RQ-4 Maintenance Stands

Awarded Award Notice Posted

Solicitation number
FA4686-16-R-0008
Agency
Air Combat Command Air Force, Department of Defense
Awarded
to CV International, Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
FA4686-16-P-0031 Federal contract award
NAICS code
332312 Fabricated Structural Metal Manufacturing
PSC
Not on record
Place of performance
Beale AFB, California 95903, United States

Notice details come from SAM.gov. Updated .

Notice text

8 versions

Update #8 · Latest ·

Added: Jul 08, 2016 11:06 am Modified: Aug 02, 2016 8:36 pmTrack Changes The following Questions were asked:

1. When is the product needed by?

The product is needed by 1 December 2016.

2. How will the RFQ be evaluated?

There is a discrepancy between the solicitation and Statement of Work in terms of how the RFQ will be evavluated. Ultimately, it will be evaluated by price and technical acceptability.

3. OSHA requirement for handrail is 42" tall with 21" midrail and
kickplate.  What portion of the handrail is to be capable of sliding or
folding and to what dimension?

The Aircraft will be backed into the insert so the front of the
aircraft will be facing the hangar doors. We would like to be able to tow
the aircraft into the hanger with most of the stands still in place. This
would require for the forward facing stands to have foldable, removable or a
collapsible feature in order to accomplish this. The remaining hand rails on
the aft side of the aircraft can have fixed rails, no need to have this
feature on that end.

4.  Are adjustable deck sections (sliders) required to conform to the
aircraft surface or is it adequate for the fixed flat leading edge of the
stand to be padded?  If flat-faced stands are utilized, depending on the
contour of the aircraft surface, it may leave gaps between the stand and the
aircraft surface into which maintenance technicians could fall.  Adjustable
deck sections are recommended.

No sliders will be required surrounding the fuselage, but a padded
edge to avoid damage will be required. Although, we require sliders on the
stands that surround the wings to accommodate our personal during sanding
operations. These should be long enough so the leading edge and trailing
edge sliders can meet underneath the wing. The intent is to provide a full
plane beneath the wing so maintainers can lay under the wing to perform the
sanding operations.


 5. Please clarify what coverage is required on the diagonal
stabilizers and around the tail area?  Are stands required to provide access
to the underside and topside of the diagonal stabilizers and, if so, does
the limitation to a maximum size of 5' X 6' apply to the tail stand?

No special requirements are needed to accommodate the vertical
stabilizers, the stand wrapping around the tail will be sufficient. Local
stands will be used if higher areas are required to be reached.


 6. Since the stands are limited to 5' X 6' and they will be modular
and with no fixed position, i.e. all the wing and fuselage stands are
interchangeable, are we to interpret the above that each modular stand
section is to be equipped with the pre filter/air water separator and air
regulator or should we interpret this that only the four air fitting attach
points should be equipped with pre filter/air water separator and air
regulator.  If this is the case, please confirm each 5' X 6' stand, however,
should be equipped with quick disconnect fittings and ball valves.

It was determined that not every stand has to be equipped with
these hook ups and that they are to be located at only 12 locations
throughout the platform. 2 on either side of the nose, 2 on either side of
the tail, 2 at the wing root aft of the wings and 2 on the wing root forward
of the wings and 2 on each wing tip (1 forward of wing tip and 1 aft of wing
tip, Left and Right side) to make a total of 12.


*PLEASE SEE UPDATED STATEMENT OF NEED AND UPDATED CLIN STRUCTURE IN THE SOLICITATION 

*CLOSE OUT DATE EXTENDED TO AUG 8, 2016 at NOON (12PM).

7. The wording is somewhat contradictory in the requirements for air in the specifications. Are we correct to read it that each supply air inlet is to have the capacity for 150 cfm, where a filter/separator will be located, with trunk lines capable of 150 cfm to each branch, which would have 3/8" supply line from the trunk to the 2-outlet manifolds, which will be supplied with 3/8" couplers? Is there a particular location that the 4 inlets should be located?


