Definitive Contract TMHQ15C0046
- Not listed
- This is a firm fixed-price delivery order awarded by the United States Mint, a civilian federal agency, to Yerba Buena Engineering & Construction, Inc., a minority-owned, HUBZone certified small disadvantaged business located in San Francisco, California. The $67,000 contract is for the exterior window replacement and repair at the United States Mint facility in San Francisco, with a period of performance through September 30, 2025. This order is not a set-aside and is part of a larger $25...
- This delivery order for $57,149.09, awarded by the Department of the Treasury United States Mint to Yerba Buena Engineering & Construction, Inc., a certified HUBZone small business, is for the replacement of fans at the United States Mint facility in San Francisco, California. The delivery order was awarded on January 2, 2024 under contract numbers 2031JG21D00034 and 2031JG24F00158, with work to be completed by January 3, 2025. As the sole awardee, Yerba Buena Engineering & Construction,...
- The United States Mint awarded Yerba Buena Engineering & Construction, Inc. a $16,100 firm fixed price delivery order against an unidentified government-wide acquisition contract for window replacement services at its San Francisco facility. As the sole prime, Yerba Buena will replace windows for the Mint through September 2026. Funding comes from the Treasury Department, which oversees Bureau of Engraving and Printing operations. Replacing dated windows supports the Mint's mission to...
- The United States Mint awarded a definitive firm fixed-price contract to Yerba Buena Engineering & Construction, Inc., a SBA-certified HUBZone firm and minority-owned small disadvantaged business based in San Francisco, for HVAC renovations at the San Francisco Mint facility. This modification funds Phases 11 and 12 of the project and adds spare parts, equipment calibration, and direct digital control (DDC) systems. The contract has a ceiling value of approximately $8.3M against a stated...
- Yerba Buena Engineering & Construction, Inc. was awarded a $23,900 firm fixed price delivery order against the Department of the Treasury United States Mint's perimeter fence project contract vehicle. Under task order 2031JG21D00034/2031JG23F00339, Yerba Buena will provide additional funding to support perimeter fence upgrades at the Mint's facility in San Francisco, California. Work will be performed between September 2023 and September 2024. As the prime contractor, Yerba Buena will...
- This federal contract award, valued at $28,354.50, was issued by the United States Mint (an agency of the U.S. Department of the Treasury) to Forell Elsesser Engineers, Inc., a structural engineering firm based in San Francisco, California. The contract provides Architectural and Engineering (A&E) services for Phase 6 of the seismic project at the San Francisco Mint facility. This delivery order contract is part of a larger $1,000,000 single-award indefinite delivery contract held by...
- This federal contract award funds testing and inspection of the anchorage of the PVD chambers and docking station at the United States Mint's San Francisco facility. The $5,737.80 firm fixed-price delivery order was issued by the United States Mint, a civilian federal agency, to the prime contractor Forell Elsesser Engineers, Inc., a structural engineering firm based in San Francisco. The purpose of this modification P00001 is to de-obligate funds. This award is part of a larger single-award...
- This is a firm fixed-price delivery order awarded by the United States Mint to Bay Architects Associates Inc., a minority-owned small disadvantaged business, for $184,783.89 to perform elevator modernization services at the United States Mint facility in San Francisco, California. The contract is a delivery order under the USM San Francisco A&E Services 2014-2019 multiple-award, indefinite-delivery, indefinite-quantity (IDIQ) contract vehicle. The work is expected to be completed by...
- The Department of the Treasury United States Mint awarded a $5,200 firm fixed price delivery order contract to Forell / Elsesser Engineers, Inc. of San Francisco, California. The contract is for seismic review services of the PVR lifting cart station at the Mint facility in San Francisco. The period of performance is through December 31, 2025. No set-aside provisions were applied to this award to support the United States Mint's mission of protecting employees, facilities, and operations through...
- Patriot Construction Inc., a Service-Disabled Veteran-Owned Small Business (SDVOSB) and SBA-certified HUBZone firm based in Stockton, California, received a firm fixed-price definitive contract from the United States Mint for seismic upgrade work on Phase 5 building structure at the San Francisco facility. The contract, awarded on September 18, 2018, carries a ceiling value of $12.4 million with an ultimate completion date of September 30, 2024. The current modification (MOD P00047) de-obligates...
This federal contract award, TMHQ15C0046, was made by the United States Mint to Yerba Buena Engineering & Construction, Inc., a minority-owned, HUBZone certified small disadvantaged business located in San Francisco, California. The $747,846.65 firm fixed price contract is for construction and seismic upgrades at the United States Mint's San Francisco facility, with a completion date of April 15, 2018. The contract was not set aside for any specific small business program. Yerba Buena Engineering & Construction holds several significant Indefinite Delivery Contracts (IDCs) with federal agencies like the U.S. Fish and Wildlife Service and United States Mint, enabling the company to compete for task orders supporting construction, maintenance, repair, and alteration projects across federal lands and facilities.
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 9 | Other Administrative Action | $0 | 3/16/18 | |
| 8 | Other Administrative Action | $0 | 9/18/17 | |
| 7 | Other Administrative Action | $0 | 6/13/17 | |
| 6 | Additional Work (new agreement, FAR part 6 applies) | $50.0k | 12/7/16 | |
| 5 | Additional Work (new agreement, FAR part 6 applies) | $15.5k | 10/20/16 |