4 versions

Update #4 · Latest ·

Added: Mar 15, 2016 1:26 pm Modified: Apr 21, 2016 11:19 amTrack Changes IGF::OT::IGF The purpose of amendment 1 is to provide April 19, 2016 contractor construction site visit questions and answers.



This project improves the existing El Portal Wastewater Treatment Plant Headworks. The work includes removal of existing manual bar rack and replacement with an automatic self-cleaning mechanical bar rack with an adjacent washer/compactor unit. Screenings disposal assembly consisting of a concrete pad, retaining wall, 4 yard dumpster, and stainless steel platform/chute. Replacement of the existing grit washer. See the attached clauses, provisions, Construction Drawings & Specifications, and other attachments for complete requirements.



In accordance with FAR 36.204, the estimated magnitude of construction for all base line items is between $250,000 and $500,000.

Update #3 ·

Added: Mar 15, 2016 1:26 pm Modified: Mar 30, 2016 7:40 pmTrack Changes IGF::OT::IGF This project improves the existing El Portal Wastewater Treatment Plant Headworks. The work includes removal of existing manual bar rack and replacement with an automatic self-cleaning mechanical bar rack with an adjacent washer/compactor unit. Screenings disposal assembly consisting of a concrete pad, retaining wall, 4 yard dumpster, and stainless steel platform/chute. Replacement of the existing grit washer. See the attached clauses, provisions, Construction Drawings & Specifications, and other attachments for complete requirements.



In accordance with FAR 36.204, the estimated magnitude of construction for all base line items is between $250,000 and $500,000.

Update #2 ·

Added: Mar 15, 2016 1:26 pm Modified: Mar 22, 2016 10:57 amTrack Changes IGF::OT::IGF This project improves the existing El Portal Wastewater Treatment Plant Headworks. The work includes removal of existing manual bar rack and replacement with an automatic self-cleaning mechanical bar rack with an adjacent washer/compactor unit. Screenings disposal assembly consisting of a concrete pad, retaining wall, 4 yard dumpster, and stainless steel platform/chute. Replacement of the existing grit washer. See the attached clauses, provisions, Construction Drawings & Specifications, and other attachments for complete requirements.



In accordance with FAR 36.204, the estimated magnitude of construction for all base line items is between $250,000 and $500,000.

Update #1 ·

Added: Mar 15, 2016 1:26 pm IGF::OT::IGF This project improves the existing El Portal Wastewater Treatment Plant Headworks. The work includes removal of existing manual bar rack and replacement with an automatic self-cleaning mechanical bar rack with an adjacent washer/compactor unit. Screenings disposal assembly consisting of a concrete pad, retaining wall, 4 yard dumpster, and stainless steel platform/chute. Replacement of the existing grit washer. See the attached clauses, provisions, Construction Drawings & Specifications, and other attachments for complete requirements.



In accordance with FAR 36.204, the estimated magnitude of construction for all base line items is between $500,000 and $1,000,000.

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
This project Improves the existing El Portal Waste Latest Award Notice
Yose-repair/replace epwwtp headworks This notice · Original Award Notice

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity