems drawings for the use, maintenance, modification, and repair of the vessel (CDRL A016).

For the duration of the contract and for five years after the delivery of the last vessel, the Contractor shall retain all drawings for use, repair, and replacement of removable parts, modification of the vessel, and to facilitate contracted maintenance and repair as directed by the

NMC.

a. Drawing Versions

The Contractor shall provide drawings for the vessel.

Drawings shall be retained by the Contractor throughout the contract period of performance. The final drawings are the construction drawings which have been revised and updated to reflect the “as built” configuration of the vessel after acceptance by the Government at the successful conclusion of OT&E.

The Contractor shall also provide revised drawings with CBP fleet number applicability for any changes in construction or in components where the new component is not a full “form, fit, and function” replacement for the original component.

b. Required Drawings

1. Required drawings shall consist of those drawings referenced in 6.2.a “Technical Package” of this SOW.

CONTRACT DATA REQUIREMENTS LIST

DATA

NO.

DATA TITLE

CONTRACT

REFERENCE

FREQUENCY

SUBMISSION

DATE

DISTRIBUTION

A001

Production Schedule

SOW Para 4.10

Monthly until delivery of the last vessel

Within 15 calendar days after contract award

1 electronic copy

A002

Production Progress Reports

SOW Para 4.10.a

Monthly until delivery of the last vessel

First report within 30 calendar days after contract award

A003

Quality Control

SOW Para 4.10.b

Every vessel

Within 30 days of ARO

A004

Manufacturer and Vendor Warranties

SOW Para 4.10.c

Upon delivery of vessel

1 hardcopy;

A005

Configuration Management Program

SOW Para 4.10.f

As required

Within 5 days after system req. review

A006

Provisioning Technical Data

SOW Para 7.1.b

Within 30 days after critical design review

A007

Master Equipment List

SOW Para 7.1.b.1

At acceptance

A008

Preventive Maintenance and Recommended Spare Parts List

SOW Para 7.1.b.2

A009

Long Lead Time Parts List

SOW Para 7.1.b.4

A010

System Requirements Review Minutes

SOW Para 5.1.c

One time

Within 10 calendar days before or after SRR

A0011

Preliminary Design Review Minutes

SOW Para 5.1.d before or after design review

A0012

Critical Design Review Minutes

SOW Para 5.1.e before or after design review

A013

Builder’s Trials and Inspection Plan

SOW Para 8.2.a

Within 14 calendar days prior to trials

A014

Builders Trials and Inspection results

SOW Para 8.2.a

Within 5 calendar days after the trials

A015

Technical Manuals, Reports, and Data

SOW Para 10.1

Upon Delivery of Vessel

A016

Drawings

SOW Para 10.4

Quarterly

At CDR and with any configuration updates

2 hardcopies;

1 CD copy

A017

Personnel Resources and Staff

SOW Para 4.4

At SRR and updates with Key Personnel movement

A018

Obsolescence Plan

SOW Para 4.7

Within 30 Days After Critical Design Review

A019

Pre and Post Operation Checklists

SOW Para 8.2

15 days prior to Acceptance of First Article

STATEMENT OF WORK (SOW)

FOR THE

RIVERINE SURFACE PATROL PLATFORM

DOCUMENT REVISION HISTORY

Version Number Date Description

Revision 1 April 24, 2018 Original Document V.1.1 July 12, 2018 Pre-Award revised original document with input from SME’s and OCC.

V.1.2 August 2, 2018 Pre-Award revised document after USBP

CONOPS/ORD revision.

V.1.3 June 11, 2019 Pre-Award Clarifications after Contracts and