Kitchen Drain & Tile Replacement
Awarded Award Notice Posted
- Solicitation number
- VA24416Q1252
- Agency
- Veterans Integrated Service Network 4 Veterans Health Administration, Department of Veterans Affairs
- Awarded
- to Fidelis Design And Construction, LLC
- Set-aside
- Service-Disabled Veteran-Owned Small Business
Opportunity facts
- Contract number
- VA24416C0277 Federal contract award
- NAICS code
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
- PSC
- Not on record
- Place of performance
- 3900 Woodland Ave Philadelphia, PA 19104 USA
Notice details come from SAM.gov. Updated .
Notice text
Added: Jun 21, 2016 10:37 am
DESCRIPTION OF WORK
This Request for Quote (RFQ) will be released on 6-21-2016 with a due date of 6-30-2016 at 3:00 PM. Below is a description of work that will be performed for this project. This is a FAR Part 13 Simplified Acquisition. Statement of work, diagrams, and additional descriptions are in the Statement of Work and will be available in the RFQ.
Phase I Kettle Area
1. Remove Kitchen equipment, store equipment in designated area provided by VA Engineering, project equipment, remove floor and cover base.
2. Remove Trough drain and floor drains in working area.
3. Install new Stainless Steel trough, 6" deep receptor and sediment bucket and Grating.
4. Install new floor drain in front of the middle walking box; install clean-out per national plumbing code.
5. Install new tile and water proof system MAPEI or equal.
6. Reinstall equipment connect piping, power, test, and restart equipment.
7. Work Duration for this phase of the project is 15 calendar days from installing the ICRA wall and inspected and approved by the VA.
8. Work is per SK-1 and SK-2 located in the statement of work.
Phase II Prep Area
1. Remove kitchen equipment, Store equipment in designated area provided by VA Engineering, and protect equipment remove floor and cove base.
2. Remove all floor drains in working area.
3. Install new floor drains and clean outs, per Plumbing National code.
4. Submit cuts for tile, drains, water proof system for VA engineer approval.
5. Install new tile and water proof system MAPEI or equal.
6. Reinstall equipment reconnect piping, power, test, and restart equipment.
7. Work duration for this phase is 15 calendar days from installing the ICRA wall that will be inspected and approved by the VA engineering staff.
8. Work is per SK-1
Attachments
| File | Type | Posted |
|---|---|---|
| VA244-16-Q-1252-004.pdf | ||
| VA244-16-Q-1252-003.docx | DOCX document | |
| VA244-16-Q-1252-002.docx | DOCX document |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity