Meve paint wetherill mesa tank
Closed Pre-Solicitation Posted
- Solicitation number
- 140P1218R0020
- Agency
- National Park Service Department of the Interior
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- 140P1218C0010 Federal contract award
- NAICS code
- 238320 Painting and Wall Covering Contractors
- PSC
- Not on record
- More information
Notice details come from SAM.gov. Updated .
Notice text
10 versions
Update #10 · Latest ·
MEVE PAINT WETHERILL MESA TANK.
Update #9 ·
MEVE PAINT WETHERILL MESA TANK.
Update #8 ·
MEVE PAINT WETHERILL MESA TANK.
Update #7 ·
MEVE PAINT WETHERILL MESA TANK.
Update #6 ·
MEVE PAINT WETHERILL MESA TANK.
Update #5 ·
MEVE PAINT WETHERILL MESA TANK.
Update #4 ·
MEVE PAINT WETHERILL MESA TANK.
Update #3 ·
MEVE PAINT WETHERILL MESA TANK.
Update #2 ·
Synopsis â€" Amendment 1
PAINT WETHERILL MESA TANK
Mesa Verde National Park (MEVE)
(1) Date: August 7, 2018
(2) Product or Service Code: J046
(3) Contracting Office Address:
NATIONAL PARK SERVICE
Intermountain Region â€" Lakewood MABO
12795 West Alameda Parkway
(4) Subject: Paint Wetherill Mesa Tank, Mesa Verde National Park (MEVE)
(5) Proposed Solicitation Number: 140P1218R0020
(6) Closing Response Date: Sept 14, 2018
(7) Contact Point or Contracting Officer: Marcia Fox
The purpose of this pre-solicitation amendment is to respond to questions received.
1. Has the existing coatings been tested for lead? Are you looking for a number for mitigation?
Yes, interior ceiling paint results exceed limits. See attached sample results.
2. Will bids with exclusions be acceptable?
No
3. Is there anybody going to be overseeing inspections?
Park COR will be on site. Will also need paint manufacture warranty inspector.
4. Will there be another contractor performing other duties beside coatings removal / install?
General contractor can hire subs for other plumbing, tank repairs in contract.
5. Will there be an pre-proposal site visit?
A pre-proposal site visit will be scheduled for 8/21/2018 starting at Stan White's office at 9 am then to Wetherill mesa water tank by 10 am.
6. Is the source of the soil contamination concern from the tank itself?
Yes, the old existing lead paint is from tank itself.
Everything else remains the same. The solicitation and supporting documentation will be released on 8/15/2018.
.
Update #1 ·
Synopsis
PAINT WETHERILL MESA TANK
Mesa Verde National Park (MEVE)
(1) Date: July 31, 2018
(2) Product or Service Code: J046
(3) Contracting Office Address:
NATIONAL PARK SERVICE
Intermountain Region â€" Lakewood MABO
12795 West Alameda Parkway
(4) Subject: Paint Wetherill Mesa Tank, Mesa Verde National Park (MEVE)
(5) Proposed Solicitation Number: 140P1218R0020
(6) Closing Response Date: Sept 14, 2018
(7) Contact Point or Contracting Officer: Marcia Fox
(8) Description
a. PROJECT DESCRIPTION / SUMMARY:
THE PRIMARY WORK OF THIS PROJECT INCLUDES THE STRIPPING AND REPAINTING OF THE INTERIOR (BASE BID), EXTERIOR (OPTION 1) OF THE 300,000 GALLON GROUND LEVEL STEEL WATER TANK, INSTALLATION OF AN INTERIOR STEEL INLET PIPE (OPTION 2), AND TESTING OF LEAD CONTAMINATED SOIL (OPTION 3) LOCATED IN THE WETHERILL MESA AREA OF MESA VERDE NATIONAL MONUMENT. RUBBER GASKETS AROUND ACCESS HATCHES WILL BE REPLACED AND A NEW WATER LEVEL INDICATOR INSTALLED.
b. OBJECTIVES:
THE PRIMARY WORK OF THIS PROJECT INCLUDES THE STRIPPING AND REPAINTING OF THE INTERIOR (BASE BID), EXTERIOR (OPTION 1) OF THE 300,000 GALLON GROUND LEVEL STEEL WATER TANK, INSTALLATION OF AN INTERIOR STEEL INLET PIPE (OPTION 2), AND TESTING OF LEAD CONTAMINATED SOIL (OPTION 3) LOCATED IN THE WETHERILL MESA AREA OF MESA VERDE NATIONAL MONUMENT. RUBBER GASKETS AROUND ACCESS HATCHES WILL BE REPLACED AND A NEW WATER LEVEL INDICATOR INSTALLED.
