This federal contract was awarded by the Department of Transportation Federal Highway Administration (FHWA) to Oftedal Construction, Inc., a for-profit construction company. The contract is a delivery order under the Yellowstone, Grand Teton, and Surrounding Area 2014-2019 indefinite delivery, indefinite quantity (IDIQ) contract, with a firm fixed price of $43,328,477.58. The contract scope includes road construction, repair, and rehabilitation work on the East Entrance Road in Yellowstone...
This is a $25,184,950.39 fixed price redetermination delivery order contract awarded by the Federal Highway Administration, a civilian agency, to Oftedal Construction, Inc. for road repairs and rehabilitation at Yellowstone National Park. The contract does not have a set-aside designation. Major subcontractors include Fisher Sand & Gravel Co. for drilling and blasting, H-K Contractors, Inc. for asphalt paving, and other vendors providing services like hauling, seeding, masonry, pavement...
The Department of Transportation Federal Highway Administration awarded a $30,000 delivery order contract to Oftedal Construction, Inc. for road construction services in Yellowstone National Park, Wyoming. Under the contract, Oftedal Construction will complete Phase 3 of the Norris to Golden Gate road project in Yellowstone National Park between January 29, 2021 and April 15, 2021. As a firm fixed price contract, Oftedal Construction will provide road construction services for a set price. The...
The Department of Transportation Federal Highway Administration awarded a $3.5 million firm fixed price delivery order contract to Oftedal Construction, Inc. for work at Yellowstone National Park. Under the contract, Oftedal Construction will repave the Roosevelt Lodge parking lot, located at Yellowstone National Park in Wyoming. As the prime contractor, Oftedal Construction will perform the work directly. Funding comes from the Federal Highway Administration to support infrastructure...
This is a $46,882,096.34 fixed-price-with-economic-price-adjustment delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency within the U.S. Department of Transportation, to H-K Contractors, Inc., a for-profit construction company. The award is for road construction and maintenance services on the Grand Loop Road in Yellowstone National Park, including resurfacing from Old Faithful to West Thumb. This work is being performed under two active indefinite-delivery,...
This is a firm fixed price delivery order contract awarded by the Federal Highway Administration, a civilian agency within the U.S. Department of Transportation, to Oftedal Construction, Inc. as the prime contractor. The contract is for the Moose Wilson Road Phase 1 project in Grand Teton National Park, Wyoming, with a ceiling value of $17,115,377.20 and a completion date of August 28, 2023. This contract is not associated with a set-aside program. Oftedal Construction, Inc. has previously...
This is a $25,045,319.62 firm-fixed-price definitive contract awarded by the Federal Highway Administration (FHWA) to Missouri River Contractors, LLC for the WY TIGER US212(9) Beartooth Highway construction project. The contract involves realigning and reconstructing 2.61 kilometers of roadway, including constructing a new 600-foot steel bridge, along U.S. Route 212 in Wyoming within the Shoshone National Forest. The work scope includes roadway excavation, drainage, mechanically stabilized earth...
The U.S. Federal Highway Administration (FHWA) awarded a $4,614,231.85 fixed-price delivery order contract to Eagle Peak Rock & Paving Inc., a small business certified as a Historically Underutilized Business Zone (HUBZone) firm, for the WY PRA YELL 10(19), Grand Loop Road, Norris to Golden Gate, Phase 2 project in Mammoth, Wyoming. This delivery order contract was issued under the Yellowstone, Grand Teton, and Surrounding Area 2014-2019 indefinite-delivery, indefinite-quantity (IDIQ)...
This is a firm fixed price delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency within the U.S. Department of Transportation, to M.A. Deatley Construction, Inc., a for-profit construction company. The $3,581,448 contract is to perform construction work on the MT FLAP PARK 2021(1), Old Yellowstone Trail South Improvements and Preservation project in Gardiner, MT. The work includes drainage, roadway reconditioning, aggregate surfacing, and signage. This delivery...
The Department of Transportation Federal Highway Administration awarded a firm-fixed-price delivery order contract to HDR Engineering, Inc. to provide construction inspection services for the WY FLAP US212(8) Beartooth Highway project in Lakewood, Colorado. The contract was awarded on July 10, 2017 with a potential value of $294,873.44 and a completion date of October 15, 2018. HDR Engineering, a large engineering and architecture firm, has been awarded numerous federal contracts to provide...