Definitive Contract INPC2011101029
Award Date 3/30/10
Potential Completion Date 5/25/11
Potential Value $3.9M
Federal Agency
Ultimate Awardee
Not listed PSC Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Three Rivers, CA 93271, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
5
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a firm fixed-price delivery order contract awarded by the National Park Service (NPS) to Anderson Hallas Architects, PC, a woman-owned small business architecture firm based in Golden, Colorado. The $80,279.70 contract is for Title III architectural and engineering services to support the replacement of a potable water tank at Sequoia National Park. The award is not associated with a set-aside program. Through this and other NPS contracts, Anderson Hallas Architects provides a range of...
- This is a $809,517.82 Firm Fixed Price contract awarded by the National Park Service (NPS) Southeast Region to Estes Bros. Const. Inc., a small disadvantaged and HUBZone certified business, to rehabilitate the water tank, waterlines, well, and septic systems at the Balsam Mountain Campground and Heintooga Picnic Area in Great Smoky Mountains National Park. The contract includes refurbishing the existing water tank, constructing a new access road and waterlines, improving the existing well, and...
- The National Park Service (NPS) awarded a firm-fixed-price contract worth $1,032,100.00 to S.t.rhoades Construction Incorporated, a minority-owned, self-certified small disadvantaged business, to replace the 100,000-gallon water storage tank that serves the Mill Creek Campground and adjacent structures at Redwood National and State Parks in Del Norte County, California. This contract was set aside for small businesses and has a completion date of March 31, 2026. The contractor will be...
- The National Park Service awarded a $10,146,187.66 firm-fixed-price contract to Record Steel and Construction, Inc. (Rsci) to replace the non-compliant lodgepole water treatment system in Sequoia-Kings Canyon National Park. Rsci is a for-profit organization and self-certified HUBZone joint venture that specializes in construction and engineering services for federal agencies, including the Department of the Interior and Department of Defense. This contract has a one-year period of performance...
- This is a firm fixed-price purchase order awarded by the National Park Service Pacific West Region to Advanced Diving Services Inc., a small business contractor, for the inspection, cleaning, and potential repair of five potable water storage tanks and one potable water storage reservoir within the Lake Roosevelt National Recreation Area. The contract has a total potential value of $19,920.00 and a period of performance through December 2, 2024. This requirement was originally issued as a...
- The National Park Service issued a $174,337.31 delivery order to HDR Engineering Inc. on July 1, 2026, for a scoping trip to replace lead and copper water services at Sequoia and Kings Canyon National Parks, California. The order is issued under the NPS Nationwide General Architect and Engineering Professional Services 2026–2031 contract, a multi-year architect-engineer vehicle supporting design and engineering services across the National Park System. Place of performance is Three Rivers, CA...
- The National Park Service awarded a $1.04 million firm fixed-price contract to Alfaro General Engineering, a small disadvantaged, minority-owned, veteran-owned business based in Rocklin, California, to perform cleaning, inspection, and repair services on water storage tanks at Yosemite National Park. The contract encompasses three tank locations—El Portal, Yosemite Valley, and Wawona—and extends through April 30, 2026. This award was made under an 8(a) sole source set-aside, which restricts...
- This is a $97,350.00 firm fixed price definitive contract awarded by the U.S. Forest Service's Pacific Southwest Region (Region 5) to Martin Brothers Construction, a HUBZone-certified small disadvantaged business. The contract is for the rehabilitation of four area water tanks at the Sierra National Forest, including work at the Minarets Work Center, Dry Gulch Campground, Mammoth Pool Campground, and Vermillion Campground. This contract is part of the Forest Service's ARRA-FS CAPITAL IMPROVEMENT...
- This is a federal contract award from the National Park Service to Anderson Hallas Architects, PC, a woman-owned small business architecture firm based in Golden, Colorado. The contract is for $382,647.60 to provide architectural, engineering, and design services for the construction of water tanks and piping at Sequoia and King Canyon National Parks. The contract is a Firm Fixed Price Delivery Order and is not set-aside. Anderson Hallas Architects holds two significant Indefinite...
- The National Park Service awarded a purchase order to Phoenix General Contractors, LLC, an 8(a)-certified Hispanic American–owned small business, for $139,274.00 on September 24, 2025, to repair and reline a 20,000-gallon concrete water storage tank at Rocky Mountain National Park. This total small business set-aside award is set to complete by July 3, 2026. Work is performed in Estes Park, Colorado at Fall River Pass (elevation 11,815 feet). The scope includes tank cleaning, sandblasting to...
This is a $3,910,052.37 firm-fixed-price definitive contract awarded by the National Park Service to Erick Ammon, Incorporated, a for-profit Native American-owned small business, to replace the potable water tanks and associated infrastructure at Sequoia National Park in California. The contract does not have a set-aside designation. The purpose of the project is to address the Recovery Act-related requirement to upgrade the park's water system infrastructure. The contract was awarded on March 30, 2010 with a completion date of May 25, 2011.
Generated 4/2/25, 9:58 AM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 4 | Supplemental Agreement for work within scope | $31.2k | 9/22/11 | |
| 3 | Supplemental Agreement for work within scope | $4.4k | 6/15/11 | |
| 2 | Other Administrative Action | $0 | 3/8/11 | |
| 1 | Supplemental Agreement for work within scope | $25.4k | 9/22/10 | |
| Not listed | Not listed | $3.8m | 3/29/10 |