Replace PWT Switchgear

Awarded Award Notice Posted

Solicitation number
FA9101-16-R-0034
Agency
Air Force Test Center Air Force Materiel Command, Department of Defense
Awarded
to Siemens Industry Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
FA9101-16-C-0041 Federal contract award
NAICS code
221121 Electric Bulk Power Transmission and Control
PSC
Not on record
Place of performance
100 Kindel Drive Suite A332 Arnold AFB, Tennessee 37389, United States

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

Added: Jun 24, 2016 1:36 pm GIS Switchgear

Update #2 ·

Added: Mar 28, 2016 7:13 pm Modified: Mar 28, 2016 7:21 pmTrack Changes NOTICE OF INTENT TO AWARD SOLE SOURCE: Arnold Engineering Development Complex (AEDC) intends to solicit, negotiate, and award a sole source contract to Siemens Energy, Inc., 1345 Ridgeland Parkway Suite 116 Alpharetta, GA 30004 for the design, equipment and installation required for replacement of medium voltage switchgear and primary unit substations. The Building 780 medium voltage switchgear replacement project includes demolishing obsolete 6.9kV switchgear and controls and providing new Siemens switchgear and controls. In addition, the work includes all equipment and installation required for replacement of the MC1 and MC4 medium voltage switchgear in Building 780 and replacing with new medium voltage Gas Insulated Switchgear (GIS).


AEDC has the need to procure medium voltage switchgear that is reliable and safe. Gas Insulated Switchgear (GIS) is the latest technology that provides power without requiring personnel to be equipped with arc flash personal protective equipment (PPE) while operating or maintaining the GIS equipment. Hours of industry wide research, competitive bidding, and accepted maintenance and reliability practice have resulted in the conclusion that Siemens Type 8DA10 Gas Insulated Switchgear is the only switchgear that confines each of the three phases of power in three separate compartments. This is a critical requirement from a safety standpoint and mitigates electrical fault severity to avoid costly shutdowns of the entire system. With the isolation of the phases a factory-trained Siemens employee can remove the damaged phase and replace it with the identical part from a spare cubicle, and return the cubicle to service in a short amount of time. In most cases this work can be completed with the remainder of the switchgear lineup still in service. If spares are available, a new enclosure could be installed from the spare cubicle but the entire lineup would be unavailable throughout the duration of the repair.

Update #1 ·

Added: Mar 28, 2016 7:13 pm Arnold Engineering Development Complex (AEDC) intends to solicit, negotiate, and award a sole source contract to Siemens Energy, Inc., 1345 Ridgeland Parkway Suite 116 Alpharetta, GA 30004 for the design, equipment and installation required for replacement of medium voltage switchgear and primary unit substations. The Building 780 medium voltage switchgear replacement project includes demolishing obsolete 6.9kV switchgear and controls and providing new Siemens switchgear and controls. In addition, the work includes all equipment and installation required for replacement of the MC1 and MC4 medium voltage switchgear in Building 780 and replacing with new medium voltage Gas Insulated Switchgear (GIS).

AEDC has the need to procure medium voltage switchgear that is reliable and safe. Gas Insulated Switchgear (GIS) is the latest technology that provides power without requiring personnel to be equipped with arc flash personal protective equipment (PPE) while operating or maintaining the GIS equipment. Hours of industry wide research, competitive bidding, and accepted maintenance and reliability practice have resulted in the conclusion that Siemens Type 8DA10 Gas Insulated Switchgear is the only switchgear that confines each of the three phases of power in three separate compartments. This is a critical requirement from a safety standpoint and mitigates electrical fault severity to avoid costly shutdowns of the entire system. With the isolation of the phases a factory-trained Siemens employee can remove the damaged phase and replace it with the identical part from a spare cubicle, and return the cubicle to service in a short amount of time. In most cases this work can be completed with the remainder of the switchgear lineup still in service. If spares are available, a new enclosure could be installed from the spare cubicle but the entire lineup would be unavailable throughout the duration of the repair.

Attachments

Files attached to this notice, newest first
File Type Posted
FA9101-16-C-0041_GIS_Switchgear_J A.pdf PDF