Delivery Order FA860119DA004-FA860120F0261
Award Date 9/15/20
Potential Completion Date 12/23/20
Potential Value $426K
Funding Federal Agency
Contracting Federal Agency
Ultimate Awardee
Not listed NAICS Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
WPAFB, OH 45433, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
Not listed
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Department of the Air Force Materiel Command awarded a $159,814 delivery order to Evol LTD 2 And DCI Joint Venture for repair and repaving of a parking lot at Wright-Patterson Air Force Base in Ohio. As the prime contractor, Evol LTD 2 And DCI Joint Venture Division will perform the work under a firm fixed-price contract running from April to August 2022. No set-aside designation or subcontractors were indicated. The Air Force Materiel Command supports Air Force acquisition and sustaining...
- The Department of the Air Force Materiel Command awarded a $541,302 delivery order to Evol LTD 2 And DCI Joint Venture for the repaving of the West parking lot at Wright-Patterson Air Force Base in Ohio. As the prime contractor, Evol LTD 2 And DCI Joint Venture will perform the work under a firm fixed-price contract running from January to June 2021. No set-aside designation or subcontractors were identified. The delivery order was issued under an unspecified multiple-award contract vehicle to...
- The Department of the Air Force Materiel Command awarded a $361,186 delivery order to Evol LTD 2 And DCI Joint Venture for the repaving of a parking lot near facility F20676 at Wright-Patterson Air Force Base in Ohio. As a firm fixed price contract set to run from December 2020 through March 2021, Evol LTD 2 And DCI Joint Venture will repave the specified parking lot to support the Air Force Materiel Command's operations at Wright-Patterson Air Force Base. No major subcontractors were identified...
- This is a $148,984.56 firm fixed-price delivery order awarded by the Department of the Air Force Materiel Command to Evol LTD 2 And DCI Joint Venture, a minority-owned small business, to provide a new parking lot at Wright-Patterson Air Force Base in Ohio. The joint venture has performed numerous previous construction and facilities maintenance projects at the base as a prime contractor without set-aside designations. Evol LTD 2 And DCI Joint Venture also holds a single-award indefinite...
- The Department of the Air Force Materiel Command awarded a $487,775 firm fixed price delivery order to Evol LTD 2 And DCI Joint Venture for project 212711 to repair and repave pavements at Wright-Patterson Air Force Base in Ohio. As the prime contractor on the order, Evol LTD 2 And DCI Joint Venture will perform the work over a three-month period from June through September 2021. The project involves repairing and repaving pavements to support operations and infrastructure maintenance programs...
- The Department of the Air Force Materiel Command awarded a $274,839 delivery order to Evol LTD 2 And DCI Joint Venture for the repaving of parking lot 0280-03 at Building F30280, located at Wright-Patterson Air Force Base in Ohio. As a firm fixed price contract, the joint venture will repave the specified parking lot between May 1 and June 15, 2020. No set aside designation or subcontractors were indicated. The delivery order was issued under an unspecified multiple award contract vehicle held...
- The Department of the Air Force Materiel Command awarded a $44,850 firm fixed price delivery order to Evol LTD 2 And DCI Joint Venture for project number 172814 to repair and repave parking lot F at Wright-Patterson Air Force Base in Ohio. The work is to be completed between July 30th and September 23rd, 2019. No additional details were provided on subcontractors or the scope of base-wide programs to provide further context. The award was made without any set aside designations to the named...
- The Department of the Air Force Materiel Command awarded a $163,000 delivery order to Evol LTD 2 And DCI Joint Venture for the repair and repaving of Birch Street at Wright-Patterson Air Force Base in Ohio. Work will be performed from April to September 2020 under the terms of a firm fixed-price contract. As the prime contractor, Evol LTD 2 And DCI Joint Venture will complete the roadwork at the Air Force installation, leveraging its expertise in infrastructure projects for DOD customers. No...
- The Department of the Air Force Materiel Command awarded a $80,222.15 firm fixed price delivery order to Evol LTD 2 And DCI Joint Venture Evol LTD 2 And DCI Joint Venture Division for PROJECT 212713 to repave the center section of the display walkway at Wright-Patterson Air Force Base in Ohio. As the prime contractor, Evol LTD 2 And DCI Joint Venture Evol LTD 2 And DCI Joint Venture Division will complete the work under the delivery order between June 3, 2021 and July 20, 2021. No subcontractors...
- This is a firm fixed-price delivery order contract awarded by the Air Force Materiel Command (AFMC) to Evol LTD 2 And DCI Joint Venture, a minority-owned small business, to repair and repave a parking lot at Wright-Patterson Air Force Base in Ohio. The contract has a ceiling value of $127,870.39 and a completion date of November 27, 2020. This delivery order is issued under a larger single-award indefinite delivery/indefinite quantity (IDIQ) contract held by Evol LTD 2 And DCI Joint Venture...
- FA860119DA004Indefinite Delivery Contract
- FA860119DA004-FA860120F0261Delivery Order
The Department of the Air Force Materiel Command awarded a $425,563.76 firm fixed-price delivery order to Evol LTD 2 And DCI Joint Venture for task order project 172804 to repair and repave a parking lot at Wright-Patterson Air Force Base in Ohio. As the prime contractor, Evol LTD 2 And DCI Joint Venture will perform the work under the delivery order from September 2020 through December 2020. No subcontractors or set-aside designations were identified. The task order was issued under an unspecified multiple-award contract vehicle held by the joint venture to support facilities maintenance and repair at Air Force installations.
Generated 12/29/23, 11:40 PM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $425.6k | 9/15/20 |