Definitive Contract 693C7320C000019
Award Date 6/1/20
Potential Completion Date 3/20/23
Potential Value $3.4M
Federal Agency
Ultimate Awardee
Not listed NAICS Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
8(a) Sole Source
Extent Competed
Not Available for Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Annandale, VA 22003, USA
Solicitation Procedures
Only One Source
Number Of Offers Received
1
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a $3,886,185.71 firm fixed-price federal contract awarded by the Federal Highway Administration (FHWA) to Veterans Kitchen Maintenance Inc., a minority-owned small disadvantaged business, for the replacement of two timber trail bridges and reconstruction of asphalt approaches on the George Washington Memorial Parkway in McLean, Virginia. The contract is set aside for total small businesses and is part of the FHWA's Eastern Federal Lands Highway Division project NP-GWMP MVT(5) with an...
- This is a federal contract awarded by the National Park Service, a civilian agency within the U.S. Department of the Interior, to Pdi-Sheetz Construction Corp, a small disadvantaged business, for the recovery and rehabilitation of Mount Vernon Trail (MVT) Bridge No. 7 on the George Washington Memorial Parkway. The $105,188 firm fixed-price contract involves the complete replacement of the bridge's decking, stringers and headers, as well as the installation of standard handrails and the...
- The Federal Highway Administration awarded a firm fixed-price definitive contract to Fort Myer Construction Corp for the George Washington Memorial Parkway Mount Vernon Trail Reconstruction project on November 3, 2025, with a ceiling value of $44.4 million and ultimate completion by May 31, 2029. This award is a modification that adds CLIN 00303 in the amount of $1.4 million, increasing the total contract amount from $43.0 million to $44.4 million. The project addresses deferred maintenance...
- The Federal Highway Administration has awarded a $759.5K firm fixed-price definitive contract to Terra Site Constructors LLC, a minority-owned 8(a) small disadvantaged business, to repair an embankment failure near the Mount Vernon Trail Bridge 26 in Alexandria, Virginia. The slope failure, identified by a trail user on January 10, 2024, extends into the trail and required immediate stabilization efforts. A recent contract modification extended the project timeline by 113 calendar days, with...
- This is a $6,157,070.31 firm fixed-price definitive contract awarded by the National Park Service to Terra Site Constructors LLC, a minority-owned small disadvantaged business certified under the SBA 8(a) program. The contract is for a bridge and pavement preservation project in Front Royal, VA, which includes bridge preservation, preventive maintenance, repair activities, as well as roadway preservation, maintenance, repair, and safety work. The contract has an ultimate completion date of April...
- This is a firm fixed-price delivery order contract awarded by the Federal Highway Administration, a civilian agency, to Pciroads LLC, a for-profit limited liability company. The contract is for PROJECT: SHEN BMS(1) BRIDGES AND TUNNEL PREVENTATIVE MAINTENANCE - SKYLINE DRIVE, with a ceiling value of $302,955.90 and an ultimate completion date of August 2, 2016. The contract was awarded on January 14, 2016 and does not have a set-aside designation. The major program code is SHEN BMS(1), and the...
- This is a definitive, firm fixed-price contract awarded by the Federal Highway Administration, a civilian agency, to Kiewit Infrastructure Co. to permanently rehabilitate the concrete approach spans and replace the bascule span on the Arlington Memorial Bridge. The total ceiling value of the contract is $201,451,160.83, and the ultimate completion date is June 21, 2024. The contract is not set aside for any specific business type. Kiewit Infrastructure Co. is a child company of Kiewit-Turner A...
- The Department of Transportation Federal Highway Administration awarded a firm fixed-price definitive contract to Martins Construction Corp., a for-profit Subchapter S Corporation, for the rehabilitation of the Windy Run Bridge on the George Washington Memorial Parkway in Arlington, VA. The $3,076,737.69 project includes partial-depth removal and repair of the concrete bridge deck, placing a latex-modified concrete overlay, cleaning and painting steel bridge members, asphalt pavement work, and...
- <p>This is a firm fixed-price delivery order contract awarded by the Federal Highway Administration, a civilian federal agency, to Pciroads LLC, a for-profit limited liability company. The contract, valued at $550,818.00, is for bridge preventative maintenance work under the project "SER BMS FY15(1) - GRSM BRIDGES" to be performed in Sterling, Virginia. The contract has no set-aside designation and was awarded on September 11, 2015 with a completion date of April 13, 2016.</p>
- This is a $17,871,118.33 definitive contract awarded by the Federal Highway Administration, a civilian agency, to Fay Southeast Inc., a foreign-owned for-profit company doing business as Iconusa. The contract is for the replacement of the existing 658-foot, 16-span, prestressed concrete girder Route 105 (Ft. Eustis Blvd) bridge over the Lee Hall Reservoir in Newport News, Virginia. The new bridge will be 676 feet long with 9 prestressed concrete bulb-T spans. The contract has a firm fixed...
This is a $3,443,844.16 definitive, firm-fixed-price design-build contract awarded by the Federal Highway Administration, a civilian agency, to Puyenpa Services, LLC, a tribally-owned small business. The contract is for the replacement of the Mount Vernon Trail Bridge #12 and realignment of the bridge approaches in Annandale, Virginia. This 8(a) sole source contract has a completion date of March 20, 2023. Puyenpa Services, LLC holds several indefinite delivery/indefinite quantity (IDIQ) contract vehicles with various federal agencies to provide IT, construction, and facility services on an ongoing basis.
Generated 3/28/25, 10:56 AM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00006 | Close Out | $0 | 3/27/25 | |
| P00005 | Other Administrative Action | $0 | 1/20/23 | |
| P00004 | Other Administrative Action | $0 | 9/9/22 | |
| P00003 | Other Administrative Action | $0 | 7/28/22 | |
| P00002 | Funding Only Action | $21.8k | 3/1/22 |