Sanitary_Disposal_Sys_Replacement

Awarded Award Notice Posted

Solicitation number
47PB0418R0019
Agency
Region 1 Public Buildings Service, General Services Administration
Awarded
to Steibris, Pete
Set-aside
Total Small Business

Opportunity facts

Contract number
47PB0418C0018 Federal contract award
NAICS code
238220 Plumbing, Heating, and Air-Conditioning Contractors
PSC
Not on record
Place of performance
West Berkshire Land Port of Entry, State Route 118, West Berkshire, VT West Bershire, Vermont, United States

Notice details come from SAM.gov. Updated .

Notice text

2 versions

Update #2 · Latest ·

Awarded Vendors: Pete Steibris O N C. Contract Award Dollar Amount: 88,700. Contract Award Date: 2018-09-19.

Update #1 ·

This project replaces the West Berkshire Land Port of Entry in West Berkshire, VT Sewer System. The current US Border contains a failing soil disposal system requiring complete replacement.


Provide a complete replacement system. Consider best options based on included site plans, existing systems in place, storm water and other obstacles within the property, The replacement system should be protected and fully operational within the property.


Additional factors:
1. Include frost protection and adequate drainage.
2. Adequate insulation and other pipe protection methods should be investigated to prevent potential frost concerns.
3. The main sewer line will require complete replacement from inside the building, currently cast pipe, out to new components.
4. Existing systems in place may need to be removed/ rerouted based on best design options
5. Reference current fixture count at the building to size accordingly.
6. Maintain a minimal size of 2500 gallon tank for maximum solid and effluent capacity.
7. Adequate design staff should be retained and Design Completed prior to any permitting and construction.
8. Design service Provided by Contractor to include, but not limited to furnishing complete functional design including civil engineering, architectural, mechanical, and other engineering services for design, investigation, estimating, final working drawings and specifications by execution of a firm fixed price task order for Design and Construction.


Please provide a copy of the following documents with your bid.
1. Price proposal with breakouts per trade, materials, labor, and equipment.
2. Timeline Schedule showing milestones, lead times on materials, and planned length of project.
3. Narrative with planned approach to performing the work, for each task, to include: Design plan, outlined to show specific method to obtain a buildable and fully-functioning Sanitary Disposal system layout considering required setbacks.


.

On GovTribe