Caution to bidders

Awarded Award Notice Posted

Solicitation number
DE-SOL-0008368
Agency
Headquarters Department of Energy
Awarded
to Titan Electric, Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
DESW0000352 Federal contract award
NAICS code
237130 Power and Communication Line and Related Structures Construction
PSC
Not on record
More information

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

Added: May 20, 2015 11:41 am Modified: May 26, 2015 7:56 amTrack Changes THE FOLLOWING ITEMS HAVE BEEN IDENTIFIED AS NEEDING CONSDIERATION IN BIDDING THIS PROJECT:

1. Several poles have rotten tops. 2. Over 100 hot crossings/road crossings that will need to be guarded. Not all are visible from the road. 3. Access to pull sights in some cases may be VERY difficult. 4. Noted dozens of mid span sleeves that may need to be cut out before pulling the new fiber in with the old. (Helicopter work.) 5. Existing Knee braces will dictate that bayonets be installed on most strs. to hang a traveler from. 6. General access is very limited. In some places there is not access. This project MAY need to be constructed with a helicopter. 7. Several river crossings. 8. Limited set up area in and around substations for pulling equipment.

A KMZ FILE IS AVAILABE FOR VIEWING IF REQUESTED FROM SEAN.LONG@SWPA.GOV

Pre-Bid meeting Questions 1. Can we use the existing static wire to pull in the new OPGW.

Answer: Yes if the old static wire will support the pull.

Question 2. I did not find the liquidated damages that would be accessed if the project does not meet the completion requirements. What are the liquidated damages for this project?

Answer: There are no per say liquidated damages. However, if you do not complete the project in time and need a time extension, depending on the circumstances, I will ask for consideration for that extension in terms of what my inspector costs or if any revenue is lost in terms of not being able to generate and supply power, I may seek those loses as well.

Question 3. Is the pre-bid mandatory?

Anwser: NO.

Update #2 ·

Added: May 20, 2015 11:41 am Modified: May 21, 2015 2:54 pmTrack Changes Pre-Bid meeting

Questions 1. Can we use the existing static wire to pull in the new OPGW.

Answer: Yes if the old static wire will support the pull.

Question 2. I did not find the liquidated damages that would be accessed if the project does not meet the completion requirements. What are the liquidated damages for this project?

Answer: There are no per say liquidated damages. However, if you do not complete the project in time and need a time extension, depending on the circumstances, I will ask for consideration for that extension in terms of what my inspector costs or if any revenue is lost in terms of not being able to generate and supply power, I may seek those loses as well.

Question 3. Is the pre-bid mandatory?

Anwser: NO.

Update #1 ·

Added: May 20, 2015 11:41 am Pre-Bid meeting

Questions 1. Can we use the existing static wire to pull in the new OPGW.

Answer: Yes if the old static wire will support the pull.

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Caution to bidders This notice · Latest Award Notice
Springfield-nixa-tablerock-grandview opgw installation Original Award Notice

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity