Project Grant 33200140112024

Award Date 1/16/24
Completion Date 1/15/28
Dollars Obligated $1.1M
Federal Grant Program
20.106
Assistance Type
Project Grant
Place of Performance
North Las Vegas, NV 89030, USA

This federal Project Grant award from the Federal Aviation Administration (FAA) under the Airport Improvement Program (CFDA 20.106) provides $1,138,133.33 in funding to the Clark County Airport System (doing business as the Department of Aviation) to reconstruct 831 feet of the existing Taxiway A pavement at an airport in Overton, Nevada. This grant covers approximately 37% of Phase 2 of a 2-phase project to address the aging taxiway infrastructure. The project, with a target completion date of January 15, 2028, is intended to enhance the safety, efficiency, and modernization of the airport facilities in southern Nevada.

Generated 10/29/24, 2:28 AM