Repair Upper Chesapeake Bay Offshore

Awarded Award Notice Posted

Solicitation number
Not on record
Agency
Coast Guard Department of Homeland Security
Awarded
to SAF Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
HSCG83-17-C-PCR060 Federal contract award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

Added: May 30, 2017 1:10 pm Major items of work shall include the following:

Repair Upper Chesapeake Range Front (Structure 8595), consisting of removing, rehabilitating, and reinstalling the existing boat landing platform at a higher elevation; modifying the existing access ladder/cage to accommodate the raised platform; removing and reinstalling overboard rungs; partially recoating the monopole and main deck stringers; replacing the davit crane; and repairs to miscellaneous appurtenances.


Repair Shad Battery SHL Range Front (Structure 8910), consisting of removing, rehabilitating, and reinstalling the existing boat landing platform at a higher elevation; modifying the existing access ladder/cage to accommodate the raised platform; removing and reinstalling overboard rungs; replacing main deck handrails; partially recoating the monopile; replacing the floor in the fiberglass battery building with new plywood and vinyl tile; replacing the davit crane; and repairs to miscellaneous appurtenances.



Work Item #1: Repair Pooles Island North Range Front (Structure 8695), consisting of removing, rehabilitating, and reinstalling the existing boat landing platform at a higher elevation; modifying the existing access ladder/cage to accommodate the raised platform; removing and reinstalling overboard rungs; replacing main deck handrails; partially recoating the monopile; replacing the davit crane; and repairs to miscellaneous appurtenances.


Work Item #2: Repair Pooles Island South Range Front (Structure 8555), consisting of removing, rehabilitating, and reinstalling the existing boat landing platform at a higher elevation; extending the existing access ladder/cage to accommodate the raised platform; replacing the personnel access barrier; removing and reinstalling overboard rungs; replacing boat landing handrails; partially recoating the monopile; replacing the davit crane; and repairs to miscellaneous appurtenances.


Work Item #3: Repair Pooles Island North/South Range Rear (Structure 8560/8700), consisting of removing, rehabilitating, and reinstalling the existing boat landing platform at a higher elevation; modifying the existing access ladder/cage to accommodate the raised platform; removing and reinstalling overboard rungs; partially recoating the monopile; replacing two davit cranes; and repairs to miscellaneous appurtenances.

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity