Handrail replacement response to contractor questions

Awarded Award Notice Posted

Solicitation number
36C24718Q0245
Agency
Veterans Integrated Service Network 7 Veterans Health Administration, Department of Veterans Affairs
Awarded
to BTR Enterprises Of SC LLC
Set-aside
No set-aside

Opportunity facts

Contract number
36C24718P0961 Federal contract award
NAICS code
332323 Ornamental and Architectural Metal Work Manufacturing
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

Added: Mar 05, 2018 3:04 pm Modified: Mar 16, 2018 2:07 pmTrack Changes Notice Type: Posted Date:

Responses to Contractor Questions March 16, 2017



Original Set Aside: Response Date:

Open Market Service-Disabled Veteran Owned March 19, 2017 @ 4:30 PM EST

Small Business

Classification Code: NAICS Code:

N054 Installation of Equipment - Prefabricated 332323 Ornamental & Architectural Metal

Structures and Scaffolding work and Manufacturing.



Synopsis:

The Purpose of this amendment is to post questions submitted during the solicitation period of this requirement. Please find questions asked, and responses provided.

*AGENCY RESPONSES ARE IN RED

Question 1: How long can an area go without any handrails? In other words, if the metal fabricator can do 30 LF per day, are we only allowed to have the demo guy remove 30 LF per day?

Answer: This would be the case unless the contractor had a way to secure the falling hazard another way that would meet patient safety guidelines.

 

Question 2: Will gates also need to be replaced?

Answer: Yes, Any gates that are in place now have to be replaced. The gate will be made of the same material as the replacement rails.



Question 3: Will we need to figure on any concrete repair on this project?  If you look at picture attached IMG 2153 & IMG 2151 it looks like concrete was replaced.

Answer: If in removing any existing railing, the concrete would have to be repaired if damaged.



Question 4: There are several types of rails we saw in the pictures.  See attached.  Are we replacing all existing rails with the picket style new rails?

Answer: All rails need to match existing replaced rails at the back of building 22 (see pictures IMG 2151, and IMG 2153) The solicitation is to replace ALL other railing and gates around the facility. The only exceptions are the back of building 22, the loading docks on building 7 and 100.



Question 5: Do you if we will need to me welding it down or core drilling when setting the rails?

Answer: The contractor will need to match the new existing railing that is currently in place on the west side of building 22. If welding is necessary on station, a full assessment as to what risks are involved and patient safety precautions would have to performed before project start.



Question 6: Do you know if we will need to remove the old railing from the job site when it is completed?

Answer: Yes, contractor will be required to remove old handrailing from the job site.



Question 7: The specification mentions the coating finish shall be "18 mil thickness" can you please verify that the 18 is correct or should it be "1.8" which is the industry standard.

Answer: The coating requirement is 18 mils or 0.018 using fluidized bed coating process and a 50 mesh powder.

Update #3 ·

Added: Mar 05, 2018 3:04 pm Modified: Mar 06, 2018 3:13 pmTrack Changes Notice Type: Posted Date:

Combined Synopsis/Solicitation March 6, 2018



Original Set Aside: Response Date:

Open Market Service-Disabled Veteran Owned March 19, 2018 @ 4:30 PM EST

Small Business

Classification Code: NAICS Code:

N054 Installation of Equipment - Prefabricated 332323 Ornamental & Architectural Metal

Structures and Scaffolding work and Manufacturing.



Synopsis:

The purpose of this amendment is to clarify the closing date for solicitation 36C24718Q0245 for handrail replacement. Page 1 of the solicitation document, Form 1449 lists a closing date of March 23, 2018; this is incorrect.



The correct closing date for solicitation 36C24718Q0245 is 4:30pm est on March 19, 2018







Any contractor who believes it is capable of meeting the requirement may submit a bid to the contracting office no later than March 19, 2018 at 4:30 p.m. EST. Bid packages may be sent to Mark West at Jeffrey.west3@va.gov. No telephone responses will be accepted.

Update #2 ·

Added: Mar 05, 2018 3:04 pm Modified: Mar 06, 2018 9:35 amTrack Changes Notice Type: Posted Date:

Combined Synopsis/Solicitation March 6, 2017



Original Set Aside: Response Date:

Open Market Service-Disabled Veteran Owned March 19, 2017 @ 4:30 PM EST

Small Business

Classification Code: NAICS Code:

N054 Installation of Equipment - Prefabricated 332323 Ornamental & Architectural Metal

Structures and Scaffolding work and Manufacturing.



Synopsis:

The purpose of this amendment is to add the specifications required for the new handrails to be installed.

Please see specifications provided below for new handrails to be installed:







Any contractor who believes it is capable of meeting the requirement may submit a bid to the contracting office no later than March 19, 2017 at 4:30 p.m. EST. Bid packages may be sent to Mark West at Jeffrey.west3@va.gov. No telephone responses will be accepted.















Railing Specifications

Handrail Replacement

Handrail cap-to be smooth finish with ¼ wall thickness

All pickets to be ¾ with 1/8 wall thickness

All post to be 1 ¼ with ¼ wall

All aluminum materials used to construct railing and to be 6063 grade and US manufactured

Welds to hold ¼ profile and ground smooth

Powder coat black finish to have a minimum of 18 mil thickness

Coating to have a 2000-hour salt spray test and fabricating contractor/sub-contractor to hold an American Architectural Manufacturers Association 2605 approved Powder Coat Applicator Certificate (certificate shall be supplied with bid as this is an industry standard)

All railing conforms to ADA ramp codes 4.8.5 as specified below.



