6 TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE ARRA PROJECT- DESIGN AND FABRICATE INTERPRETIVE SIGNS ON VARIOUS TRAILS AND PATHS AROUND MAMMOTH LAKES, THIS PROJECT IS A PARTNERSHIP BETWEEN THE TOWN OF MAMMOTH LAKES AND FOREST SERVICE THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: A. CHANGE THE CALENDAR DAY COMPLETION OF 731 DAYS TO 751 DAYS. THEREFORE, THE NEW DELIVERY DATE IS CHANGED FROM SEPTEMBER 1, 2012 TO SEPTEMBER 21, 2012. B. THIS MODIFICATION IS PROCESSED AT NO ADDITIONAL COST TO THE GOVERNMENT. C. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. Change Order $0 9/13/12 5 TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE ARRA PROJECT- DESIGN AND FABRICATE INTERPRETIVE SIGNS ON VARIOUS TRAILS AND PATHS AROUND MAMMOTH LAKES, THIS PROJECT IS A PARTNERSHIP BETWEEN THE TOWN OF MAMMOTH LAKES AND FOREST SERVICE THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: A. CHANGE THE CALENDAR DAY COMPLETION OF 486 DAYS TO 731 DAYS. THEREFORE, THE NEW DELIVERY DATE IS CHANGED FROM DECEMBER 30, 2011 TO SEPTEMBER 1, 2012. B. THIS MODIFICATION IS PROCESSED AT NO ADDITIONAL COST TO THE GOVERNMENT. C. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. Change Order $0 1/11/12 4 TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE ARRA PROJECT- DESIGN AND FABRICATE INTERPRETIVE SIGNS ON VARIOUS TRAILS AND PATHS AROUND MAMMOTH LAKES, THIS PROJECT IS A PARTNERSHIP BETWEEN THE TOWN OF MAMMOTH LAKES AND FOREST SERVICE THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: A. CHANGE THE CALENDAR DAY COMPLETION OF 395 DAYS TO 486 DAYS. THEREFORE, THE NEW DELIVERY DATE IS CHANGED FROM SEPTEMBER 30, 2011 TO DECEMBER 30, 2011. B. THIS MODIFICATION IS PROCESSED AT NO ADDITIONAL COST TO THE GOVERNMENT. C. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. Change Order $0 9/28/11 3 TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE ARRA PROJECT- DESIGN AND FABRICATE INTERPRETIVE SIGNS ON VARIOUS TRAILS AND PATHS AROUND MAMMOTH LAKES, THIS PROJECT IS A PARTNERSHIP BETWEEN THE TOWN OF MAMMOTH LAKES AND FOREST SERVICE THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: A. CHANGE THE CALENDAR DAY COMPLETION OF 288 DAYS TO 395 DAYS. THEREFORE, THE NEW DELIVERY DATE IS CHANGED FROM JUNE 15, 2011 TO SEPTEMBER 30, 2011. B. THIS MODIFICATION IS PROCESSED AT NO ADDITIONAL COST TO THE GOVERNMENT. C. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. Change Order $0 5/17/11 2 TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE ARRA PROJECT- DESIGN AND FABRICATE INTERPRETIVE SIGNS ON VARIOUS TRAILS AND PATHS AROUND MAMMOTH LAKES, THIS PROJECT IS A PARTNERSHIP BETWEEN THE TOWN OF MAMMOTH LAKES AND FOREST SERVICE THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: A. CHANGE THE CALENDAR DAY COMPLETION OF 196 DAYS TO 288 DAYS. THEREFORE, THE NEW DELIVERY DATE IS CHANGED FROM MARCH 15, 2011 TO JUNE 15, 2011. B. THE FOREST SERVICE WILL NO LONGER PROVIDE PHOTOS TO THE CONTRACTOR. THE CONTRACTOR WILL ACQUIRE THE PHOTOS THROUGH AN AGREEMENT WITH THE EASTERN SIERRA INTERPRETIVE ASSOCIATION (ESIA) SPECIFIED IN THE PHOTO LIST SUBMITTED TO THE FOREST SERVICE ON NOVEMBER 12, 2010 BY THE CONTRACTOR. THE PHOTOS ARE TO BE SUBMITTED TO THE FOREST SERVICE FOR APPROVAL PRIOR TO USE IN PANEL DESIGNS. C. THE FOLLOWING EIGHT (8) PANELS ARE TO BE SUBMITTED TO THE FS FOR FINAL SUBMISSION ON APRIL 15, 2011: 1. LBP_1.70 - LAKES BASIN PATH/VALENTINE - PANEL 1: CONNECTING TO THE ENVIRONMENT 2. LBP_2.13 - LAKES BASIN PATH/VALENTINE - PANEL 2: VITAL WATERWAYS 3. TLP_002 - TWIN LAKES VISTA - PANEL 1: PICTURE PERFECT 4. TLP_003 - TWIN LAKES VISTA - PANEL 2: A PORTAL TO THE LAKES BASIN 5. TLP_004 - TWIN LAKES VISTA - PANEL 3: PROTECTING WILD INTERESTS 6. LBP_4.11 - LAKE MARY - PANEL 1: WALKING IN THEIR FOOTSTEPS 7. HLP_001 - HORSESHOE LAKE - PANEL 1: INVISIBLE DANGER 8. LBP_5.21 - HORSESHOE LAKE - PANEL 2: THE BIG PICTURE D. THE FOLLOWING EIGHT (8) PANELS ARE TO BE SUBMITTED TO THE FS FOR FINAL SUBMISSION ON JUNE 15, 2011: 1. MAMMOTH CREEK PARK - PANEL 1: A LAND OF FIRE AND ICE 2. MAMMOTH CREEK PARK - PANEL 2: A UNIQUE AND DIVERSE ECOSYSTEM 3. MAMMOTH CREEK PARK - PANEL 3: STEP THROUGH THE AGES 4. LAVA TUBE LOOKOUT - PANEL 1: THIS STORY HAS A HOLE IN IT 5. LAVA TUBE LOOKOUT - PANEL 2: HUMAN USE OVER TIME 6. TWIN LAKES OVERLOOK - PANEL 1: ADVENTURES FROM THE PAST 7. TWIN LAKES OVERLOOK - PANEL 2: THE AQUATIC LIFE 8. TWIN LAKES OVERLOOK - PANEL 3: THESE ROCKS CAN TALK E. THIS MODIFICATION IS PROCESSED AT NO ADDITIONAL COST TO THE GOVERNMENT. F. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. Change Order $0 1/31/11