Definitive Contract W912ES24C0019
- Not listed
- The U.S. Army Corps of Engineers, St. Paul District, awarded a $560,418 firm fixed-price contract to Three Oaks Construction, Inc., a small disadvantaged business based in North Sioux City, South Dakota, for the St. Vincent Township—Noyes Levee Repair project near Noyes, Minnesota. The contract, designated as a total small business set-aside, requires repair of approximately 3,150 feet of levee through removal of topsoil, debris, and damaged soil, followed by recompaction of levee fill sourced...
- The U.S. Army Corps of Engineers, Omaha District, awarded an $8.19 million firm fixed-price definitive contract to Three Oaks Construction, Inc., a small disadvantaged business headquartered in North Sioux City, South Dakota, on January 15, 2026. This total small business set-aside contract supports the Lower Brule North Element 1 Phase 2 North Ecosystem Restoration Project at Fort Thompson, South Dakota, with final completion targeted for April 22, 2027. The project encompasses shoreline...
- Three Oaks Construction, Inc., a small disadvantaged business based in North Sioux City, South Dakota, was awarded a $382,429.42 firm fixed-price delivery order by the U.S. Army Corps of Engineers, Norfolk District, for emergency spillway work at the Craney Island Pipeline Outfall in Portsmouth, Virginia. The contract is designated as a total small business set-aside and carries an ultimate completion date of October 31, 2025. This delivery order is issued under a $75 million indefinite delivery...
- Three Oaks Construction, Inc., a small disadvantaged business based in North Sioux City, South Dakota, has been awarded a delivery order valued at $528,294 by the U.S. Army Corps of Engineers, Norfolk District, for repairs to the North Cell West Dike near Spillbox 5 at the Craney Island Dredged Material Management Area in Portsmouth, Virginia. The task order, awarded on July 28, 2025, requires excavation, transportation, and placement of fill material to repair the collapsed section of the dike....
- The U.S. Army Corps of Engineers St. Paul District awarded a $11.07 million firm fixed-price definitive contract to Legacy Corporation of Illinois for tree clearing, removal, and RM-H3 alignment work associated with Pool 10, Stage 1 of the Island Building Project. This small business set-aside contract supports the Lower Pool 10 Habitat Rehabilitation and Enhancement Project on the Mississippi River, which involves constructing islands using granular fill from dredging operations and stabilizing...
- This is a $2,366,631.57 firm fixed price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to Portable Barge Service Inc. for the Pool 8 Islands Phase III, Stage 3A, Habitat Rehabilitation and Enhancement Project (HREP). The contract does not have a set-aside designation. The project consists of constructing islands using dredged material, as well as building various erosion control structures such as rocklog sills, riprap slope protection, and wildlife loafing...
- This is a definitive contract awarded by the U.S. Army Corps of Engineers, St. Paul District (USACE-SPL) to Coastal Environmental Group Inc., a self-certified small disadvantaged business, for the Lock and Dam 3 Upper Embankments Project. The $5,279,899.59 firm-fixed-price contract includes reconstructing nine channel closures along approximately 2.25 miles of the Wisconsin embankment upstream of Lock & Dam 3 on the Mississippi River. The project is designated as a HUBZone set-aside and...
- The U.S. Army Corps of Engineers awarded a $376,270.71 firm-fixed-price contract to L S Marine Inc., a self-certified small disadvantaged business, for the Corps Island Bank Stabilization Construction project on the Upper Mississippi River. This contract, which is set aside for small businesses, requires the construction of a sand berm, sand bench, and riprap vanes to stabilize the Corps Island temporary dredge material storage island near Lock and Dam 3 in Minnesota. L S Marine Inc. is a...
- Three Oaks Construction, Inc., a self-certified small disadvantaged business headquartered in North Sioux City, South Dakota, was awarded a delivery order valued at approximately $14.96 million by the Engineering and Support Activity (ENDIST) Norfolk, a Defense agency component, on October 27, 2025. The task order, which is a single-award contract under a larger $75 million Indefinite Delivery Contract with the U.S. Army Corps of Engineers Norfolk District, involves earthwork and dike raising...
- The US Army Corps of Engineers awarded a $220,358.95 definitive contract to Three Oaks Construction, Inc. for Indian Creek bank stabilization in Walworth County, South Dakota on September 26, 2024, under a total small business set-aside. Three Oaks Construction is a self-certified small disadvantaged business headquartered in North Sioux City, South Dakota. Place of performance is Mobridge, SD. The contract is firm fixed price with an ultimate completion date of October 22, 2025. The originating...
The U.S. Army Corps of Engineers, St. Paul District, awarded a $10.1 million firm fixed-price definitive contract to Three Oaks Construction, Inc., a small disadvantaged business headquartered in North Sioux City, South Dakota, on September 4, 2024. This total small business set-aside contract supports habitat restoration and infrastructure protection near Hastings, Minnesota, where Three Oaks will construct an island above Lock and Dam 2 using dredged material from Pool 2 of the Mississippi River. The project scope includes creating a mudflat for fish overwintering habitat, installing riprap shoreline protection, and constructing associated earthwork to shield the exposed Lock and Dam 2 embankment while generating wetland and floodplain habitat benefits. Work is scheduled for completion by November 30, 2026. Three Oaks Construction brings substantial expertise to this mission, with a demonstrated track record executing comparable civil infrastructure and water management projects for the Army Corps of Engineers across multiple districts. The contractor's relevant experience includes the Lower Brule Bank Stabilization project ($7.7 million) and multiple dike construction and repair initiatives, along with active participation in a $75 million indefinite delivery contract with the Army Corps of Engineers, Norfolk District, focused on dredged material management operations. This island construction project aligns with the Army Corps' broader mission to balance navigation, flood risk management, and environmental restoration objectives throughout the Mississippi River system.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Pool 2 Protective Island | W912ES24B0008 | Department of the Army Corps of Engineers Engineering District St Paul | Pre-Solicitation 1/3 | 5/21/24, 12:01 PM | |
Lock and Dam 2 Protective Island | W912ES24C0019 | Department of the Army Corps of Engineers Engineering District St Paul | Award Notice 3/3 | 9/25/24, 12:07 PM | |
Lock and Dam 2 Protective Island | W912ES24B0008 | Department of the Army Corps of Engineers Engineering District St Paul | Solicitation 2/3 | 7/19/24, 5:27 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00002 | Change Order | ($79k) | 10/23/25 | |
| Not listed | Not listed | $9.8m | 9/24/24 |