Definitive Contract W9128F21C0045

Award Date 9/17/21
Potential Completion Date 4/14/25
Potential Value $138M
Federal Agency
ENDIST Omaha
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
721 kenney Rd, Ellsworth AFB, SD 57706, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
4
Legislative Mandate
Service Contract Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This is a $19,476,530.00 firm fixed-price construction contract awarded by the U.S. Army Corps of Engineers Engineering District Omaha to Edman Bryan LLC, a small business joint venture, to convert a portion of the PRIDE hangar at Ellsworth Air Force Base in South Dakota into a B-21 parts storage facility. The contract includes demolition, hazardous materials abatement, and construction of secure and climate-controlled spaces to support the B-21 program. The contract was set aside for small...
This $44,922,985 firm-fixed-price contract was awarded by the U.S. Army Corps of Engineers, Omaha District (USACE) to Federal Contracting Inc., doing business as Bryan Construction, a Colorado-based construction firm. The contract is for the construction of an addition to the existing B-1B flight simulator facility at Ellsworth Air Force Base in South Dakota to support B-21 operations. The contract has no set-aside designation. The original procurement, a sources sought notice, was seeking...
The U.S. Army Corps of Engineers Omaha District awarded a $44,796,271 Firm Fixed Price contract to Conti Federal Services, LLC for the construction of a B-21 Weapons Loader Training (WLT) Facility at Ellsworth Air Force Base in South Dakota. This design-bid-build contract was awarded on September 21, 2023 with a period of performance of 720 calendar days. The facility will renovate approximately 60,000 square feet of an existing 120,000 square foot hangar to include a new weapons loader...
The U.S. Army Corps of Engineers awarded a $109,751,147.28 firm-fixed-price contract to Federal Contracting Inc., doing business as Bryan Construction, to construct a B-21 Mission Operations Planning Facility (MPF) and a B-21 Field Detachment Training Facility (FTD) at Ellsworth Air Force Base in South Dakota. The contract was awarded on June 30, 2022, and has a completion date of June 4, 2025. There was no set-aside designation for this contract. The original solicitation was a...
This is a $207,502,915 definitive contract awarded by the Air Force Civil Engineer Center to prime contractor BL Harbert International LLC to construct the B21 Weapons Generation Facility - Site F (WGF-F) at Ellsworth Air Force Base in South Dakota. The project involves building a 52,210 square foot hardened facility with consolidated storage, maintenance, inspection, and administrative functions to support weapons generation operations. The contract has a firm fixed price pricing type and...
The U.S. Army Corps of Engineers, Engineering District Omaha awarded a $138,664,575.00 firm fixed-price contract to Conti Federal Services, LLC to construct a new approximately 80,000 square foot two-bay maintenance hangar facility and associated infrastructure at Ellsworth Air Force Base for the emerging B-21 airframe. The contract is not set aside for any particular business type. Conti Federal Services is a mid-size construction and engineering company that specializes in projects for the...
The U.S. Army Corps of Engineers, Omaha District awarded a $18,263,119.20 firm-fixed price contract to Roundhouse-Mv JV, a small business joint venture, to convert the PRIDE Hangar (B7504) at Ellsworth Air Force Base in South Dakota into a B-1 parts storage facility. The contract has an ultimate completion date of August 6, 2024. This project is part of the facilities beddown in support of the B-21 program at Ellsworth AFB. Roundhouse-Mv JV has previously performed similar projects for the...
The Department of the Army Corps of Engineers Engineering District Omaha awarded a $355,911.97 firm fixed price delivery order to R H A LLC under an unspecified contract vehicle. The order is for B-21 COMPLEX FACILITIES VE STUDY WORKSHOP(S) to be completed by November 9, 2020. The place of performance is Ellsworth Air Force Base in South Dakota. No set aside designation was used for this order to provide workshop support services related to the B-21 bomber program being carried out by the...
This is a $33,837,010.00 firm fixed price contract awarded by the U.S. Army Corps of Engineers, Omaha District to Conti Federal Services, LLC for the construction and renovation of the B-21 Renovate Dock 81 facility at Ellsworth Air Force Base in South Dakota. The project involves converting approximately 26,000 square feet of an existing general maintenance hangar into a fuel systems maintenance dock hangar, with potential optional bid items. The contract has a completion date of September...
The United States Army Corps of Engineers Engineering District Omaha awarded a $348,435.59 delivery order contract to Rcecm-Crawford LLC for Architectural and Engineering Services for the B-21 Phase Hangar at Ellsworth Air Force Base in South Dakota. The firm fixed price contract runs from September 20, 2022 through September 30, 2024 and involves Rcecm-Crawford LLC providing A-E services in support of constructing a new hangar to house the B-21 Raider bomber at its planned Ellsworth AFB...

This is a $137,886,101.02 firm fixed-price contract awarded to Walsh Federal LLC by the U.S. Army Corps of Engineers, Omaha District to construct a B-21 Low-Observable Restoration Facility (LO Hangar) at Ellsworth Air Force Base in South Dakota. The 95,500 square foot, two-bay hangar facility with associated site features, utilities, and infrastructure is being built to support maintenance of the emerging B-21 stealth bomber aircraft. This contract is part of a multi-year facilities beddown in support of the B-21 program at Ellsworth AFB and has an expected completion date of April 14, 2025. The contract was awarded through full and open competition without any set-aside designation.

Generated 1/30/25, 9:08 AM