Saginaw CDF Incremental Dike Raising Phase II

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W911XK25BA004
Agency
ENDIST Detroit US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Z2KF Repair Or Alteration Of Dredging Facilities
Points of contact
More information

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers Detroit District is seeking a contractor to complete Phase II of the Saginaw CDF Incremental Dike Raising project, which involves constructing and raising the south perimeter dike of a containment facility. The primary contract objectives include clearing vegetation, utilizing existing CDF materials to raise the dike to an elevation of +18 LWD with 3H:1V slopes, preparing subgrade, compacting fill, and planting grass for erosion control. The solicitation (ID: W911XK25BA004) is structured with multiple line items covering mobilization, topographic surveys, vegetation clearing, and dike construction. Bids were due by April 10, 2025, with contractors required to submit 20% bid security and acknowledge contract amendments. Evaluation criteria appear to focus on comprehensive pricing across defined line items and adherence to technical specifications.

The contract is designated as a Total Small Business set-aside, targeting smaller engineering and civil construction firms within the NAICS 237990 category (Other Heavy and Civil Engineering Construction). The Abstract of Bids indicates 10 total bidders, including companies like Anglin Civil LLC, C&M Asset Holdings LLC, and Walsh Service Solutions. The government's estimated project budget ranges from $424,109 to $2,825,000 per line item, with a total potential project value around $6,445,000. The work will be performed at the Saginaw CDF, with site access through the northeast platform, and contractors will be expected to mobilize, complete the dike raising, and demobilize upon project completion. The project involves precise engineering requirements, including elevating a weir to at least +15 LWD and maintaining specific slope gradients.

Notice text

4 versions

Update #4 · Latest ·

Posting the Bid Abstract ***Amendment 0002 is issued to extend the bid due date from March 27, 2025 to April 10, 2025 and to provide government responses to questions received. FAR clauses 52.204-8 and 52.223-23 have been deleted and replaced with 52.204-8 (Deviation 2025-O0004) and 52.223-23 (Deviation 2025-O0004). All other terms and conditions remain unchanged.*** ***Amendment 0001 is issued to remove FAR Clauses in accordance with Class Deviation 2025-O0003 Restoring Merit Based Opportunity In Federal Contracts, Issued March 4, 2025. Full details can be found in the amendment document. All other terms and conditions remain unchanged.*** This project includes the construction of Phase II of the incremental raising of the south perimeter dike at the Saginaw CDF. Mobilize to the site through the northeast platform of the CDF. Clear and grub the brush and vegetation from the dike construction limits and all material borrow areas. Material from the CDF will be used to raise the dike, excluding NE cell. Grade and compact the raised south dike to EL +18 LWD with 3H:1V slopes including subgrade preparation and compaction prior of fill placement; raising area around weir to +12.5 LWD including elevating the weir to at least +15 LWD. Plant grass on the exterior slope of the raised dike for erosion control. Demobilize when complete.

Update #3 ·

***Amendment 0002 is issued to extend the bid due date from March 27, 2025 to April 10, 2025 and to provide government responses to questions received. FAR clauses 52.204-8 and 52.223-23 have been deleted and replaced with 52.204-8 (Deviation 2025-O0004) and 52.223-23 (Deviation 2025-O0004). All other terms and conditions remain unchanged.*** ***Amendment 0001 is issued to remove FAR Clauses in accordance with Class Deviation 2025-O0003 Restoring Merit Based Opportunity In Federal Contracts, Issued March 4, 2025. Full details can be found in the amendment document. All other terms and conditions remain unchanged.*** This project includes the construction of Phase II of the incremental raising of the south perimeter dike at the Saginaw CDF. Mobilize to the site through the northeast platform of the CDF. Clear and grub the brush and vegetation from the dike construction limits and all material borrow areas. Material from the CDF will be used to raise the dike, excluding NE cell. Grade and compact the raised south dike to EL +18 LWD with 3H:1V slopes including subgrade preparation and compaction prior of fill placement; raising area around weir to +12.5 LWD including elevating the weir to at least +15 LWD. Plant grass on the exterior slope of the raised dike for erosion control. Demobilize when complete.

Update #2 ·

***Amendment 0001 is issued to remove FAR Clauses in accordance with Class Deviation 2025-O0003 Restoring Merit Based Opportunity In Federal Contracts, Issued March 4, 2025. Full details can be found in the amendment document. All other terms and conditions remain unchanged.*** This project includes the construction of Phase II of the incremental raising of the south perimeter dike at the Saginaw CDF. Mobilize to the site through the northeast platform of the CDF. Clear and grub the brush and vegetation from the dike construction limits and all material borrow areas. Material from the CDF will be used to raise the dike, excluding NE cell. Grade and compact the raised south dike to EL +18 LWD with 3H:1V slopes including subgrade preparation and compaction prior of fill placement; raising area around weir to +12.5 LWD including elevating the weir to at least +15 LWD. Plant grass on the exterior slope of the raised dike for erosion control. Demobilize when complete.

Update #1 ·

This project includes the construction of Phase II of the incremental raising of the south perimeter dike at the Saginaw CDF. Mobilize to the site through the northeast platform of the CDF. Clear and grub the brush and vegetation from the dike construction limits and all material borrow areas. Material from the CDF will be used to raise the dike, excluding NE cell. Grade and compact the raised south dike to EL +18 LWD with 3H:1V slopes including subgrade preparation and compaction prior of fill placement; raising area around weir to +12.5 LWD including elevating the weir to at least +15 LWD. Plant grass on the exterior slope of the raised dike for erosion control. Demobilize when complete.

Attachments

Files attached to this notice, newest first
File Type Posted
Abstract of Bids (FINAL) W911XK25BA004.pdf PDF

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Saginaw CDF Incremental Dike Raising Phase II Award Award Notice
Saginaw CDF Incremental Dike Raising Phase II This notice · Latest solicitation Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity