Unnamed Project
Awarded Award Notice Posted
- Solicitation number
- W912EK-15-R-0017
- Agency
- ENDIST Rock Island US Army Corps of Engineers, Department of Defense
- Awarded
- to Gale Construction Company Of Illinois
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- W912EK15C0043 Federal contract award
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Not on record
- Place of performance
- Usace District, Rock Island P.O. Box 2004, Clock Tower Building, Attn: Cemvr-CT Rock Island IL 61204 US
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
Added: Jul 20, 2015 10:28 am Modified: Jul 20, 2015 11:18 amTrack Changes Posted in Error, see pre-solicitation notice W912EK-15-B-0005.
Update #1 ·
Added: Jul 20, 2015 10:28 am
The Base Bid scope of work is for the removal of existing and installation of new steam lines along the existing tainter gates dam and includes, but is not limited to: the removal and demolition of existing steam lines, insulation, drop branches, hangers, supports, heat trace and appurtenances and the installation of new steam lines, insulation, drop branches, hangers, supports, heat trace and appurtenances as indicated along the existing dam.
Option A
The Option A scope of work is for the removal of the existing and installation of a new boiler, pumps and appurtenances within and adjacent to the boiler house and includes, but is not limited to: the partial demolition of existing boiler house interior walls, the removal of the existing boiler and associated pumps and mechanical items, and the removal of existing electrical items and the installation of new structural items, a new boiler with associated pumps and mechanical items, and new electrical items as indicated in and adjacent to the existing boiler house.
Option B
The Option B scope of work is for the repair of the boiler house roof and filling of the chimney and includes, but is not limited to: the removal of existing ballast, a vent, metal attachments, and metal covers, the temporary removal of testing equipment and the installation of new metal coping with flashing, new EPDM roofing system, the filling of the existing chimney with grout, and the replacement of the testing equipment.
Option C
The option C scope of work is for the improvement of the boiler house valve pits and includes, but is