We would like the air inlets at the most forward nose side, the tail section and each wing tip.



8. What Skid Steer Loader is being referenced?


Please disregard any reference to Skid Steer Loader.


9. Does CLIN 0001 include all our Engineering and PM labor as well as Beale AFB Personnel visitation to our facility costs and Beale AFB Final (Drawing?) Approval/Inspection of drawings?


If necessary, this would talk to a final site visit for the winning bidder to take final measurements.


10. What costs will our company incur relative to Beale AFB Personnel visitation here other than the time that our people spend showing them around and talking with them?


No Beale AFB employee will need to visit the winning bidder's company.


11. How many days do they anticipate being here to satisfy the CLIN 0001 requirements?


If necessary, the final visit will last at most 1 day.



12. Does CLIN 0002 include all material and build related costs as well as the freight charges to ship to Beale AFB, CA? Currently CLIN 0002 only states Delivery unlike the original Solicitation in CLIN 0001listing "RQ-4 Maintenance Stand" With "Include Delivery Cost in Total Price". Should there be an additional CLIN showing the requirement for "RQ-4 Maintenance Stand" listed separately?


CLIN 002 covers materials, production and delivery.


13. Originally, We had anticipated that Beale AFB Personnel would off-load the delivery trucks and maneuver the individual stands to wherever they wish. Do you wish to add costs for our company personnel to do this for them?


We would like a vendor to offload the trucks.


14. Does CLIN 0003 apply to Beale AFB Personnel conducting an equipment inspection at their facility upon equipment delivery? Relates back to the above question on off-loading by Beale AFB personnel performing this or a requirement for our company to supply off-load personnel.


Beale AFB personnel will complete the inspection of the product.


15. What customer training will be required by CLIN 0003? Are they looking for a hands-on showing of how these platforms can be pushed into place and locked together? Or, do they require paper documentation showing this? Relates back to the above question on off-loading by Beale AFB personnel performing this or a requirement for our company to supply off-load personnel and provide training by our company.


We would like a representative to show us how to set-up and use the stands.


16. Do you want lighting or electrical outlets on the stands?

No.

17. What height do you want the stands?

This will be determined at Post-Award.

Update #7 ·

Added: Jul 08, 2016 11:06 am Modified: Jul 28, 2016 2:47 pmTrack Changes The following Questions were asked:

1. When is the product needed by?

The product is needed by 1 December 2016.

2. How will the RFQ be evaluated?

There is a discrepancy between the solicitation and Statement of Work in terms of how the RFQ will be evavluated. Ultimately, it will be evaluated by price and technical acceptability.

3. OSHA requirement for handrail is 42" tall with 21" midrail and
kickplate.  What portion of the handrail is to be capable of sliding or
folding and to what dimension?

The Aircraft will be backed into the insert so the front of the
aircraft will be facing the hangar doors. We would like to be able to tow
the aircraft into the hanger with most of the stands still in place. This
would require for the forward facing stands to have foldable, removable or a
collapsible feature in order to accomplish this. The remaining hand rails on
the aft side of the aircraft can have fixed rails, no need to have this
feature on that end.

4.  Are adjustable deck sections (sliders) required to conform to the
aircraft surface or is it adequate for the fixed flat leading edge of the
stand to be padded?  If flat-faced stands are utilized, depending on the
contour of the aircraft surface, it may leave gaps between the stand and the
aircraft surface into which maintenance technicians could fall.  Adjustable
deck sections are recommended.

No sliders will be required surrounding the fuselage, but a padded
edge to avoid damage will be required. Although, we require sliders on the
stands that surround the wings to accommodate our personal during sanding
operations. These should be long enough so the leading edge and trailing
edge sliders can meet underneath the wing. The intent is to provide a full
plane beneath the wing so maintainers can lay under the wing to perform the
sanding operations.


 5. Please clarify what coverage is required on the diagonal
stabilizers and around the tail area?  Are stands required to provide access
to the underside and topside of the diagonal stabilizers and, if so, does
the limitation to a maximum size of 5' X 6' apply to the tail stand?

