Definitive Contract AG82B1C090001
Award Date 6/9/09
Potential Completion Date 10/26/10
Potential Value $3.2M
Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
PSC Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Red Lodge, MT 59068, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
6
Legislative Mandate
Not listed National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a $3,993,821.00 Firm Fixed Price Definitive Contract awarded by the U.S. Department of Agriculture's (USDA) Region 1 - Northern Region to Montana Civil Contractors Inc., a self-certified small disadvantaged veteran-owned business. The contract is for the reconstruction of the SHIELDS RIVER RD. #844 project, which is part of the American Recovery and Reinvestment Act (ARRA) program. The contract has an ultimate completion date of June 1, 2012 and was awarded on June 16, 2009. The contract...
- This is a definitive contract awarded by a U.S. government agency to Leufkens Construction Inc., a small business, for capital improvement and maintenance recovery work. The contract has a ceiling value of $47,061.00 and is funded through the American Recovery and Reinvestment Act (ARRA) under the Forest Service (FS) Capital Improvement program. The contract is fixed-price and the place of performance is Thompson Falls, Montana. The ultimate completion date for the work is September 15, 2010.
- This federal contract award, valued at $46,084.00, was issued by the Operations Center Intermountain, a civilian agency, to Schlegel & Sons Contractors, Inc. The contract is for the TAS Recovery Herrig Cr. and Wild Bill Cr. AOP Replacements ARRA CIM-0110-02R project, which is part of the U.S. Forest Service's (USFS) American Recovery and Reinvestment Act (ARRA) Capital Improvement and Maintenance (CIM) program. The contract has a Firm Fixed Price pricing type and a Definitive Contract...
- <p>This is a $56,700.00 firm fixed price purchase order awarded by the Operations Center Intermountain, a civilian federal agency, to Capitol City Construction for the Recovery Funds - Mt. Roosevelt Historic Masonry Restoration Construction Supervision project. The contract is set aside for a small business and has an ultimate completion date of September 30, 2010. The contract does not appear to be associated with a larger procurement vehicle.</p>
- <p>This is a firm-fixed-price definitive contract awarded by the Operations Center Intermountain, a civilian agency, to M.L. Albright & Sons, Inc., a self-certified small disadvantaged business. The contract, worth $164,813.35, is for the TAS-RECOVERY FUNDED-CIM-08R PROJECT 17 - WILDERNESS GATEWAY BRIDGE MTNCE and has an ultimate completion date of July 1, 2011. The contract was awarded on August 12, 2010 and does not have a set-aside designation.</p>
- This is a $5,646,469.87 firm fixed-price contract awarded by the Federal Highway Administration (FHWA), a civilian agency under the U.S. Department of Transportation, to Riverside Contracting Inc. for the MT PFH 101(1), West Fork Rock Creek Road Reconstruction project in Red Lodge, Montana. The contract is for road reconstruction services, including surface improvements, paving, grading, and roadway reconditioning. Riverside Contracting Inc. collaborated with several subcontractors for this...
- This is a $320,844.00 firm fixed price definitive contract awarded by the Operations Center Intermountain, a civilian agency, to Treasure State Concrete Inc., a Small Disadvantaged Business and HUBZone certified firm. The contract is for the LITTLE BLACKFOOT ROAD MAINTENANCE AND SURFACING - RFCA (ARRA FUNDED) project. It does not have a set-aside designation. The contract was awarded on November 3, 2009 with an ultimate completion date of October 8, 2010. The agency responsible for this contract...
- <p>This is a federal contract award made by the Operations Center Intermountain, a civilian agency, to Wesslen Construction, Inc. for the ARRA-CIM-0105-23F PROJECT 6 - REC RENTAL REPAIRS. The contract is a Definitive Contract with a Firm Fixed Price of $134,961.16 and an Ultimate Completion Date of October 23, 2011. The contract is not associated with a larger vehicle and does not have a set-aside designation. This appears to be a contract for capital improvement and maintenance work.</p>
- This is a firm fixed-price definitive contract awarded by the U.S. Forest Service (USFS), Region 1 - Northern Region, to R & R Conner, Inc., a small business, for $154,056.97. The contract, which is funded under the American Recovery and Reinvestment Act (ARRA) and falls under the ARRA-FS CAPITAL IMPROVEMENT AND MAINTENANCE program, is for gravel crushing and stockpiling at the Tough Creek Pit in the Bitterroot National Forest. The contract has an ultimate completion date of November 15,...
- This is a firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers, Engineering District Seattle to Centennial Contractors Enterprises, Inc., a construction company, for $199,601.00. The contract is for the construction of technical section offices at the Libby Dam in Libby, Montana. This contract is part of the American Recovery and Reinvestment Act (ARRA) projects for operations and maintenance. The contract does not have a set-aside designation and was awarded on...
This is a $3,154,725.79 firm-fixed-price definitive contract awarded by the Operations Center Intermountain, a civilian agency, to W Construction LLC for capital improvement and maintenance services. The contract is funded through the American Recovery and Reinvestment Act (ARRA) and is for work on the Cascade Baer West Fork Rock Creek Road #2071 in Red Lodge, Montana. The contract does not have a set-aside designation.
Generated 4/2/25, 9:57 AM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
RECOVERY - CUSTER NATIONAL FOREST, FY09 West Fork Rock Creek Road Reconstruction | AG-0355-S-09-0004 | Department of Agriculture Forest Service R1-Northern Region | Award Notice 1/1 | 1/30/09, 12:50 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 14 | Funding Only Action | ($27k) | 10/26/10 | |
| 13 | Change Order | ($25k) | 8/17/10 | |
| 12 | Change Order | $35.1k | 7/29/10 | |
| 11 | Change Order | $0 | 4/5/10 | |
| 10 | Change Order | $99.7k | 3/9/10 |