Purchase Order 15BFA022P00000014

Award Date 10/1/21
Potential Completion Date 7/6/23
Potential Value $1.8M
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Not Available for Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
585 Av. Franklin Delano Roosevelt Ste 202, San Juan, 00936, Puerto Rico
Solicitation Procedures
Only One Source
Number Of Offers Received
1
Legislative Mandate
Not listed
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
The Puerto Rico Electric Power Authority Finance Directorate Division, doing business as Prepa, has been awarded a $2.2 million firm fixed-price contract by the Department of Justice Bureau of Prisons to provide electric utility service to the Metropolitan Detention Center Guaynabo in San Juan, Puerto Rico from October 1, 2020 through September 30, 2021. Under the contract, Prepa will deliver electric power to the BOP facility over the one-year period. The Bureau of Prisons Metropolitan...
The Department of Justice Bureau of Prisons has awarded a firm fixed price purchase order to the Puerto Rico Electric Power Authority (PREPA) to provide electric utility services to the Metropolitan Detention Center in Guaynabo, Puerto Rico for the period of October 1, 2019 to September 30, 2020. The contract has a potential value of $2,080,000.00. PREPA is the sole provider of electric power in Puerto Rico, operating power plants, dams, and infrastructure to generate and distribute...
The Department of Justice Bureau of Prisons Metropolitan Detention Center Guaynabo has awarded a Firm Fixed Price Purchase Order to the Puerto Rico Electric Power Authority (PREPA) to provide electric utility service for the facility from October 1, 2017 through September 30, 2018 (Fiscal Year 2018). The potential value of this one-year contract is $2,026,000.00. PREPA is the sole provider of electric power in Puerto Rico, generating and distributing electricity across the territory. In addition...
This is a federal contract award to the Puerto Rico Electric Power Authority (PREPA), doing business as Prepa, for electric utility services to the U.S. Department of Justice's Metropolitan Detention Center Guaynabo in Puerto Rico. The contract has a ceiling value of $1,514,757.71 and covers the period from October 2015 through September 2016. The contract is a firm fixed-price purchase order and does not have a set-aside designation. As the sole electric utility provider in Puerto Rico, PREPA...
This is a firm fixed price purchase order awarded by the Department of Justice Bureau of Prisons to the Puerto Rico Electric Power Authority (PREPA) to provide electric utility service to the Metropolitan Detention Center in Guaynabo, Puerto Rico for the period of October 1, 2018 to September 30, 2019. The potential value of the contract is $2,026,000.00. PREPA is the sole provider of electric power in Puerto Rico, operating power plants, dams, and infrastructure to generate and distribute...
The Department of Justice Bureau of Prisons Metropolitan Detention Center Guaynabo awarded a $424,421.81 firm fixed price purchase order contract to the Puerto Rico Electric Power Authority Finance Directorate Division, doing business as Prepa, to provide electric utility service at the MDC Guaynabo facility for the period of October 1, 2022 through December 31, 2022. Prepa will be responsible for supplying electricity to the MDC Guaynabo correctional facility during the specified period of...
This is a firm fixed-price purchase order awarded by the U.S. Department of Justice (DOJ) to the Puerto Rico Electric Power Authority (PREPA) to provide electric utility service to the Metropolitan Detention Center Guaynabo in Puerto Rico for the period of October 2016 through September 2017. The contract has a ceiling value of $1,617,341.87 and was not set aside for any specific socioeconomic program. As the sole electric utility provider in Puerto Rico, PREPA has a long-standing relationship...
The Department of Justice (DOJ) Bureau of Prisons awarded a firm-fixed-price purchase order to the Puerto Rico Electric Power Authority (PREPA) to provide electric utility services to the Metropolitan Detention Center in Guaynabo, Puerto Rico for the month of October in fiscal year 2022. The award has a potential value of $185,098.11 and did not utilize a set-aside designation. PREPA is the sole provider of electric power in Puerto Rico, operating power plants, dams, and infrastructure to...
This firm fixed price purchase order was awarded by the Department of Justice Bureau of Prisons to the Puerto Rico Electric Power Authority (PREPA) to provide electric utility service to the Metropolitan Detention Center in Guaynabo, Puerto Rico for the month of January 2023. The potential value of this contract is $210,873.21. PREPA is the sole provider of electric power in Puerto Rico and has previously been awarded similar contracts by the Department of Justice and Department of Veterans...
This is a firm fixed price purchase order awarded by the Department of Justice Bureau of Prisons to the Puerto Rico Electric Power Authority (PREPA) to provide electric utility services to the Metropolitan Detention Center in Guaynabo, Puerto Rico for the month of December in fiscal year 2022. The potential value of the contract is $166,415.04. PREPA is the sole provider of electric power in Puerto Rico, operating power plants, dams, and distribution infrastructure. In addition to this...

The Puerto Rico Electric Power Authority Finance Directorate Division, doing business as Prepa, has been awarded a firm fixed price purchase order valued at approximately $1.8 million to provide electric utility services to the Metropolitan Detention Center in Guaynabo, Puerto Rico. The contract was awarded by the Department of Justice Bureau of Prisons Field Acquisition Office for the period of October 1, 2021 through July 6, 2023. Funding is associated with the Bureau's major program for Federal Acquisition Operations. Prepa will serve as the prime contractor to deliver electric utility services to the Guaynabo detention facility, with all work to be performed in San Juan, Puerto Rico.

Generated 12/25/23, 12:28 AM