No special requirements are needed to accommodate the vertical
stabilizers, the stand wrapping around the tail will be sufficient. Local
stands will be used if higher areas are required to be reached.


 6. Since the stands are limited to 5' X 6' and they will be modular
and with no fixed position, i.e. all the wing and fuselage stands are
interchangeable, are we to interpret the above that each modular stand
section is to be equipped with the pre filter/air water separator and air
regulator or should we interpret this that only the four air fitting attach
points should be equipped with pre filter/air water separator and air
regulator.  If this is the case, please confirm each 5' X 6' stand, however,
should be equipped with quick disconnect fittings and ball valves.

It was determined that not every stand has to be equipped with
these hook ups and that they are to be located at only 12 locations
throughout the platform. 2 on either side of the nose, 2 on either side of
the tail, 2 at the wing root aft of the wings and 2 on the wing root forward
of the wings and 2 on each wing tip (1 forward of wing tip and 1 aft of wing
tip, Left and Right side) to make a total of 12.


*PLEASE SEE UPDATED STATEMENT OF NEED AND UPDATED CLIN STRUCTURE IN THE SOLICITATION 

*CLOSE OUT DATE EXTENDED TO AUG 5, 2016 at NOON (12PM).

7. The wording is somewhat contradictory in the requirements for air in the specifications. Are we correct to read it that each supply air inlet is to have the capacity for 150 cfm, where a filter/separator will be located, with trunk lines capable of 150 cfm to each branch, which would have 3/8" supply line from the trunk to the 2-outlet manifolds, which will be supplied with 3/8" couplers? Is there a particular location that the 4 inlets should be located?


We would like the air inlets at the most forward nose side, the tail section and each wing tip.



8. What Skid Steer Loader is being referenced?


Please disregard any reference to Skid Steer Loader.


9. Does CLIN 0001 include all our Engineering and PM labor as well as Beale AFB Personnel visitation to our facility costs and Beale AFB Final (Drawing?) Approval/Inspection of drawings?


If necessary, this would talk to a final site visit for the winning bidder to take final measurements.


10. What costs will our company incur relative to Beale AFB Personnel visitation here other than the time that our people spend showing them around and talking with them?


No Beale AFB employee will need to visit the winning bidder's company.


11. How many days do they anticipate being here to satisfy the CLIN 0001 requirements?


If necessary, the final visit will last at most 1 day.



12. Does CLIN 0002 include all material and build related costs as well as the freight charges to ship to Beale AFB, CA? Currently CLIN 0002 only states Delivery unlike the original Solicitation in CLIN 0001listing "RQ-4 Maintenance Stand" With "Include Delivery Cost in Total Price". Should there be an additional CLIN showing the requirement for "RQ-4 Maintenance Stand" listed separately?


CLIN 002 covers materials, production and delivery.


13. Originally, We had anticipated that Beale AFB Personnel would off-load the delivery trucks and maneuver the individual stands to wherever they wish. Do you wish to add costs for our company personnel to do this for them?


We would like a vendor to offload the trucks.


14. Does CLIN 0003 apply to Beale AFB Personnel conducting an equipment inspection at their facility upon equipment delivery? Relates back to the above question on off-loading by Beale AFB personnel performing this or a requirement for our company to supply off-load personnel.


Beale AFB personnel will complete the inspection of the product.


15. What customer training will be required by CLIN 0003? Are they looking for a hands-on showing of how these platforms can be pushed into place and locked together? Or, do they require paper documentation showing this? Relates back to the above question on off-loading by Beale AFB personnel performing this or a requirement for our company to supply off-load personnel and provide training by our company.


We would like a representative to show us how to set-up and use the stands.


16. Do you want lighting or electrical outlets on the stands?

No.

17. What height do you want the stands?

This will be determined at Post-Award.

Update #6 ·

Added: Jul 08, 2016 11:06 am Modified: Jul 22, 2016 2:59 pmTrack Changes The following Questions were asked:

1. When is the product needed by?

The product is needed by 1 December 2016.

