Definitive Contract 697DCK18C00225
Award Date 5/15/18
Potential Completion Date 1/30/19
Potential Value $339K
Funding Federal Agency
Contracting Federal Agency
Ultimate Awardee
Not listed Set-Aside Type
Total Small Business
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
San Antonio, TX 78216, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
4
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Department of Transportation Federal Aviation Administration awarded a definitive contract valued at $708,397 to Joe R. Jones Construction, Inc. for construction services to upgrade the runway 04 localizer and glide slope instrument landing system at San Antonio International Airport in San Antonio, Texas. Performance will occur at the airport location over a one year period concluding in September 2021. The firm fixed price contract has a total small business set aside designation. Joe R....
- This is a $372,319.00 definitive contract awarded by the Department of Transportation Federal Aviation Administration Headquarters to Joe R. Jones Construction, Inc., a small business contractor, for the replacement of the VASIS (Visual Approach Slope Indicator System) on Runway 17R and 35L with PAPI (Precision Approach Path Indicator) at the Abilene Regional Airport in Abilene, Texas. The contract was awarded on July 20, 2017, with a completion date of December 15, 2017. This contract is a firm...
- This is a definitive contract awarded by the Federal Aviation Administration (FAA), a civilian agency within the U.S. Department of Transportation, to Joe R. Jones Construction, Inc., a small business prime contractor. The $278,571.00 firm fixed-price contract is for the construction and installation of Runway 7 Approach Lighting System Facility (ALSF) stations and an ALSF access road at Toledo Express Airport in Ohio. The contract has a total small business set-aside designation. The work...
- This is a definitive contract awarded by the U.S. Department of Transportation's Federal Aviation Administration (FAA) to Joe R. Jones Construction, Inc., a small business prime contractor. The contract, valued at $273,124.00, is for the upgrade of electrical distribution panels and lighting at two FAA Very High Frequency Omnidirectional Range (VOR) sites located in Marfa, Texas and Pecos, Texas. The contract has a completion date of May 31, 2024 and was awarded on December 20, 2021 as a total...
- This is a definitive contract awarded by the Department of Transportation Federal Aviation Administration (DOT FAA) to Joe R. Jones Construction, Inc., a small business, to replace Runway 30 Visual Approach Slope Indicator (VASI) with new Precision Approach Path Indicator (PAPI) at Santa Maria Public Airport (SMX) in Santa Maria, California. The firm-fixed-price contract, valued at $395,812.00, is a total small business set-aside. The project aims to upgrade the airport's approach guidance...
- This is a $1,069,274.00 definitive firm-fixed-price contract awarded by the Department of Transportation Federal Aviation Administration Headquarters to Joe R. Jones Construction, Inc., a for-profit small business, to provide construction services for the upgrade of Runway 02 Instrument Landing System (ILS) at Louis Armstrong International Airport in Kenner, Louisiana. The contract is designated as a total small business set-aside. Joe R. Jones Construction, Inc. has provided similar...
- This federal contract award is for the construction of a new precision approach path indicator (PAPI) system and demolition of an existing visual approach slope indicator (VASI) system at Runway 9L on Gillespie Field in El Cajon, California. The $353,915.00 definitive contract was awarded on November 7, 2019 to the small business prime contractor Joe R. Jones Construction, Inc. The work is to be completed by June 30, 2022 and is funded by the Department of Transportation Federal Aviation...
- This is a $247,487.00 definitive contract award to Joe R. Jones Construction, Inc., a small business, by the Department of Transportation Federal Aviation Administration Headquarters. The contract is for the establishment of a Distance Measuring Equipment (DME) at Alamo Landing Field Airport in Alamo, Nevada. The contract has a firm fixed price and a completion date of March 27, 2020. As a small business prime contractor, Joe R. Jones Construction, Inc. has provided similar construction services...
- This is a firm fixed price definitive contract awarded by the Federal Aviation Administration (FAA) to Joe R. Jones Construction, Inc., a small business prime contractor, to replace the Heating, Ventilation, and Air Conditioning (HVAC) system and environmental controls for the San Antonio Air Traffic Control Tower (SAT ATCT) at San Antonio International Airport in San Antonio, Texas. The contract has a ceiling value of $1,268,053.00 and a period of performance through March 30, 2018. This...
- This is a federal contract awarded by the Department of Transportation Federal Aviation Administration (FAA) to Joe R. Jones Construction, Inc., a small business, to replace a Visual Approach Slope Indicator (VASI) with a Precision Approach Path Indicator (PAPI) system on Runway 33 at the Lake Charles Regional Airport in Louisiana. The contract is a definitive, firm-fixed price contract valued at $237,122.00. Joe R. Jones Construction, Inc. has provided similar services to the FAA, including for...
The Department of Transportation Federal Aviation Administration Headquarters awarded a $338,992.00 Firm Fixed Price Definitive Contract to Joe R. Jones Construction, Inc., a for-profit small business, for the RUNWAY 31L ILS-420 UPGRADE-SAN ANTONIO, TX project. This contract was set aside for total small business participation. The contract involves precision approach path indicator system installation, localizer upgrades, distance measuring equipment establishment, and tower replacements to upgrade lighting, navigation aids, and approach guidance technology at the San Antonio, TX airport. This work aims to meet Federal Aviation Administration standards and requirements to improve flight navigation by upgrading aging infrastructure.
Generated 3/22/24, 10:21 PM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00004 | Change Order | $18.8k | 12/20/18 | |
| P00003 | Change Order | $12.7k | 10/25/18 | |
| P00001 | Change Order | $5.8k | 8/2/18 | |
| Not listed | Not listed | $301.6k | 5/15/18 |