Replace Transformer Station # 21 at Range # 206, GTA
Awarded Award Notice Posted
- Solicitation number
- W912PB15B8011
- Agency
- RCO Bavaria 409th CSB Expeditionary Contracting Command, Department of Defense
- Awarded
- to Josef Pravida
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W912PB-15-C-8006 Federal contract award
- NAICS code
- 238210 Electrical Contractors and Other Wiring Installation Contractors
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
Added: Apr 07, 2015 9:12 am
Modified: Jun 30, 2015 4:47 amTrack Changes
The construction site is located within the Training Area Grafenwoehr.
- Disassembly of the existing medium voltage and low voltage installation devices
inside of the old transformer station # 21, Range # 206, consisting of:
1 each existing oil transformer 100 kVA
1 each existing medium-voltage switching system,
consisting of 4 each medium-voltage cells
1 each existing low-voltage switching system, l x w x d = 2.0 m x 2.0 m x 0.6 m
Disassemble all existing metal structures.
- Demolish the existing transformer building and backfill the construction pit.
(Top course: gravel layer)
- Construction of a new transformer building with cable vault and gable roof,
roof slope 30 degrees.
Size of building: approx. 9.80 m x 3.0 m, clear height 2.60 m,
consisting of:
1 each transformer room,
1 each joint medium-voltage and low-voltage switching room,
1 each telecommunication room for data processing technology,
cable vault of reinforced concrete,
dimensions: l x w x h = 9.80 m x 3.0 m, 0.90 m high
- Installation of a medium-voltage switching system 24 kV, consisting of:
1 each 24 kV transformer control panel
2 each 24 kV insecure cable control panels
2 each 24 kV secure cable control panels with circuit breaker as backup cells
1 each 20 kV oil transformer 250 kVA
- Installation of a low-voltage switching system, consisting of:
1 each transformer circuit breaker 630 A
1 each busbar system 1000 A
4 each fuse load isolating bars 400 A
16 each fuse load isolating bars 160 A
- 1 each cross connection box (EMCS) as wall cabinet.
Relocate all existing medium-voltage and low-voltage cables in the new station.
Earth work:
- Perform soil backfilling work in the area of the new transformer station.
- Provide a construction pit for the new transformer station with cable vault.
- Provide strip foundations for the new transformer station.
- Provide a gravel access road for the new transformer station.
Pave the access roads towards one front side and one longitudinal side.
Provide a gravel layer on the rear surfaces adjacent to the new transformer
station (see drawing).
Restore the adjacent lawn surfaces.
Update #1 ·
Added: Apr 07, 2015 9:12 am
Replace Transformer Station # 21 at Range # 206, Grafenwoehr Training Area. This project consists of the following work - Disassembly of the existing medium voltage and low voltage installation devices inside of the old transformer station, disassemble all existing metal structures, demolish the existing transformer building and backfill the construction pit, construction of a new transformer building with cable vault and gable roof, installation of a medium-voltage switching system 24 kV, installation of a low-voltage switching system, relocate all existing medium-voltage and low-voltage cables in the new station.
Earth work: Perform soil backfilling work in the area of the new transformer station, provide a construction pit for the new transformer station with cable vault, provide strip foundations for the new transformer station, provide a gravel access road for the new transformer station, pave the access roads towards one front side and one longitudial side, provide a gravel layer on the rear surfaces adjacent to the new transformer station, restore the adjacent lawn surfaces.
The solicitation will result in a Firm Fixed Price contract. Magnitude of work: Between $100,000 and $250,000. Time for completion is 210 calendar days, whereby a commencement time of 120 days is included. Work is to be performed in Germany and contractor must comply with German laws (e.g. authorization to do business in Germany). Contractor shall perform on the site and with its own organization work equivalent to at least 30% of the total amount of work to be performed under the contract.
All responsible sources may submit a bid, which will be considered by the Regional Contracting Office - Bavaria. Only local sources are solicited in accordance with FAR 5.202(a)(12). Please contact the contract specialist for any questions.
RCO-Bavaria Point of Contact: MAJ Sean Higgins, +49-9641-83-8716, sean.o.higgins.mil@mail.mil