Delivery Order NNK07CB26B-NNK09CA88D
Award Date 6/17/09
Potential Completion Date 5/6/11
Potential Value $4.2M
Federal Agency
Ultimate Awardee
Not listed PSC Category
Not listed Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Competitive Delivery Order
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Kennedy Space Center, FL 32899, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
7
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Defense Or Civilian federal agency Shared Services Center awarded a purchase order to Armag Corp for an explosion-resistant prefabricated facility on June 4, 2026, with a ceiling value of $278,627.76. The order procures a 30-foot by 15-foot by 10-foot explosion-resistant operations building constructed to ATF Type 2 magazine specifications for use as a cured propellant test facility at NASA Marshall Space Flight Center in Huntsville, Alabama. The facility includes integrated HD 1.3...
- The Department of Energy issued a $314,320 delivery order to Air Products and Chemicals, Inc. on February 9, 2026, for propellant pressurizing agent with an ultimate completion date of March 31, 2026. Place of performance is Wescosville, PA. The order is firm fixed price. No set-aside was used. Air Products and Chemicals, Inc. is a for-profit manufacturer of industrial gases headquartered in Allentown, Pennsylvania, supplying compressed and liquefied gases, propellant oxidizers, and cryogenic...
- The U.S. Air Force Air Combat Command awarded a $293.5K delivery order to West Coast Contractors, Inc., a certified HUBZone small business based in Coos Bay, Oregon, for the removal and replacement of a noncondensing boiler with a condensing boiler system at Grand Forks Air Force Base Building 201 in North Dakota. The contract, awarded on March 11, 2024, with a completion date of September 30, 2024, is structured as a firm fixed-price delivery order under a total small business set-aside...
- The U.S. Army Corps of Engineers Omaha District awarded a $19.2 million definitive contract to Hcpa-Garco JV1 for construction of an emergency power plant fuel storage facility at Cavalier Space Force Station, North Dakota, on October 23, 2024, under firm fixed-price terms with no set-aside. The originating solicitation calls for construction of a 360,000-gallon fuel storage farm designed to Department of Defense standards for antiterrorism and force protection to support emergency power...
- This federal contract was awarded by the Department of the Air Force Materiel Command to Aptim Federal Services LLC, a global industry leader in critical infrastructure, resilience, program management, environmental services, sustainability and energy solutions. The contract is for the HIGH PRESSURE AIR SYSTEM UPGRADE - FOUNDATIONS project, with a potential value of $1,822,751.35, and a completion date of November 30, 2020. The contract is a Delivery Order under the Facilities Acquisitions for...
- This is a delivery order contract award to Air Products & Chemicals, Inc., doing business as Air Products, by the Defense Logistics Agency (DLA) Energy. The contract is for the supply of PROPELLANT PRESSURI, with an ultimate completion date of March 31, 2022. The contract has a firm fixed price and a ceiling value of $15,214.50. The contract does not have a set-aside designation. Air Products is a leading global supplier of industrial gases and related equipment, including liquid nitrogen,...
- The Department of the Air Force Air Combat Command (DOD - United States Air Force) awarded a $1.76 million firm fixed price delivery order contract to T.F. Powers Construction Co. to complete a hangar boiler project at Grand Forks Air Force Base in Grand Forks, North Dakota. The contract has a period of performance starting on October 19, 2022 through October 27, 2023. No subcontractors were identified. The prime contractor, T.F. Powers Construction Co., will provide construction services to...
- <p>The Department of Defense Energy issued a $5,788.18 delivery order to Nippon Sanso Matheson, Inc. (doing business as Aeris) on April 22, 2026, for propellant pressurization gases, with an ultimate completion date of April 30, 2026.</p> <p>Place of performance is Warren, NJ 07059. The order is priced on a firm fixed-price basis with no set-aside.</p>
- Air Combat Command issued a delivery order to RFS LLC on July 24, 2023, with a ceiling value of $963,522.77 under the Minot AFB Multiple Award Construction Contract (MACC), a $90 million total small business set-aside IDIQ. RFS LLC is a woman-owned small business. Work is performed at Minot Air Force Base, North Dakota. The order calls for removal and disposal of an existing controls system in Building 867 (Dock 1) and replacement of a fuel tank purge and SCBA hose reel control panel. The...
- <p>The Department of Energy issued a delivery order to Airgas USA, LLC on February 9, 2026, with a ceiling value of $15,865.44 for propellant pressurization products, with ultimate completion by February 28, 2026.</p> <p>Place of performance is Tulsa, OK. The order is firm fixed price with no set-aside used. The source identifies this as a child delivery order against a parent vehicle, though the parent contract name is not explicitly stated in the award record provided.</p>
- NNK07CB26BIndefinite Delivery Contract
- NNK07CB26B-NNK09CA88DDelivery Order
CONSTRUCT REPLACEMENT PROPELLANTS NORTH ADMINISTRATION FACILITIES
Posted 6/17/09
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 16 | Supplemental Agreement for work within scope | $75.0k | 5/5/11 | |
| 15 | Supplemental Agreement for work within scope | $36.2k | 4/21/11 | |
| 14 | Supplemental Agreement for work within scope | $7.5k | 3/7/11 | |
| 13 | Supplemental Agreement for work within scope | $0 | 2/1/11 | |
| 12 | Supplemental Agreement for work within scope | $159.0k | 11/19/10 |