02.02.01 - Final SOW_Roofing Build Material for DR4715GU - 06.04.2023.docx
DOCX document 1 MB Posted
- Attached to
- Roofing Build Material DR-4715-GU Federal contract opportunity
- Solicitation number
- 70FBR923Q00000018
- Issued by
- Federal Emergency Management Agency
About this file
This statement of work outlines requirements for roofing materials to support recovery efforts in Guam following Super Typhoon Mawar. The Federal Emergency Management Agency requires delivery of various roofing components including metal roofing panels, rafters, purlins, fasteners and other hardware. Materials must be packaged for air or ocean transport and delivered within 48 hours of award to the FEMA distribution center in Tracy, California. The statement of work provides specifications for approximately 60,000 individual items across 15 material types to construct temporary roofs for 500 structures damaged by the typhoon. Pricing and response deadlines are not specified.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 02.02.01 - Quote Pricing Template.xlsx | XLSX spreadsheet | |
| 02.02.01 - Request for Quote - Roofing Build Material DR4715GU.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Homeland Security (DHS) DHS Statement of Work (SOW)
Federal Emergency Management Agency
STATEMENT OF WORK (SOW) FOR:
Roofing Build Material for DR4715GU
Demetria Carter, Contracting Officer
PROCUREMENT SENSITIVE INFORMATION
This document contains non-public information intended for use on a need-to-know basis within FEMA only.
Please protect this document as procurement sensitive and handle accordingly.
STATEMENT OF WORK (SOW)
DEPARTMENT OF HOMELAND SECURITY (DHS)
FEDERAL EMERGENCY MANAGEMENT AGENCY (FEMA)
ROOFING BUILD MATERIAL FOR DR4715GU
1. BACKGROUND
The US territory of Guam has experienced extreme wind and flooding on Wednesday 24, 2023 with super Typhoon Mawar. Guam experienced moderate to severe damage to residences, displacing residents. To address the needs for sheltering and recovery, FEMA is authorizing Direct Federal Assistance for the Emergency Temporary Roofing Program. Where safe and practicable, the Emergency Temporary Roofing Program may enable residents to return to or remain in their homes as a form of shelter while permanent repairs are completed. In agreement with United States Army Corps of Engineers (USACE), FEMA will procure and deliver roofing build material for temporary roofing program use.
2. SCOPE
The contractor shall supply and deliver building materials as described in the temporary roofing mission Build of Material (BoM) list.
3. OBJECTIVE
The desired goal of this solicitation is to obtain the required building materials at the needed quantities for the Emergency Temporary Roofing Program operating in Guam.
4. SPECIFIC REQUIREMENTS/ PRODUCT SPECIFICATIONS
4.1. The contractor shall deliver building materials at the required order quantities from the temporary roofing mission Build of Material (BoM) list:
| Material Need per Structure** |
| Size |
| Quantity |
(Per Structure)
| Unit |
| Structures |
(Per Mission) Total Quantity
| Ridge Cap - Galvalume |
| 12' |
| 4 |
| Each |
| 500 |
| 2,000 |
| Metal Roofing Panels (24-gauge w/ no greater than 1" ridges) - Galvalume |
| 36" x 12' |
| 20 |
| Each |
| 500 |
| 10,000 |
| Roof Rafters (@24" o/c max) – Non-Pressure Treated Lumber |
| 2" x 6" x 12' |
| 10 |
| Each |
| 500 |
| 5,000 |
| Roof Purlins (@24" o/c max) – Non-Pressure Treated Lumber |
| 2" x 4" x 12' |
| 10 |
| Each |
| 500 |
| 5,000 |
| Self-tapping Galvanized Roofing Screws w/ Neoprene Washers |
| 2.5" |
| 10 |
| lbs. |
| 500 |
| 5,000 |
| Galvanized Common 16d Nails |
| 3.5" |
| 10 |
| lbs. |
| 500 |
| 5,000 |
| Rafter Hanger Brackets, 18 gauge, Galvanized |
| 3-2/7” |
| 10 |
| Each |
| 500 |
| 5,000 |
| Sill Attachment Plate – Non-Pressure Treated Lumber |
| 2" x 6" x 12' |
| 2 |
| Each |
| 500 |
| 1,000 |
| Beams at Centerline – Non-Pressure Treated Lumber |
| 2" x 8" x 12' |
| 2 |
| Each |
| 500 |
| 1,000 |
| Strap Ties, 12 gauge, Galvanized Steel |
| 1.375" x 12' |
| 8 |
| Each |
| 500 |
| 4,000 |
| Common 10d Nails, Galvanized |
| 1.5" |
| 1 |
| lbs. |
| 500 |
| 500 |
| Tapcon Concrete Screws |
| 1/4" x 3" |
| 50 |
| Each |
| 500 |
| 25,000 |
4.2. The contractor shall package all building materials so that they are ready to be transported by FEMA to Guam by air or ocean transport. Specifically:
4.2.1. Metal Roofing Panels shall be packaged in wooden shipping crates with 100 units per crate. Attachment #1 to this SOW provides a picture of the wooden shipping crates as an example.
4.2.2. All other building materials shall be packaged in sturdy shipping boxes. Material must be packaged in such a manner as to afford adequate protection to the item against corrosion, deterioration, and physical damage during shipment.
4.2.3. All building material packages shall be clearly labeled with its contents, listing the type of building material and quantity included in the package.
4.2.4. Material must be accompanied by an itemized packaging list securely attached to the outside of the shipment.
4.2.5. All packing lists shall cite the contract number with the packaging in such a manner to ensure identification of the material provided.
4.3. The contractor shall deliver building materials within 48 hours of award.
4.4. The contractor shall deliver building materials to the following location:
FEMA Distribution Center Tracy, 1547 E. Grant Line Road, Tracy CA 95304
5. PERIOD OF PERFORMANCE
Delivery shall be made within 48 hours after award.
6. PLACE OF PERFORMANCE
The contractor shall deliver building materials to:
FEMA Distribution Center Tracy, 1547 E. Grant Line Road, Tracy CA 95304
7. GOVERNMENT FURNISHED RESOURCES
The Government will not furnish any resources to the Contractor in support of this contract.
Attachment #1
| June 2021 2 | |
| Learn more at fema.gov | June 2021 1 |
image1.jpg image2.png
File details come from the government source that posted it. Updated .