4.8.5

Handrails:

If a ramp run has a rise greater than 6 inches or a horizontal projection greater than 72 inches, then it shall have handrails on both sides. Handrails shall have the following features.

Handrails shall be provided along both sides of ramp segments. The inside handrail on switchbacks or dogleg ramps shall always be continuous.

If handrails are not continuous, they shall extend at least 12 inches beyond the top and bottom of the ramp segment and shall be parallel with the floor or ground surface.

The clear space between the handrail and the wall shall be 1 1/2 inches.

Handrails may be located in a recess if the recess is a maximum of 3 inches deep and extends at least 18 inches above the top of the rail.

Gripping surfaces shall be continuous, without interruption by newel posts, other construction elements, or obstructions.

The diameter of width of the gripping surface of a handrail shall be 1 1/4 inches to 1 1/2 inches or the shape shall provide an equivalent gripping surface.

The top of the handrail gripping surfaces shall be mounted between 34 inches and 38 inches above ramp surfaces.

A handrail and any wall or other surface adjacent to it shall be free of any sharp or abrasive elements. Edges shall have a minimum radius of 1/8 inch.

National building code specs for commercial handrails should be incorporated.





Specifications



Guardrails and Handrails shall be the product of a company normally engaged in the manufacture of pipe railing. Railings shall be shop assembled in lengths not to exceed 24 feet for field erection.

The handrail shall be made of pipes joined together with component fittings.

Samples of all components, bases, toe board and pipe shall be submitted for approval at the request of the engineer.

Components that are pop-riveted or glued at the joints are not acceptable. All components must be mechanically fastened with stainless steel hardware.

Guardrails and Handrails shall be designed to withstand a 200lb concentrated load applied in any direction and at any point on the top rail. Guardrails and Handrails shall also be designed to withstand a uniform load of 50 lb/ft applied horizontally to the top rail. Uniform loads are not to be applied simultaneously with the concentrated loads.

Pickets and intermediate railings shall be provided such that a 4-inch diameter sphere cannot pass through any opening up to a height of 34 inches. From a height of 34 inches to 42 inches above the adjacent walking surface, a sphere 8 inches in diameter shall not pass.

The triangular openings formed by the riser, tread and bottom rail at the open side of a stairway shall be of a maximum size such that a sphere of 6 inches in diameter cannot pass through the opening.

Pickets and intermediate railings shall be designed to withstand a horizontally applied normal load of 50lb on an area not to exceed one square foot including openings and spaces between rails.

Posts shall not interrupt the continuation of the top rail at any point along the railing, including corners and end terminations (OSHA 1910.23).

The top surface of the top railing shall be smooth and shall not be interrupted by projected fittings.

The mid-rail at a corner return shall be able to withstand a 200lb load without loosening.

A self-closing gate shall guard openings in the railing (OSHA 1910.23).

Safety chains shall not be used unless specifically shown on the drawings.

Finish shall be Aluminum Association M10-C22-A41 (215-R1).

The pipe shall be plastic-wrapped.

The plastic wrap is to be removed after erection.

Aluminum surfaces in contact with concrete, grout or dissimilar metals will be protected with a coat of bituminous paint, Mylar isolators or other approved material.

Update #1 ·

Added: Mar 05, 2018 3:04 pm Notice Type: Posted Date:

Combined Synopsis/Solicitation March 5, 2017



Original Set Aside: Response Date:

Open Market Service-Disabled Veteran Owned March 19, 2017 @ 4:30 PM EST

Small Business

Classification Code: NAICS Code:

N054 Installation of Equipment - Prefabricated 332323 Ornamental & Architectural Metal

Structures and Scaffolding work and Manufacturing.



Synopsis:

The WJB Dorn VA Medical Center located in Columbia South Carolina intends to negotiate a firm fixed priced contract for services to remove and replace approximately 1118 feet of steel pipe handrails and approximately 981 feet of steel grip handrails with powder coated aluminum handrails to match recently installed handrail in other areas. Some of the existing handrails are coated with lead-based paint and must be handled per local and national guidelines that can be provided upon request.

Site Visit:

A site visit is scheduled for Tuesday, March 13, 2017 @ 1:00 pm est. and any contractor interested in competing for this requirement is encouraged to attend to ensure they understand the requirement and prepare any questions they may have following the site visit.

Evaluation Criteria:

American Architectural Manufacturers Association 2605 approved Powder Coat Applicator Certificate.

OSHA 30-Hour Card of On-Site Supervisor that will be assigned.

Past Performance

Technical Capabilities referencing similar services performed.

Please reference section E of the solicitation for complete evaluation criteria.

Any contractor who believes it is capable of meeting the requirement may submit a bid to the contracting office no later than March 19, 2017 at 4:30 p.m. EST. Bid packages may be sent to Mark West at Jeffrey.west3@va.gov. No telephone responses will be accepted.

Attachments

Files attached to this notice, newest first
File Type Posted
36C24718Q0245-004.docx DOCX document
36C24718Q0245-003.docx DOCX document
36C24718Q0245-002.docx DOCX document
36C24718Q0245-001.docx DOCX document
36C24718Q0245-000.docx DOCX document

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Handrail replacement Latest Award Notice
Handrail replacement response to contractor questions This notice · Original Award Notice