Definitive Contract 47PJ0023C0013

Award Date 5/17/23
Potential Completion Date 7/31/25
Potential Value $3.6M
Federal Agency
Region 8
Ultimate Awardee
MYR Group Inc.
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Not Competed
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Lakewood, CO 80225, USA
Solicitation Procedures
Only One Source
Number Of Offers Received
1
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
The General Services Administration (GSA) Public Buildings Service Region 8 awarded a $808,264.55 firm-fixed-price definitive contract to Sturgeon Electric Company, Inc., a subsidiary of MYR Group Inc., for construction work at the Denver Federal Center in Lakewood, Colorado. The contract involves replacing equipment and underground cabling throughout the site and upgrading items identified in engineering reports for Building 41 Service C and Buildings 54 and 55 transformers. This includes...
This federal contract award to Sturgeon Electric Company, Inc. is for electrical grid upgrades at the Denver Federal Center in Lakewood, Colorado. The $408,955.13 firm fixed-price contract was awarded by the General Services Administration's (GSA) Public Buildings Service Region 8 and has an ultimate completion date of August 7, 2017. Sturgeon Electric, a subsidiary of MYR Group Inc., has extensive experience supporting federal facilities through both prime and subcontract awards, with a focus...
The General Services Administration (GSA) Public Buildings Service Region 8 awarded a $567,990.05 firm fixed price definitive contract to Sturgeon Electric Company, Inc., a subsidiary of MYR Group Inc., to perform electrical upgrades at Building 53 F and G lines of the Denver Federal Center in Lakewood, Colorado. The contract has a completion date of October 31, 2021. Sturgeon Electric has extensive experience supporting electrical infrastructure projects at federal facilities, including...
This firm fixed-price delivery order was awarded by the General Services Administration's Public Buildings Service Region 8 to Sturgeon Electric Company, Inc., a subsidiary of MYR Group Inc., to upgrade the DFC X-Y feed parallel transformer project at the Denver Federal Center in Lakewood, Colorado. The award has a ceiling value of $126,513.28 and a completion date of September 2, 2019. Sturgeon Electric is an experienced federal contractor that has provided a wide range of electrical...
This firm fixed-price delivery order was awarded by the General Services Administration's (GSA) Public Buildings Service Region 8 to Sturgeon Electric Company, Inc., a subsidiary of MYR Group Inc. The $52,802.52 contract is for the repair of lighting circuits and transformer disposal at the Denver Federal Center in Lakewood, Colorado. This delivery order is part of a larger $2,952,509.03 indefinite delivery contract that Sturgeon Electric holds with GSA Region 8 for electrical operations and...
This firm fixed-price delivery order contract, valued at $22,665.00, was awarded by the General Services Administration's (GSA) Public Buildings Service Region 8 to Sturgeon Electric Company, Inc., a subsidiary of MYR Group Inc. The contract is for the GATE 2 ELECTRICAL UPGRADE project at the Denver Federal Center in Lakewood, Colorado. The work involves electrical construction and infrastructure upgrades at this civilian federal facility. Sturgeon Electric is an experienced federal...
This federal contract award to Sturgeon Electric Company, Inc., a subsidiary of MYR Group Inc., is for the installation of path lighting at Gate 5 of the Denver Federal Center in Lakewood, Colorado. The $35,142.00 firm fixed-price delivery order was issued by the General Services Administration's (GSA) Public Buildings Service Region 8. The contract has no set-aside designation and is intended to provide electrical infrastructure upgrades at the 665-acre Denver Federal Center campus, which...
This is a firm-fixed-price delivery order awarded by the General Services Administration's Public Buildings Service Region 8 to Sturgeon Electric Company, Inc. for the repair of switchgear located near Building 810 at the Denver Federal Center in Lakewood, Colorado. The contract has a ceiling value of $24,350.00 and a completion date of December 15, 2017. Sturgeon Electric Company, Inc. is a specialty electrical contractor and subsidiary of MYR Group Inc. that provides a wide range of electrical...
This is a firm fixed-price delivery order awarded by the General Services Administration's (GSA) Public Buildings Service Region 8 to Sturgeon Electric Company, Inc., a subsidiary of MYR Group Inc. The $8,319.97 task order is for a Substations Findings Report at the Denver Federal Center in Lakewood, Colorado. Sturgeon Electric has an indefinite delivery contract (IDV) with GSA Region 8 for high and low voltage electrical system operations and maintenance, as well as solar energy services, at...
This is a firm fixed-price delivery order awarded by the General Services Administration's (GSA) Public Buildings Service Region 8 to Sturgeon Electric Company, Inc., a subsidiary of MYR Group Inc. The $204,936.58 contract is for utility upgrades at Buildings 53 C, D1, and D2 at the Denver Federal Center in Lakewood, Colorado. The work includes various electrical construction, repair, and upgrade projects across the 665-acre campus. This delivery order is issued under Sturgeon Electric's...

The U.S. General Services Administration (GSA) awarded a $3,604,112.75 firm-fixed-price contract to Sturgeon Electric Company, Inc., a subsidiary of MYR Group Inc., to replace a 22.4 MVA substation transformer and associated switchgear at the Denver Federal Center in Lakewood, Colorado. The project involves engineering, procurement, and installation of the new transformer and switchgear, as well as civil and electrical infrastructure work to support the replacement. This contract is not associated with any set-aside program. Sturgeon Electric Company, Inc. is the current operations and maintenance contractor for the electrical grid at the Denver Federal Center, a 665-acre campus that houses multiple federal agencies. This contract award is part of Sturgeon Electric's ongoing support for the facility's electrical infrastructure and 8 MW solar energy system through a $2,952,509.03 indefinite delivery vehicle contract with the GSA Public Buildings Service Region 8.

Generated 4/8/25, 9:51 AM