Definitive Contract W912DS24C0014

Award Date 6/13/24
Potential Completion Date 3/31/25
Potential Value $48M
Funding Federal Agency
US Army Corps of Engineers
Contracting Federal Agency
ENDIST New York
Ultimate Awardee
Not listed
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
Extent Competed
Full and Open Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Ocean Beach, NY 11770, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
3
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This is a firm fixed-price contract awarded by the U.S. Army Corps of Engineers to Great Lakes Dredge & Dock Co, LLC, a leading provider of dredging and marine construction services, for the Fire Island Inlet to Montauk Point, Fire Island Stabilization Project, Contract 3A in Suffolk County, New York. The contract has a ceiling value of $28,025,936.97 and a completion date of December 14, 2018. The contract scope includes dune grass planting, sand fence installation, residential structure...
The Army Corps of Engineers awarded a definitive firm fixed price contract valued at $53.7 million to Great Lakes Dredge & Dock Company, LLC for mobilization and demobilization services in support of beach replenishment along approximately 25 miles of shoreline from Fire Island Inlet to Montauk Point in Suffolk County, New York. The solicitation sought dredging, placement of approximately 1.5 million cubic yards of fill material, dune construction and repair services to be completed...
The U.S. Army Corps of Engineers (USACE) awarded a $40,177,106.90 Firm Fixed Price contract to Great Lakes Dredge & Dock Co, LLC for the Fire Island Inlet to Montauk Inlet, PL 84-99 Rehabilitation Project in Saltaire to Suffolk County, New York. The work involves placing approximately 800,000 cubic yards of beach fill with a dune and berm along the Fire Island barrier island, as well as an additional 500,000 cubic yards of beach fill along the Montauk Beach shoreline. This emergency...
The Department of the Army Corps of Engineers Engineering District New York awarded a firm-fixed-price definitive contract to Great Lakes Dredge & Dock Company, LLC for the maintenance dredging of Fire Island Inlet and shores westerly to Jones Inlet, New York. The potential value of the contract is $26,719,132.70. Great Lakes Dredge & Dock Company is a provider of dredging services and marine construction solutions, and has an extensive history performing dredging and marine construction...
The U.S. Army Corps of Engineers, New York District has awarded a definitive, firm-fixed-price contract valued at $16,474,097.30 to Norfolk Dredging Company, a for-profit organization, for dredging services at Jones Inlet. This contract is not set-aside. The award is associated with the Corps' regional Indefinite Delivery Contract for dredging and shore protection services in the South Atlantic Division, which has a potential value of $450 million. Under this contract, Norfolk Dredging will...
The U.S. Army Corps of Engineers, New York District awarded a $2,336,560 firm-fixed-price contract to Dredgit Corporation for maintenance dredging of the Long Island Intracoastal Waterway Federal Navigation Project at Moriches Bay, Suffolk County, New York. The contract, which has a completion date of December 6, 2023, requires dredging of approximately 100,000 cubic yards of sand and placement along 1.5 miles of shoreline at Cupsogue Beach County Park. This work is part of a larger...
The U.S. Army Corps of Engineers, New York District awarded Great Lakes Dredge & Dock Company, LLC a firm fixed price contract valued at $26,018,345.70 for mobilization and demobilization services in Montauk, New York. The contract has no set-aside designation and work is to be completed by March 24, 2023. The award is associated with a sources sought announcement issued in May 2022 regarding a future dredging and beach nourishment construction project near Moriches and Shinnecock Inlets...
This is a definitive, firm-fixed-price contract awarded by the U.S. Army Corps of Engineers (USACE) to Norfolk Dredging Company for maintenance dredging of the New York Harbor and Sandy Hook Federal Navigation Channel. The contract has a ceiling value of $4,048,010.00 and a completion date of December 22, 2024. This contract is not associated with a set-aside designation. Norfolk Dredging Company, a for-profit organization specializing in dredging and marine construction services, will be...
This is a $3,063,080.27 firm fixed-price contract awarded by the U.S. Army Corps of Engineers (USACE) to Great Lakes Dredge & Dock Co, LLC, a subsidiary of Great Lakes Dredge & Dock Corporation, for maintenance dredging of the Shinnecock Inlet Federal Navigation Channel in New York. The work includes providing labor, equipment, and materials to perform the dredging, with disposal of the material along the shoreline. This project, which is cost-shared between the federal government and...
The Army Corps of Engineers awarded Norfolk Dredging Company a $2.5 million firm fixed price contract for mobilization and demobilization in support of maintenance dredging services. The solicitation sought dredging of approximately 96,120 cubic yards of material from the Sandy Hook Federal Navigation Channel in New York Harbor. Norfolk Dredging provided the lowest bid of $3.9 million for the work, which includes dredging, transporting, and disposing of material from specified areas between...

This is a definitive, firm-fixed-price contract awarded by the U.S. Army Corps of Engineers (USACE) to Norfolk Dredging Company for maintenance dredging and beach nourishment of the Fire Island Inlet and Shores Westerly to Jones Inlet Beach Erosion Control and Navigation Project in New York. The contract, valued at $48,310,815.80, requires dredging the federal navigation channel and deposition basin to a depth of 14 feet plus 2 feet of allowable over-depth, with subsequent placement of approximately 700,000 to 1,000,000 cubic yards of dredged sand as nourishment along Gilgo Beach. The work is scheduled for completion by March 31, 2025. This full and open competition contract has no set-aside designation. The project aims to alleviate shoaling, maintain the project dimensions, and provide safe and economical use of the Fire Island Inlet waterway for commercial and recreational boating.

Generated 6/21/25, 9:46 AM