c. BACKGROUND:
THE PRIMARY WORK OF THIS PROJECT INCLUDES THE STRIPPING AND REPAINTING OF THE INTERIOR (BASE BID), EXTERIOR (OPTION 1) OF THE 300,000 GALLON GROUND LEVEL STEEL WATER TANK, INSTALLATION OF AN INTERIOR STEEL INLET PIPE (OPTION 2), AND TESTING OF LEAD CONTAMINATED SOIL (OPTION 3) LOCATED IN THE WETHERILL MESA AREA OF MESA VERDE NATIONAL MONUMENT. RUBBER GASKETS AROUND ACCESS HATCHES WILL BE REPLACED AND A NEW WATER LEVEL INDICATOR INSTALLED.
d. SPECIFIC WORK / TASKS:
A. SANDBLAST AND REPAINT THE INTERIOR OF THE WATER TANK (BASE BID)
B. SANDBLAST AND REPAINT THE EXTERIOR OF THE WATER TANK (OPTION 1)
C. REMOVE EXISTING INTERIOR PEX INLET PIPE AND INSTALL NEW STEEL INLET PIPE OF SAME DIAMETER (OPTION 2)
D. LEAD SOIL TESTING AND REPORT DETAILING EXTENT OF LEAD CONTAMINATION IN SOIL AND RECOMMENDATIONS FOR ABATEMENT (INCLUDING VOLUME OF SOIL TO EXCAVATE AND REPLACE, OPTION 3).
1. SAMPLES SHALL BE TAKEN AT INTERVALS FROM THE EDGE OF THE WATER TANK TO 20’ AWAY FROM THE TANK. THERE ARE THREE SAMPLE LOCATIONS IN EACH CARDINAL DIRECTION AWAY FROM THE TANK: DISTANCES OF 5’, 10’, 20’ AWAY FROM THE TANK EDGE. SAMPLES SHALL BE TAKEN WITH STANDARD PROTOCOLS.
2. TAKE SOIL SAMPLE AT THE SURFACE (0-2†DEPTH), AND ANOTHER SAMPLE AT THE SUBSURFACE (6-12†DEPTH) TAKEN NO FURTHER THAN 1’ AWAY FROM THE CORRESPONDING SURFACE SAMPLE.
• TAKE NO LESS THAN 24 SAMPLES AT 0-2†DEPTH (SURFACE)
• TAKE NO LESS THAN 24 SAMPLES AT 6-12†DEPTH (SUBSURFACE)
• FIVE CONTROL SAMPLES AT 0-2†DEPTH (SURFACE)
• FIVE CONTROL SAMPLES AT 6’12†DEPTH (SUBSURFACE)
• TOTAL OF 58 SOIL SAMPLES
3. CONTROL SAMPLES SHALL BE TAKEN NO LESS THAN 100 FT AWAY FROM THE OUTSIDE EDGE OF THE WATER TANK
4. INCLUDE MAP OF SAMPLE LOCATIONS WITH APPROXIMATE DISTANCES FROM THE TANK.
5. INCLUDE RAW DATA IN REPORT.
E. INSTALL NEW RUBBER GASKETS AS PER NSF 61 IN ALL MANWAYS, ACCESS HATCHES, AND BETWEEN TANK ROOF AND ROOF VENT APPARATUS
F. INSTALL NEW WATER LEVEL INDICATOR SYSTEM WITH RAIL, GAUGE BOARD, FLOAT SYSTEM, AND ALL OTHER APPURTENANCES AS REQUIRED AND INDICATED BY THE MANUFACTURER.
G. INSTALL WELDED, SEALED STEEL JUNCTION BETWEEN GALVANIZED PIPE (CONTAINING THE EXISTING PRESSURE TRANSDUCER CABLING) AND TANK ROOF
H. CONDUCT PAINT THICKNESS TESTING
I. CONDUCT DISINFECTION OF THE WATER TANK
J. CONDUCT BACTERIA TEST AS PER STATE REQUIREMENTS
K. CONDUCT FIELD TESTING AND VERIFICATION OF SYSTEM FUNCTION AFTER INSTALLATION
L. COMPLETE FINAL CLEAN UP. SUBMIT AS-BUILT DRAWINGS WITH MARK-UPS.
(10) Period of Performance: Estimated Period of performance is 10/15/2018 â€" 12/14/2018.
(12)
a. A description of the procedures to be used in awarding the contract: Request for Proposal
b. The anticipated award date: September 18, 2018
(13) The Request for Proposal will be posted on www.fbo.gov and www.fedconnect.net
Questions can be emailed to marcia_fox@nps.gov. Questions will not be accepted if submitted on FedConnect.
(14) Place of Contract Performance:
a. Mesa Verde National Park
b. Water Tank Area, Wetherill Mesa
c. The Nearest Town is Cortez, CO.
(15) Set-aside Status: Total Small Business Set-Aside.
NAICS 238320 Painting and Wall Covering Contractors
Size Standard $15.0 million
(16) Estimated Construction Magnitude: Between $250,000 and $500,000.
(17) Award shall be made in accordance with FAR Part 15 to the lowest priced technically acceptable proposal with submittals that meet the specifications herein received from a responsible small business (see Subpart 9.1)
.
Attachments
| File | Type | Posted |
|---|---|---|
| FedConnect File | — |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity