This is a $409,643,260.80 firm-fixed price design-build construction contract awarded by the Naval Facilities Engineering Command to Archer Western Federal JV, a joint venture between Archer Western Contractors, Ltd. and The Walsh Group. The contract is for Hurricane Florence recovery work at Marine Corps Air Station New River in North Carolina, designated as MILCON Package 7. It includes demolishing existing facilities and constructing four new buildings totaling over 800,000 square feet for aircraft maintenance, personnel housing, and other support functions. The work has a planned completion date of February 18, 2026. This contract was the result of a pre-solicitation issued in October 2019 and was not set aside for small businesses. Archer Western Federal JV and The Walsh Group have extensive experience executing large construction projects for the Department of Defense.
Generated 12/30/24, 1:34 PM