Definitive Contract 140P2020C0020
- Not listed
- This is a definitive contract awarded by the Department of the Interior National Park Service to Pacific Gas and Electric Company (PG&E), a for-profit energy company, to provide emergency generator rental services in support of operations at Yosemite National Park in California. The contract is a firm fixed-price award with a potential value of $633,932.89 and a completion date of December 31, 2018. The contract does not have a set-aside designation. As a subcontractor, Aggreko, LLC, a...
- This is a firm fixed-price delivery order for $568,785.00 awarded by the National Office (an alternate name for a civilian federal agency) to Pacific Gas and Electric Company (PG&E) for power generation services during an outage at Yosemite National Park in California. The contract has an ultimate completion date of September 25, 2025 and does not utilize a set-aside designation. PG&E is a for-profit energy utility company that provides comprehensive utility services to various federal...
- This is a firm fixed-price delivery order contract awarded by the National Office of a civilian federal agency to Pacific Gas and Electric Company (PG&E), a for-profit utility company, for power generation services at Yosemite National Park. The contract has a ceiling value of $491,641.23 and a period of performance through February 28, 2025. There is no set-aside designation for this award. In addition to this contract, PG&E has received numerous other prime contracts and task orders...
- This is a firm fixed-price purchase order awarded by the Department of the Interior National Park Service Pacific West Region to Pacific Gas and Electric Company (PG&E) for $167,612.96 to provide emergency generator rental services to support operations at Yosemite National Park in California. The contract does not have a set-aside designation. As a major utility provider, PG&E has experience delivering a range of energy and infrastructure services to support government operations,...
- The U.S. Department of the Interior issued a delivery order valued at $218,249.95 to Pacific Gas and Electric Company (PG&E) on February 27, 2026, for administrative camp services at Yosemite National Park in El Portal, California. This firm fixed-price contract, which carries no set-aside designation, will be completed by March 30, 2026. The delivery order falls under PG&E's existing utility service relationships with federal agencies, leveraging the company's extensive infrastructure...
- The U.S. Department of the Interior awarded a $411,053.73 firm fixed-price delivery order to Pacific Gas and Electric Company (PG&E) for transmission tower repair work at Yosemite National Park in California. The contract, which was competitively awarded without set-aside designation, carries an ultimate completion date of September 24, 2025. This delivery order likely falls under one of PG&E's existing indefinite delivery vehicles, such as the $50 million GSA Public Buildings Service...
- Pacific Gas and Electric Company (PG&E) has been awarded a $287,435.28 firm fixed price delivery order from the Department of the Interior's National Park Service National Office to provide YOSE-GENERATION FOR POWER OUTAGE services in San Francisco, California. This order was issued on February 10, 2023 under an unspecified contract vehicle and does not include a set-aside designation. As the prime contractor, PG&E will deliver electricity generation services to support outage...
- The National Park Service awarded an $8.9 million firm fixed price contract to Pacific Gas and Electric Company (PG&E) to replace or repair approximately 5.1 miles of 70-kilovolt transmission line within Yosemite National Park in California. The line provides power to Yosemite Valley and surrounding areas serving up to 20,000 daily visitors and residents. Work will include repairs and replacements to address deficiencies identified in condition assessments of the towers, insulators, and...
- This is a $554,691.00 firm fixed price construction contract awarded by the National Park Service, Pacific West Region, to Helios Resources, LTD, an Alaskan Native Corporation-owned, minority-owned, and self-certified small disadvantaged business. The contract is for the replacement of the existing generator set with a new Tier 4 generator set at the Yosemite Valley Substation Building in Yosemite National Park, California. The work includes the removal of the existing generator set and the...
- This is a firm fixed price delivery order contract awarded by the National Park Service (NPS), Pacific West Region, to Pacific Gas and Electric Company (PG&E) for $26,798.90. The contract is to support services to review and comment on pre-design reports, feasibility analysis, design alternatives, and schematic design for conformance with PG&E standards, for the development of a photovoltaic project design and implementation. It also includes securing applicable land use authorizations...
This is a firm fixed price definitive contract awarded by the Department of the Interior's National Park Service to Pacific Gas and Electric Company (PG&E) for $498,831.00 to provide a stationary generator hub at the Yosemite Valley Station in Yosemite National Park, California. The contract has a completion date of December 31, 2020 and was awarded on April 29, 2020 without any set-aside designation. PG&E, as a utility services provider, has experience delivering electricity, natural gas, and infrastructure upgrades to support federal government operations across various agencies including the Department of Defense, Department of Justice, Department of Veterans Affairs, and National Aeronautics and Space Administration. This award is not associated with a larger contract vehicle.
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00001 | Supplemental Agreement for work within scope | $0 | 10/23/20 | |
| Not listed | Not listed | $498.8k | 4/29/20 |