Caution to bidders
Awarded Award Notice Posted
- Solicitation number
- DE-SOL-0008368
- Agency
- Headquarters Department of Energy
- Awarded
- to Titan Electric, Inc.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- DESW0000352 Federal contract award
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- PSC
- Not on record
- More information
Notice details come from SAM.gov. Updated .
Notice text
3 versions
Update #3 · Latest ·
Added: May 20, 2015 11:41 am
Modified: May 26, 2015 7:56 amTrack Changes
THE FOLLOWING ITEMS HAVE BEEN IDENTIFIED AS NEEDING CONSDIERATION IN BIDDING THIS PROJECT:
1. Several poles have rotten tops. 2. Over 100 hot crossings/road crossings that will need to be guarded. Not all are visible from the road. 3. Access to pull sights in some cases may be VERY difficult. 4. Noted dozens of mid span sleeves that may need to be cut out before pulling the new fiber in with the old. (Helicopter work.) 5. Existing Knee braces will dictate that bayonets be installed on most strs. to hang a traveler from. 6. General access is very limited. In some places there is not access. This project MAY need to be constructed with a helicopter. 7. Several river crossings. 8. Limited set up area in and around substations for pulling equipment.
A KMZ FILE IS AVAILABE FOR VIEWING IF REQUESTED FROM SEAN.LONG@SWPA.GOV
Pre-Bid meeting Questions 1. Can we use the existing static wire to pull in the new OPGW.
Answer: Yes if the old static wire will support the pull.
Question 2. I did not find the liquidated damages that would be accessed if the project does not meet the completion requirements. What are the liquidated damages for this project?
Answer: There are no per say liquidated damages. However, if you do not complete the project in time and need a time extension, depending on the circumstances, I will ask for consideration for that extension in terms of what my inspector costs or if any revenue is lost in terms of not being able to generate and supply power, I may seek those loses as well.
Question 3. Is the pre-bid mandatory?
Anwser: NO.
Update #2 ·
Added: May 20, 2015 11:41 am
Modified: May 21, 2015 2:54 pmTrack Changes
Pre-Bid meeting
Questions 1. Can we use the existing static wire to pull in the new OPGW.
Answer: Yes if the old static wire will support the pull.
Question 2. I did not find the liquidated damages that would be accessed if the project does not meet the completion requirements. What are the liquidated damages for this project?
Answer: There are no per say liquidated damages. However, if you do not complete the project in time and need a time extension, depending on the circumstances, I will ask for consideration for that extension in terms of what my inspector costs or if any revenue is lost in terms of not being able to generate and supply power, I may seek those loses as well.
Question 3. Is the pre-bid mandatory?
Anwser: NO.
Update #1 ·
Added: May 20, 2015 11:41 am
Pre-Bid meeting
Questions 1. Can we use the existing static wire to pull in the new OPGW.
Answer: Yes if the old static wire will support the pull.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Caution to bidders | Award Notice | |
| Springfield-nixa-tablerock-grandview opgw installation | Award Notice |