2. How will the RFQ be evaluated?

There is a discrepancy between the solicitation and Statement of Work in terms of how the RFQ will be evavluated. Ultimately, it will be evaluated by price and technical acceptability.

3. OSHA requirement for handrail is 42" tall with 21" midrail and
kickplate.  What portion of the handrail is to be capable of sliding or
folding and to what dimension?

The Aircraft will be backed into the insert so the front of the
aircraft will be facing the hangar doors. We would like to be able to tow
the aircraft into the hanger with most of the stands still in place. This
would require for the forward facing stands to have foldable, removable or a
collapsible feature in order to accomplish this. The remaining hand rails on
the aft side of the aircraft can have fixed rails, no need to have this
feature on that end.

4.  Are adjustable deck sections (sliders) required to conform to the
aircraft surface or is it adequate for the fixed flat leading edge of the
stand to be padded?  If flat-faced stands are utilized, depending on the
contour of the aircraft surface, it may leave gaps between the stand and the
aircraft surface into which maintenance technicians could fall.  Adjustable
deck sections are recommended.

No sliders will be required surrounding the fuselage, but a padded
edge to avoid damage will be required. Although, we require sliders on the
stands that surround the wings to accommodate our personal during sanding
operations. These should be long enough so the leading edge and trailing
edge sliders can meet underneath the wing. The intent is to provide a full
plane beneath the wing so maintainers can lay under the wing to perform the
sanding operations.


 5. Please clarify what coverage is required on the diagonal
stabilizers and around the tail area?  Are stands required to provide access
to the underside and topside of the diagonal stabilizers and, if so, does
the limitation to a maximum size of 5' X 6' apply to the tail stand?

No special requirements are needed to accommodate the vertical
stabilizers, the stand wrapping around the tail will be sufficient. Local
stands will be used if higher areas are required to be reached.


 6. Since the stands are limited to 5' X 6' and they will be modular
and with no fixed position, i.e. all the wing and fuselage stands are
interchangeable, are we to interpret the above that each modular stand
section is to be equipped with the pre filter/air water separator and air
regulator or should we interpret this that only the four air fitting attach
points should be equipped with pre filter/air water separator and air
regulator.  If this is the case, please confirm each 5' X 6' stand, however,
should be equipped with quick disconnect fittings and ball valves.

It was determined that not every stand has to be equipped with
these hook ups and that they are to be located at only 12 locations
throughout the platform. 2 on either side of the nose, 2 on either side of
the tail, 2 at the wing root aft of the wings and 2 on the wing root forward
of the wings and 2 on each wing tip (1 forward of wing tip and 1 aft of wing
tip, Left and Right side) to make a total of 12.


*PLEASE SEE UPDATED STATEMENT OF NEED AND UPDATED CLIN STRUCTURE IN THE SOLICITATION 

*CLOSE OUT DATE EXTENDED TO AUG 5, 2016 at NOON (12PM).

7. The wording is somewhat contradictory in the requirements for air in the specifications. Are we correct to read it that each supply air inlet is to have the capacity for 150 cfm, where a filter/separator will be located, with trunk lines capable of 150 cfm to each branch, which would have 3/8" supply line from the trunk to the 2-outlet manifolds, which will be supplied with 3/8" couplers? Is there a particular location that the 4 inlets should be located?


We would like the air inlets at the most forward nose side, the tail section and each wing tip.



8. What Skid Steer Loader is being referenced?


Please disregard any reference to Skid Steer Loader.


9. Does CLIN 0001 include all our Engineering and PM labor as well as Beale AFB Personnel visitation to our facility costs and Beale AFB Final (Drawing?) Approval/Inspection of drawings?


If necessary, this would talk to a final site visit for the winning bidder to take final measurements.


10. What costs will our company incur relative to Beale AFB Personnel visitation here other than the time that our people spend showing them around and talking with them?


No Beale AFB employee will need to visit the winning bidder's company.


