Keystone Guardrail Replacement
Awarded Award Notice Posted
- Solicitation number
- 12850818R0004
- Agency
- Region 2 - Rocky Mountain Region Forest Service, Department of Agriculture
- Awarded
- to Trinity Of Utah Incorporated
- Set-aside
- Woman-Owned Small Business
Opportunity facts
- Contract number
- 12850818C0010 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- 2468 Jackson Street Laramie, Wyoming 82070, United States
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
Added: Jul 06, 2018 9:16 pm
In response to Solicitation 12850818R0004, the Keystone Guardrail Replacement for the Medicine Bow/Routt National Forest and Thunder Basin National Grasslands is awarded to Trinity of Utah, Inc.
Responsive offers were received from three (3) firms.
One firm fixed price contract shall be awarded for this project to Trinity of Utah, Ogden, UT in the amount of $63,698.
Award was made to the Offeror, whose offer conformed to the solicitation and were found to be the Lowest Price Technically Acceptable to the Government.
Update #1 ·
Added: May 10, 2018 5:08 pm
The Medicine Bow Routt National Forest has a requirement to replaced a damage portion of the guard rail near Rob Roy Resevoir due to damage from fire suppresion activities.
This project consists of the removal, disposal, and replacement of approximately 515 linear feet of damaged guardrail and posts with new G4 W-Beam Guardrail and posts. This project is located approximately 40 miles west of Laramie, Wyoming on National Forest System Road 500. The guardrail system is only being replaced on the north side of the embankment that crosses the northeast finger of Rob Roy Reservoir.
All work shall adhere to industry standards, attached specifications, and manufacturer installation recommendations.
The project shall include all labor, materials, mobilization, equipment, and incidentals necessary to perform the work. This project will be completed under a single construction contract and shall be performed in accordance with all applicable OSHA and U.S. Forest Service safety regulations. The contractor shall be responsible for obtaining all Local, State and Federal permits, as necessary.
The roadway will be open to traffic during construction. Therefore, the Contractor shall take the necessary safety measures to protect employees and the public during construction.
Detailed site plans were not feasible for this project. In lieu of detailed site plans, the site will be staked by the contractor in accordance with the standard guardrail plans and accepted by the contracting officer prior to construction beginning. Final quantities will be measured upon completion of the project and payment will be adjusted according to the bid items listed in the schedule of items.
A PRESOLICITATION CALL WILL BE HELD TO DISCUSS THIS PROJECT ON MAY 23,2018 AT 1:00 P.M. MOUNTAIN TIME
PLEASE RSVP WITH CONTRACTING OFFICER STAR M YEO AT STARMYEO@FS.FED.US IN ORDER TO RECEIVE THE PHONE LINE NUMBER.
A SITE VISIT WILL BE CONDUCTED ON JUNE 18, 2018 AND ALL INTERESTED PARTIES WILL NEED TO RSVP WITH THE CONTRACTING OFFICER STAR M YEO AT STARMYEO@FS.FED.US.
Contract Magnitude: Between $25,000 to $100,000
WOMAN OWNED SET ASIDE
Attachments
| File | Type | Posted |
|---|---|---|
| FP-14_Specs.pdf | ||
| FSSS_Specs.pdf | ||
| Keystone_Fire_Guardrail_Replacement_Map.pdf | ||
| WY41.pdf | ||
| Final_Plans.pdf | ||
| 12850818R0004.pdf |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity