BPA Call AG02NVB100004-AG0343K110003
Award Date 12/2/10
Potential Completion Date 3/31/16
Potential Value $3.8M
Funding Federal Agency
Contracting Federal Agency
Ultimate Awardee
Not listed NAICS Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Soda Springs, ID 83276, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
Not listed
Legislative Mandate
Not listed National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- EPA Region 7 issued a delivery order to Ch2M Hill, Inc. on September 23, 2021, for the Madison County Mines Superfund Site, Operable Unit 1 Remedial Investigation/Feasibility Study with a ceiling value of $3.2 million and an ultimate completion date of September 30, 2028. This delivery order is issued under the EPA Remedial Acquisition Framework: Design and Engineering Services (DES), a cost-plus-fixed-fee parent vehicle. Place of performance is Fredericktown, Missouri. The order covers remedial...
- EPA Region 2 issued a delivery order to Versar-Wsp JV on June 5, 2026, with a ceiling value of $1,480,246.65 under the EPA Remedial Acquisition Framework: Design and Engineering Services (RAF DES) IDIQ for a remedial investigation and feasibility study at the Arsenic Mine Superfund site in Kent, New York. The RAF DES is a multiple-award IDIQ vehicle supporting remedial investigation, feasibility studies, site characterization, and remedial design services across EPA regional offices. Place of...
- EPA Region 9 issued a delivery order to Ch2M Hill, Inc. on September 29, 2025, with a ceiling value of $19.1 million for remedial design and remedial action support at the Iron King Mine-Humboldt Smelter site, with ultimate completion September 24, 2029. The order is issued under the EPA Remedial Acquisition Framework: Design and Engineering Services (DES) IDIQ. Work is performed in San Francisco, CA under cost-plus-fixed-fee pricing. The award incorporates a statement of work and adds funding...
- EPA Region 8 issued a delivery order to CDM Federal Programs Corporation (doing business as CDM Smith) on May 28, 2026, with a ceiling value of $1,803,562.18 under the EPA Remedial Acquisition Framework: Design and Engineering Services (DES) to provide remedial design support for implementation of a remedial action at the Upper Tenmile Creek Mining District in East Helena, Montana. The order is priced on a cost-plus-fixed-fee basis with an ultimate completion date of November 30, 2028. Work is...
- On June 23, 2023, the U.S. Army Corps of Engineers Engineering District Omaha awarded a $12.3 million cost-plus-fixed-fee delivery order to CDM Smith-Bay West JV, A Joint Venture for long-term remedial investigation and feasibility studies at the Bonita Peak mining site in Silverton, Colorado. This delivery order, which operates under the parent Northwest Division Environmental Remediation Services - Unrestricted 2021-2026 multiple award task order contract, supports the Corps' environmental...
- This is a new task order awarded by the U.S. Environmental Protection Agency (EPA) Region 9 to EA Engineering, Science, and Technology, Inc., PBC, a for-profit environmental consulting firm. The $1,409,526.62 task order is for a Remedial Investigation/Feasibility Study for the Klau/Buena Vista Mine Pilot Study. It is not a set-aside contract. The task order includes work plan and cost estimate development. Major subcontractors include Papich Construction Company, Inc. for sediment basin...
- EPA Region 9 issued a delivery order to EA Engineering, Science, And Technology, Inc., PBC on September 30, 2024, under the EPA Remedial Acquisition Framework: Design and Engineering Services (DES) vehicle for a remedial investigation and feasibility study at the Copper Bluff Mine, with a ceiling value of $9,155,604.98. The order exercises optional tasks and funds CLINs 0023, 0032, and 0039 under cost-plus-fixed-fee pricing. The EPA Remedial Acquisition Framework (DES) is a total small...
- This contract was awarded by the Environmental Protection Agency (EPA) Region 7 to A And M Engineering & Environmental Services, Inc., a minority-owned small disadvantaged business certified as a HUBZone firm by the Small Business Administration. The $6,429,962.00 Firm Fixed Price Delivery Order contract is for remedial action at the WCLD (Potosi, Old Mines, Furnace Creek) sites under Operable Unit 01. This task order is part of a larger Indefinite Delivery Vehicle (IDV) contract between A...
- The U.S. Environmental Protection Agency Region 7 awarded a modification to delivery order 68HE0718D0005 to A and M Engineering & Environmental Services, Inc. for remedial action work at the Washington County Lead District (WCLD) Operable Unit 01, encompassing sites in Potosi, Old Mines, and Furnace Creek, Missouri. This modification de-obligates excess funds and closes out the task order, which was originally awarded on July 28, 2023, with a ceiling value of $6.0 million on a firm...
- EPA Region 7 issued a delivery order to A and M Engineering & Environmental Services, Inc., an SBA-certified HUBZone small business, on September 22, 2023, with a ceiling value of $33.7 million for remedial action at the Oronogo-Duenweg Mining Belt, Operable Unit 1, in the Tri-State Mining District, under a total small business set-aside. Place of performance is Joplin, Missouri. Ultimate completion date is November 30, 2028. The order is firm fixed price. A and M has invoiced $10.3...
- AG02NVB100004Blanket Purchase Agreement
- AG02NVB100004-AG0343K110003BPA Call
REMEDIAL INVESTIGATION/FEASIBILITY STUDIES ON THE EAST MILL OPERABLE UNIT-MINES
Posted 12/2/10
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 16 | Close Out | ($151k) | 3/22/17 | |
| 15 | Other Administrative Action | ($104k) | 2/24/16 | |
| 14 | Supplemental Agreement for work within scope | $39.7k | 4/23/15 | |
| 13 | Supplemental Agreement for work within scope | $117.2k | 4/7/15 | |
| 12 | Supplemental Agreement for work within scope | $48.1k | 2/11/15 |