11. How many days do they anticipate being here to satisfy the CLIN 0001 requirements?


If necessary, the final visit will last at most 1 day.



12. Does CLIN 0002 include all material and build related costs as well as the freight charges to ship to Beale AFB, CA? Currently CLIN 0002 only states Delivery unlike the original Solicitation in CLIN 0001listing "RQ-4 Maintenance Stand" With "Include Delivery Cost in Total Price". Should there be an additional CLIN showing the requirement for "RQ-4 Maintenance Stand" listed separately?


CLIN 002 covers materials, production and delivery.


13. Originally, We had anticipated that Beale AFB Personnel would off-load the delivery trucks and maneuver the individual stands to wherever they wish. Do you wish to add costs for our company personnel to do this for them?


We would like a vendor to offload the trucks.


14. Does CLIN 0003 apply to Beale AFB Personnel conducting an equipment inspection at their facility upon equipment delivery? Relates back to the above question on off-loading by Beale AFB personnel performing this or a requirement for our company to supply off-load personnel.


Beale AFB personnel will complete the inspection of the product.


15. What customer training will be required by CLIN 0003? Are they looking for a hands-on showing of how these platforms can be pushed into place and locked together? Or, do they require paper documentation showing this? Relates back to the above question on off-loading by Beale AFB personnel performing this or a requirement for our company to supply off-load personnel and provide training by our company.


We would like a representative to show us how to set-up and use the stands.


Update #5 ·

Added: Jul 08, 2016 11:06 am Modified: Jul 15, 2016 11:29 amTrack Changes The following Questions were asked:

1. When is the product needed by?

The product is needed by 1 December 2016.

2. How will the RFQ be evaluated?

There is a discrepancy between the solicitation and Statement of Work in terms of how the RFQ will be evavluated. Ultimately, it will be evaluated by price and technical acceptability.

3. OSHA requirement for handrail is 42" tall with 21" midrail and
kickplate.  What portion of the handrail is to be capable of sliding or
folding and to what dimension?

The Aircraft will be backed into the insert so the front of the
aircraft will be facing the hangar doors. We would like to be able to tow
the aircraft into the hanger with most of the stands still in place. This
would require for the forward facing stands to have foldable, removable or a
collapsible feature in order to accomplish this. The remaining hand rails on
the aft side of the aircraft can have fixed rails, no need to have this
feature on that end.

4.  Are adjustable deck sections (sliders) required to conform to the
aircraft surface or is it adequate for the fixed flat leading edge of the
stand to be padded?  If flat-faced stands are utilized, depending on the
contour of the aircraft surface, it may leave gaps between the stand and the
aircraft surface into which maintenance technicians could fall.  Adjustable
deck sections are recommended.

No sliders will be required surrounding the fuselage, but a padded
edge to avoid damage will be required. Although, we require sliders on the
stands that surround the wings to accommodate our personal during sanding
operations. These should be long enough so the leading edge and trailing
edge sliders can meet underneath the wing. The intent is to provide a full
plane beneath the wing so maintainers can lay under the wing to perform the
sanding operations.


 5. Please clarify what coverage is required on the diagonal
stabilizers and around the tail area?  Are stands required to provide access
to the underside and topside of the diagonal stabilizers and, if so, does
the limitation to a maximum size of 5' X 6' apply to the tail stand?

No special requirements are needed to accommodate the vertical
stabilizers, the stand wrapping around the tail will be sufficient. Local
stands will be used if higher areas are required to be reached.


 6. Since the stands are limited to 5' X 6' and they will be modular
and with no fixed position, i.e. all the wing and fuselage stands are
interchangeable, are we to interpret the above that each modular stand
section is to be equipped with the pre filter/air water separator and air
regulator or should we interpret this that only the four air fitting attach
points should be equipped with pre filter/air water separator and air
regulator.  If this is the case, please confirm each 5' X 6' stand, however,
should be equipped with quick disconnect fittings and ball valves.

It was determined that not every stand has to be equipped with
these hook ups and that they are to be located at only 12 locations
throughout the platform. 2 on either side of the nose, 2 on either side of
the tail, 2 at the wing root aft of the wings and 2 on the wing root forward
of the wings and 2 on each wing tip (1 forward of wing tip and 1 aft of wing
tip, Left and Right side) to make a total of 12.


*PLEASE SEE UPDATED STATEMENT OF NEED AND UPDATED CLIN STRUCTURE IN THE SOLICITATION 

*CLOSE OUT DATE EXTENDED TO AUG 5, 2016 at NOON (12PM).

Update #4 ·

Added: Jul 08, 2016 11:06 am Modified: Jul 14, 2016 7:22 pmTrack Changes The following Questions were asked:

1. When is the product needed by?

The product is needed by 1 December 2016.

2. How will the RFQ be evaluated?

There is a discrepancy between the solicitation and Statement of Work in terms of how the RFQ will be evavluated. Ultimately, it will be evaluated by price and technical acceptability.

3. OSHA requirement for handrail is 42" tall with 21" midrail and
kickplate.  What portion of the handrail is to be capable of sliding or
folding and to what dimension?

The Aircraft will be backed into the insert so the front of the
aircraft will be facing the hangar doors. We would like to be able to tow
the aircraft into the hanger with most of the stands still in place. This
would require for the forward facing stands to have foldable, removable or a
collapsible feature in order to accomplish this. The remaining hand rails on
the aft side of the aircraft can have fixed rails, no need to have this
feature on that end.

4.  Are adjustable deck sections (sliders) required to conform to the
aircraft surface or is it adequate for the fixed flat leading edge of the
stand to be padded?  If flat-faced stands are utilized, depending on the
contour of the aircraft surface, it may leave gaps between the stand and the
aircraft surface into which maintenance technicians could fall.  Adjustable
deck sections are recommended.

No sliders will be required surrounding the fuselage, but a padded
edge to avoid damage will be required. Although, we require sliders on the
stands that surround the wings to accommodate our personal during sanding
operations. These should be long enough so the leading edge and trailing
edge sliders can meet underneath the wing. The intent is to provide a full
plane beneath the wing so maintainers can lay under the wing to perform the
sanding operations.


 5. Please clarify what coverage is required on the diagonal
stabilizers and around the tail area?  Are stands required to provide access
to the underside and topside of the diagonal stabilizers and, if so, does
the limitation to a maximum size of 5' X 6' apply to the tail stand?

No special requirements are needed to accommodate the vertical
stabilizers, the stand wrapping around the tail will be sufficient. Local
stands will be used if higher areas are required to be reached.


 6. Since the stands are limited to 5' X 6' and they will be modular
and with no fixed position, i.e. all the wing and fuselage stands are
interchangeable, are we to interpret the above that each modular stand
section is to be equipped with the pre filter/air water separator and air
regulator or should we interpret this that only the four air fitting attach
points should be equipped with pre filter/air water separator and air
regulator.  If this is the case, please confirm each 5' X 6' stand, however,
should be equipped with quick disconnect fittings and ball valves.

It was determined that not every stand has to be equipped with
these hook ups and that they are to be located at only 12 locations
throughout the platform. 2 on either side of the nose, 2 on either side of
the tail, 2 at the wing root aft of the wings and 2 on the wing root forward
of the wings and 2 on each wing tip (1 forward of wing tip and 1 aft of wing
tip, Left and Right side) to make a total of 12.


*PLEASE SEE UPDATED STATEMENT OF NEED AND UPDATED CLIN STRUCTURE IN THE SOLICITATION 

Update #3 ·

Added: Jul 08, 2016 11:06 am Modified: Jul 13, 2016 7:27 pmTrack Changes The following Questions were asked:

1. When is the product needed by?

The product is needed by 1 December 2016.

2. How will the RFQ be evaluated?

There is a discrepancy between the solicitation and Statement of Work in terms of how the RFQ will be evavluated. Ultimately, it will be evaluated by price and technical acceptability.

