Questions and Answers WPS.docx

DOCX document 14 KB Posted

Attached to
WPS ANALYST FY 21 Federal contract opportunity
Solicitation number
W91QF0-21-Q-7002
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis

View the file

Other files for this federal contract opportunity

Other files attached to WPS ANALYST FY 21, newest first.
File Type Posted
PWS PKSOI WPS FY21 AMND_2.docx DOCX document
Section 889 Provisions (REVISED Oct 2020).pdf PDF
Quote WPS FY 21.xlsx XLSX spreadsheet
W1QF0-21-Q-7002.pdf PDF
212-1 212-2 WPS.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W91QF0-21-Q-7002 PKSOI WPS Q&A

1. Is this a new requirement or is there an incumbent contractor currently providing these or very similar requirements?

· This is an entirely new requirement.

2. If there is an incumbent contractor, please provide the contract number.

· See #1

3. Were these requirements previously filled by a government employee or under a personal services contract? If a PSC, can you please provide the contract number and/or name of the individual?

· See #1, this was not previously a government employee.

4. Is an active facility clearance required for an offeror to be eligible to submit a quote for this requirement?

· An active facility and individual clearance would both be required to meet the “Highly Qualified” standard of PWS 6.2.9.

5. What is the anticipated value or budget for the award?

· This information shall not be released.

6. Can you please provide further details on the section 1.7.5 Place of Performance? Is remote/telework authorized for all or some portion of the delivery of contract requirements? Can you please provide further details on expectations and customer needs for onsite vs remote delivery of the work according to current Mission/Command policies?

· Remote/telework shall be considered up to 100%, please specify if the candidate intends to be remote.

7. Please clarify if there are page limits or format requirements for the Technical Proposal?

· The Volumes 1 & 2 of the quote does not need to be in a specific format per the 52.212-1 Addendum, however, PDF is the most common format. Volume 3 needs to be either PDF or Excel Spreadsheet. There is no limit on the number of pages, however, our email inboxes do have a maximum size limit of 10 megabytes.

8. Can you please extend the due date for quotations by one week?

· This amendment also extends the solicitation due date until 7 July 2021 @ 0700 EDT.

9. I have a candidate who cannot start until 1 September. Is that acceptable to the government?

· Start date can be negotiated if required. Please state the opening availability of the candidate as a part of the quote (if not 1 August 2021)