Delivery Order DTFH6816D00007-0006
Award Date 7/25/16
Potential Completion Date 12/30/21
Potential Value $713K
Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Greenwood Village, CO 80112, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
1
Legislative Mandate
Service Contract Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a firm fixed-price delivery order awarded by the Federal Highway Administration, a civilian agency, to CH2M Hill, Inc. for $2,406,467.95 to prepare 100% plans, specifications, and estimates for the CA FLAP SR89(1) Truckee River Bridge project. The order was placed under an existing contract vehicle and does not have a set-aside designation. Key subcontractors include Arrowtrenchless for other transportation support activities, Andregg Geomatics for surveying and mapping, and Shannon...
- This is a delivery order issued under the Federal Highway Administration's (FHWA) Roadwork Architect Engineering IDIQ contract, awarded to CH2M Hill, Inc. for $694,208.85. The order is for 30% through 100% design services related to the UT FLAP 3108(1) CASCADE SPRINGS ROAD project in Greenwood Village, CO. There is no set-aside designation for this award. The key subcontractors are Horrocks LLC for surveying and mapping services, Metcalf Archaeological Consultants, Inc. for environmental...
- This is a $79,576.53 firm fixed-price delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency, to CH2M Hill, Inc. for intermediate through final design phases of a pavement preservation project in the Bay Area. The order is placed against the FHWA's Roadwork Architect Engineering IDIQ contract, a multiple-award indefinite-delivery, indefinite-quantity vehicle active from 2016-2021. This award has no set-aside designation. CH2M Hill is an engineering and...
- This is a delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency, to Ch2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc. The $176,950.30 firm-fixed-price delivery order was issued against the FHWA's Roadwork Architect Engineering IDIQ contract and is for CO FLAP PIT 82(1) BRUSH CREEK PARKING services. The award has no set-aside designation. As a large engineering and construction firm, Ch2M Hill provides a range of professional services to federal...
- This federal contract award was issued by the Department of Transportation Federal Highway Administration (FHWA) to CH2M Hill, Inc., an engineering and construction firm, for a task order under the FHWA's Roadwork Architect Engineering IDIQ contract. The task order, valued at $301,931.65, is for 30% design work related to the CA FLAP MRN CR107(1) Muir Woods Road project, including project management, NEPA compliance, hydraulics, geotechnical, survey, and right-of-way services. The contract...
- This firm-fixed price delivery order was awarded to Ch2M Hill, Inc. by the Federal Highway Administration, a civilian agency, to provide final design services for the HI STP SR11(1) HILEA STREAM BRIDGE project in Greenwood Village, Colorado. The $364,409.68 award was made under an existing indefinite delivery/indefinite quantity (ID/IQ) contract with a $466,309.73 ceiling value. This delivery order does not have a set-aside designation. Ch2M Hill, Inc. is a subsidiary of the global engineering...
- Ch2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc., received a delivery order valued at $668,458 for environmental and preliminary design services on the Muir Woods Road project (CA FLAP MRN CR107(1)) under the Federal Highway Administration's Roadwork Architect Engineering IDIQ 2016-2021 vehicle. This modification extended the period of performance through June 30, 2026, with an original award date of May 21, 2020. The contract utilizes firm fixed-price pricing and does not...
- This delivery order modification, issued on October 17, 2019, represents the closeout of a design services task order under the California FLAP MRN CR107(1) Muir Woods Road project. Ch2M Hill, Inc., a large engineering and construction firm headquartered in Greenwood Village, Colorado and now owned by Jacobs Engineering Group Inc., served as the prime contractor on this firm fixed-price delivery order with a ceiling value of $321,003.21. The work was performed in Greenwood Village, Colorado,...
- This is a delivery order awarded by the Federal Highway Administration (FHWA) to CH2M Hill, Inc., a subsidiary of Jacobs Engineering Group Inc., for various roadwork services along routes 010, 900, 901, and 300. The delivery order, valued at $115,187.02, is part of a larger FHWA Roadwork Architect Engineering IDIQ contract that runs from 2016 to 2021. The work is being performed in Greenwood Village, Colorado and has a completion date of April 30, 2021. This delivery order does not have a...
- This is a $450,791.51 firm fixed price delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency, to CH2M Hill, Inc. for final design services related to the HI STP SR50(2) BRIDGE #7E project in Greenwood Village, Colorado. The award is not associated with a set-aside program. CH2M Hill, an engineering and construction firm, has previously received multiple-award indefinite delivery/indefinite quantity (IDIQ) contracts from various defense and civilian agencies for...
- DTFH6816D00007Indefinite Delivery Contract
- DTFH6816D00007-0006Delivery Order
This is a delivery order issued under the Federal Highway Administration's (FHWA) Roadwork Architect Engineering IDIQ contract, awarded to the engineering firm Ch2M Hill, Inc. The $713,395.65 firm-fixed-price contract is for post-design services related to the construction of the CA FLAP SR89(1) Truckee River Bridge project. The order does not have a set-aside designation. Ch2M Hill, a for-profit engineering and construction company, will provide services such as environmental assessments, engineering designs, and construction management to support this FHWA infrastructure project, which is located in Greenwood Village, Colorado. The ultimate completion date for this contract is December 30, 2021.
Generated 4/2/25, 10:59 PM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
4-State Gravel MATOC- CANCELED | DTFH6816R00001 | Department of Transportation Federal Highway Administration | Award Notice 2/2 | 11/17/15, 12:43 PM | |
A-E FULL SERVICE DESIGN IDIQ | DTFH6816R00001 | Department of Transportation Federal Highway Administration | Award Notice 1/2 | 10/1/15, 12:24 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 11 | Close Out | ($22k) | 8/2/22 | |
| 10 | Supplemental Agreement for work within scope | $0 | 10/27/21 | |
| 9 | Supplemental Agreement for work within scope | $0 | 3/10/21 | |
| 8 | Supplemental Agreement for work within scope | $0 | 1/22/20 | |
| 7 | Supplemental Agreement for work within scope | $15.0k | 8/29/19 |