3. OSHA requirement for handrail is 42" tall with 21" midrail and
kickplate.  What portion of the handrail is to be capable of sliding or
folding and to what dimension?

The Aircraft will be backed into the insert so the front of the
aircraft will be facing the hangar doors. We would like to be able to tow
the aircraft into the hanger with most of the stands still in place. This
would require for the forward facing stands to have foldable, removable or a
collapsible feature in order to accomplish this. The remaining hand rails on
the aft side of the aircraft can have fixed rails, no need to have this
feature on that end.

4.  Are adjustable deck sections (sliders) required to conform to the
aircraft surface or is it adequate for the fixed flat leading edge of the
stand to be padded?  If flat-faced stands are utilized, depending on the
contour of the aircraft surface, it may leave gaps between the stand and the
aircraft surface into which maintenance technicians could fall.  Adjustable
deck sections are recommended.

No sliders will be required surrounding the fuselage, but a padded
edge to avoid damage will be required. Although, we require sliders on the
stands that surround the wings to accommodate our personal during sanding
operations. These should be long enough so the leading edge and trailing
edge sliders can meet underneath the wing. The intent is to provide a full
plane beneath the wing so maintainers can lay under the wing to perform the
sanding operations.


 5. Please clarify what coverage is required on the diagonal
stabilizers and around the tail area?  Are stands required to provide access
to the underside and topside of the diagonal stabilizers and, if so, does
the limitation to a maximum size of 5' X 6' apply to the tail stand?

No special requirements are needed to accommodate the vertical
stabilizers, the stand wrapping around the tail will be sufficient. Local
stands will be used if higher areas are required to be reached.


 6. Since the stands are limited to 5' X 6' and they will be modular
and with no fixed position, i.e. all the wing and fuselage stands are
interchangeable, are we to interpret the above that each modular stand
section is to be equipped with the pre filter/air water separator and air
regulator or should we interpret this that only the four air fitting attach
points should be equipped with pre filter/air water separator and air
regulator.  If this is the case, please confirm each 5' X 6' stand, however,
should be equipped with quick disconnect fittings and ball valves.

It was determined that not every stand has to be equipped with
these hook ups and that they are to be located at only 12 locations
throughout the platform. 2 on either side of the nose, 2 on either side of
the tail, 2 at the wing root aft of the wings and 2 on the wing root forward
of the wings and 2 on each wing tip (1 forward of wing tip and 1 aft of wing
tip, Left and Right side) to make a total of 12.


 

Update #2 ·

Added: Jul 08, 2016 11:06 am The following Questions were asked:

1. When is the product needed by?
The product is needed by 1 December 2016.

2. How will the RFQ be evaluated?
There is a discrepancy between the solicitation and Statement of Work in terms of how the RFQ will be evavluated. Ultimately, it will be evaluated by price and technical acceptability.

Update #1 ·

Added: Jun 28, 2016 6:28 pm

This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in FAR Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested.

This will be a 100% Small Business Set-Aside. The North American Industrial Classification System (NAICS) Code is 332312 -- Fabricated Structural Metal Manufacturing. The Standard Industry Code for this procurement is 3441.  The small business size standard for this procurement, as defined by the U.S. Small Business Administration is 500 employees. Please provide any suggestions or requests if you feel a more appropriate NAICS code exists.

Please complete and return the attached solicitation.

If you have any questions or concerns, please contact 2d Lt Ryan Finley at Ryan.Finley.2@us.af.mil or phone at (530) 634-3370.



 


Attachments

Files attached to this notice, newest first
File Type Posted
RQ-4_Stand_SON_(July14Update).pdf PDF
rq4.docx DOCX document
RQ4_Maintenance_Platform.pdf PDF
2038_Paint_Stand.pptx PPTX presentation
Solicitation.pdf PDF
Hangar_Dimensions.pptx PPTX presentation
GH_dimensions_2.pdf PDF

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
RQ-4 Maintenance Stands This notice · Latest Award Notice
RQ4 Maintenance Stands Original Award Notice

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity