This is a five-year, $49,394,902.63 fixed-price contract awarded by the U.S. Bureau of Reclamation, a civilian agency under the Department of the Interior, to Yellowstone Electric Co, a woman-owned small business. The contract is for the replacement of main transformers and isophase bus systems at a facility located in Page, Arizona. The contract was set aside for small businesses. Yellowstone Electric Co has previously held over $11 million in federal contracts with the Department of the...
This is a $1,309,606.70 firm fixed price contract awarded by the U.S. Bureau of Reclamation, a civilian agency under the Department of the Interior, to Yellowstone Electric Co, a woman-owned small business. The contract is for the Fontenelle Unit Breaker Replacement project, which involves replacing electrical components at a hydroelectric facility in Kemmerer, Wyoming. The contract has a total small business set-aside and was awarded on September 15, 2015, with a final completion date of August...
This is a Definitive Contract awarded by the Department of the Interior's Bureau of Reclamation to Yellowstone Electric Co, a woman-owned small business, for $200,500.00. The contract is for the replacement of a station service transformer and the addition of gauges and cable on the KR2B transformer at a facility in Dutch John, Utah. The contract has a firm fixed price and has no set-aside designation. Yellowstone Electric Co has received over $11 million in federal contracts from the Department...
This is a federal contract award worth $683,821.67 to Yellowstone Electric Co, a woman-owned small business, for the demolition and installation of a new transformer at the Davis Dam Power Plant. The contract was awarded by the Bureau of Reclamation, a civilian agency within the Department of the Interior, under the "Generator Step Up (GSU) Transformer Replacements for Davis Dam Power Plant IDIQ" program. The contract has a firm fixed price and is a delivery order, but does not have...
This is a firm fixed price delivery order awarded by the Department of the Interior Bureau of Reclamation to Yellowstone Electric Co, a for-profit woman-owned small business. The $718,104.49 contract is for the installation of a transformer at the Davis Dam Power Plant as part of the agency's "Generator Step Up (GSU) Transformer Replacements for Davis Dam Power Plant IDIQ" program. This work is not designated as a small business set-aside. Yellowstone Electric Co has received over...
This is a definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to Yellowstone Electric Co, a woman-owned small business, to manufacture and deliver 115 kV transformers. The contract has a firm fixed price of $15,501,226.69 and a completion date of May 4, 2012. The contract did not have a set-aside designation. As a prime contractor, Yellowstone Electric has received over $11 million in federal contracts from agencies like the Department of the Interior to supply and install...
This federal contract was awarded by the Department of the Interior Bureau of Reclamation to Yellowstone Electric Co, a woman-owned small business. The $655,764.07 firm-fixed-price delivery order contract is for the installation of a transformer as part of the "Generator Step Up (GSU) Transformer Replacements for Davis Dam Power Plant Indefinite Delivery Indefinite Quantity (IDIQ)" program. The work is to be performed in Bullhead City, Arizona. Yellowstone Electric Co has previously...
This firm fixed-price delivery order was awarded by the Department of the Interior's Bureau of Reclamation to Yellowstone Electric Co, a for-profit woman-owned small business, to perform Generator Step Up (GSU) Transformer Replacements at the Davis Dam Power Plant under an Indefinite Delivery/Indefinite Quantity (IDIQ) contract. The contract has a potential value of $718,104.49 and was completed on May 2, 2022. Yellowstone Electric Co has received over $11 million in federal contracts from the...
The Department of the Interior Bureau of Reclamation awarded a Firm Fixed Price delivery order contract to Yellowstone Electric Co, a woman-owned small business, for the replacement of D-4 Transformer Generator Step Up (GSU) transformers at the Davis Dam Power Plant in Bullhead City, Arizona. The contract has a potential value of $1,296,429.66 and was not set aside for small businesses. Yellowstone Electric has received over $11 million in federal contracts from the Department of the Interior...
This is a $497,496.00 firm fixed price contract awarded by the Bureau of Reclamation, a civilian agency within the U.S. Department of the Interior, to Yellowstone Electric Co, a woman-owned small business. The contract is for the Dolores Project Pumping Plants Electrical and Mechanical Upgrade, which involves replacing and upgrading electrical and mechanical equipment at hydroelectric facilities in Cortez, Colorado. The contract has a total small business set-aside designation. As a prime...
This contract is for the replacement of a station service transformer at a hydroelectric facility operated by the Department of the Interior's Bureau of Reclamation. The $550,468.93 firm fixed price contract was awarded to Yellowstone Electric Co., a woman-owned small business, on September 7, 2017. The work was completed by October 15, 2018 and involved the supply and installation of electrical equipment and components at the Montrose, Colorado facility. As a prime contractor, Yellowstone Electric has received over $11 million in federal contracts from agencies like the Department of the Interior to provide similar services for hydroelectric dams and power plants across the Western United States.