Definitive Contract DTFASA17C00340
- Not listed
- This is a federal contract awarded by the Department of Transportation Federal Aviation Administration (FAA) to Joe R. Jones Construction, Inc., a small business, to replace a Visual Approach Slope Indicator (VASI) with a Precision Approach Path Indicator (PAPI) system on Runway 33 at the Lake Charles Regional Airport in Louisiana. The contract is a definitive, firm-fixed price contract valued at $237,122.00. Joe R. Jones Construction, Inc. has provided similar services to the FAA, including for...
- This federal contract award is for the construction of a new precision approach path indicator (PAPI) system and demolition of an existing visual approach slope indicator (VASI) system at Runway 9L on Gillespie Field in El Cajon, California. The $353,915.00 definitive contract was awarded on November 7, 2019 to the small business prime contractor Joe R. Jones Construction, Inc. The work is to be completed by June 30, 2022 and is funded by the Department of Transportation Federal Aviation...
- This is a definitive contract awarded by the Federal Aviation Administration (FAA) to Joe R. Jones Construction, Inc., a small business prime contractor, to replace the Runway Visual Approach Slope Indicator (VASI) system with a Precision Approach Path Indicator (PAPI) system at the Terre Haute International Airport in Terre Haute, Indiana. The firm fixed-price contract is valued at $209,277.00 and has a completion date of November 15, 2016. The contract was awarded as a total small business...
- Joe R. Jones Construction, Inc. has been awarded a $355,275 definitive firm fixed price contract by the Department of Transportation's Federal Aviation Administration Headquarters to replace the runway visual approach slope indicator system with a precision approach path indicator system at Esler Regional Airport in Pineville, Louisiana. Designated as a total small business set-aside, the contract supports the FAA's mission to upgrade aging infrastructure for improved flight navigation. Work...
- The Department of Transportation Federal Aviation Administration Headquarters awarded a $338,992.00 Firm Fixed Price Definitive Contract to Joe R. Jones Construction, Inc., a for-profit small business, for the RUNWAY 31L ILS-420 UPGRADE-SAN ANTONIO, TX project. This contract was set aside for total small business participation. The contract involves precision approach path indicator system installation, localizer upgrades, distance measuring equipment establishment, and tower replacements to...
- The Department of Transportation Federal Aviation Administration awarded a definitive contract valued at $708,397 to Joe R. Jones Construction, Inc. for construction services to upgrade the runway 04 localizer and glide slope instrument landing system at San Antonio International Airport in San Antonio, Texas. Performance will occur at the airport location over a one year period concluding in September 2021. The firm fixed price contract has a total small business set aside designation. Joe R....
- This is a $372,319.00 definitive contract awarded by the Department of Transportation Federal Aviation Administration Headquarters to Joe R. Jones Construction, Inc., a small business contractor, for the replacement of the VASIS (Visual Approach Slope Indicator System) on Runway 17R and 35L with PAPI (Precision Approach Path Indicator) at the Abilene Regional Airport in Abilene, Texas. The contract was awarded on July 20, 2017, with a completion date of December 15, 2017. This contract is a firm...
- This definitive contract awarded by the Department of Transportation Federal Aviation Administration Headquarters (DOT-FAA) is valued at one million two hundred fifty-one thousand four hundred twenty-eight dollars ($1,251,428) to Joe R. Jones Construction, Inc. for replacing the Visual Approach Slope Indicator Lights (VASI) with Precision Approach Path Indicator Lights (PAPI) on runway 16 and replacing the Medium Intensity Approach Lighting System with Runway Alignment Indicator Lights (MALSR)...
- This is a $1,069,274.00 definitive firm-fixed-price contract awarded by the Department of Transportation Federal Aviation Administration Headquarters to Joe R. Jones Construction, Inc., a for-profit small business, to provide construction services for the upgrade of Runway 02 Instrument Landing System (ILS) at Louis Armstrong International Airport in Kenner, Louisiana. The contract is designated as a total small business set-aside. Joe R. Jones Construction, Inc. has provided similar...
- This is a definitive contract awarded by the Federal Aviation Administration (FAA), a civilian agency under the U.S. Department of Transportation, to Joe R. Jones Construction, Inc., a small business prime contractor. The $1,947,208.54 firm fixed-price contract is for the installation of window seals and exterior joints at the Roswell International Air Center in New Mexico. The contract was set aside for small businesses and was awarded on November 18, 2015, with a completion date of April 30,...
This is a definitive contract awarded by the Department of Transportation Federal Aviation Administration (DOT FAA) to Joe R. Jones Construction, Inc., a small business, to replace Runway 30 Visual Approach Slope Indicator (VASI) with new Precision Approach Path Indicator (PAPI) at Santa Maria Public Airport (SMX) in Santa Maria, California. The firm-fixed-price contract, valued at $395,812.00, is a total small business set-aside. The project aims to upgrade the airport's approach guidance technology to meet FAA standards and improve flight navigation. Joe R. Jones Construction, Inc. has previously provided construction services to upgrade lighting, navigation aids, and other infrastructure at regional and international airports across the U.S. as a prime contractor for the FAA.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
AMENDMENT 1 - INSTALLATION OF PAPI AND DEMOLITION OF EXISTING VASI AT SANTA MARIA PUBLIC AIRPORT IN SANTA MARIA, CA | DTFASA-17-R-00145 | Department of Transportation Federal Aviation Administration Northwest Mountain Region | Award Notice 1/1 | 1/17/17, 6:36 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 3 | Close Out | $0 | 9/15/17 | |
| 2 | Other Administrative Action | $0 | 6/7/17 | |
| 1 | Change Order | $30.1k | 5/18/17 | |
| Not listed | Not listed | $365.7k | 3/29/17 |