W912P519T0048_TSpec.pdf
PDF 3 MB Posted
- Attached to
- Cheatham Lock Transformer Replacement Federal contract opportunity
- Solicitation number
- W912P519T0048
About this file
TSpecs
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912P519T0048P00001.pdf | ||
| US_Citizen_Pre-Bid_or_Site_Visit_Form_AUG_2014.pdf | ||
| FN_Site_Visit_Form_AUG_2016.pdf | ||
| US_Citizen_Pre-Bid_or_Site_Visit_Form_AUG_2014_(4).pdf | ||
| FN_Site_Visit_Form_AUG_2016.pdf | ||
| W912P519T0048__Solicitation.pdf | ||
| W912P519T0048_TPlans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps Of Engineers Nashville District
Lock Power Transformer Replacement
Cheatham Lock Cheatham County, Tennessee
Technical Specifications Certified Final - RTA
July 2019
Contract No. W912P519T0048
THIS PAGE INTENTIONALLY LEFT BLANK
FOR DUPLEX PRINTING
Power Transformer Replacement Cheatham Lock W912P519T0048 Ashland City, TN
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 00 00 GENERAL REQUIREMENTS
01 10 10 CONTRACTOR'S SITE OPERATIONS
01 22 00 PRICE AND PAYMENT PROCEDURES
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 50 PROJECT SITE SECURITY AND AT/OPSEC PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
01 95 00 FORMS AND ATTACHMENTS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
DI VI SI ON 26 - ELECTRI CAL
26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 13 MEDIUM-VOLTAGE CABLE
26 08 01 TRANSFORMER COMMISSIONING
DI VI SI ON 48 - ELECTRI CAL POWER GENERATI ON
48 20 00 TRANSFORMER SHIPMENT, HAULING AND SITE ASSEMBLY
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
1.2 COORDINATION CONFERENCES
1.3 SUBMITTALS
1.4 CONTRACTOR'S STAGING AREA
1.5 DAILY CLEANUP AND DISPOSAL
1.6 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.7 EVALUATION OF CONTRACTOR PERFORMANCE
1.8 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.9 MEASUREMENT AND PAYMENT
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 AVAILABILITY AND USE OF UTILITY SERVICES
3.1.1 Contractor Responsibilities
3.1.2 Interruptions of Utilities
-- End of Section Table of Contents --
SECTION 01 00 00 Page 1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
This section comprises an explanation of the general contract requirements needed to accomplish the work. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and drawings.
1.2 COORDINATION CONFERENCES
Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this project. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to this construction. The Corps of Engineers and the Contractor will be represented at each of these meetings. Coordination conferences will be scheduled to occur when notified by the Contracting Officer.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
1.4 CONTRACTOR'S STAGING AREA
The Contractor will be assigned an area within or near the project site for use as a staging area. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner. Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.
1.5 DAILY CLEANUP AND DISPOSAL
Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.
1.6 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included
SECTION 01 00 00 Page 2 as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.
1.7 EVALUATION OF CONTRACTOR PERFORMANCE
The Contractor's performance will be evaluated in accordance with FAR Part
42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum.
The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section
01 95 00 FORMS AND ATTACHMENTS.
The Contractor's review of the evaluation shall be completed electronically at the CPARS, http://www.cpars.gov . This website also includes guidance and the user's manual.
Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.
1.8 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran employment information at:
http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance:
http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act:
http://benefits.va.gov/vow/
Army Wounded Warrior Program:
http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material:
http://www.whitehouse.gov/sites/default/files/docs/ white_house_business_council_-_guide_to_hiring_veterans_0.pdf
SECTION 01 00 00 Page 3
1.9 MEASUREMENT AND PAYMENT
No separate payment will be made for the work covered under this section.
The costs thereof shall be included in the item to which the work pertains.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 AVAILABILITY AND USE OF UTILITY SERVICES
3.1.1 Contractor Responsibilities
a. The Contractor shall be responsible for the availability of utilities for use on the project. Raw water is available with no charge at the site. The contractor shall supply any other utilities needed at his cost. The Contractor shall carefully conserve any utilities furnished without charge.
b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia.
c. The Contractor is responsible for providing drinking water facilities for all personnel associated with this contract.
3.1.2 Interruptions of Utilities
a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.
b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) days prior to date of proposed interruption. The request shall give the following information:
(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)
(2) Size of line and location of shutoff.
(3) Buildings and services affected.
(4) Hours and date of shutoff.
(5) Estimated length of time services will be interrupted.
c. Services shall not be shutoff until receipt of approval of the proposed hours and date from the Contracting Officer.
d. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency.
e. Operation of valves on water mains will be by Government personnel.
Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations and have sufficient material and personnel available to complete the
SECTION 01 00 00 Page 4 work without undue delay or to restore service without delay in event of emergency.
-- End of Section --
SECTION 01 00 00 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 10 10
CONTRACTOR'S SITE OPERATIONS
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 REFERENCES
1.3 SUBMITTALS
1.4 WORK AREAS AND ACCESS
1.4.1 Powerhouse and Lock Location
1.4.2 Access Roads
1.4.3 Access By Government Personnel
1.4.4 Contractor's Staging Area and Employee Access
1.5 VEHICLES
1.5.1 Use of Private Vehicles
1.5.2 Identification of Vehicles
1.6 PROJECT SECURITY
1.7 SITE WORKING HOURS
1.7.1 Government Project Personnel Working Hours
1.7.2 Contractor's Working Hours
1.8 SAFE CLEARANCE PROCEDURES
1.9 DRAWINGS AND MANUALS
1.10 UTILITIES
1.10.1 General
1.10.2 Telephone
1.10.3 Area Lighting
1.11 CRANES AND HEAVY EQUIPMENT
1.11.1 Contractor Crane Safety
1.11.2 Contractor Crane Testing
1.11.3 Contractor's Cranes and Heavy Equipment
1.11.4 Movement of Equipment and Materials by the Contractor
1.11.5 Use of Government Cranes
1.12 DAMAGED EQUIPMENT OR ABNORMAL CONDITIONS
1.13 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.14 NOISE CONTROL
1.15 FIRE CONTROL
1.16 CARE OF DRAINS
1.17 DAILY CLEANUP AND DISPOSAL
1.18 SITE INVESTIGATIONS AND CONDITIONS AFFECTING THE WORK
1.19 PERMITS AND RESPONSIBILITIES
1.20 PARTS CONTROL AT THE JOBSITE
1.21 COORDINATION
1.22 CONTRACTOR'S PERSONNEL
1.22.1 Contractor's Personnel
1.23 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK
1.24 QUALITY CONTROL AT THE JOB SITE
SECTION 01 10 10 Page 1
SECTION 01 10 10
CONTRACTOR'S SITE OPERATIONS
PART 1 GENERAL
1.1 GENERAL INFORMATION
This Section covers the general requirements applicable to specific Contractor's operations or equipment for work performed on-site at Cheatham Lock.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic definition only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR PART 1910 (2018) Occupational Safety and Health Standards
29 CFR PART 1926 (2018) Safety and Health Regulations for Construction
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00.
SD-01 Preconstruction Submittals
1. Employee Identification and Control Procedure; G
Procedure for identification and control of employees entering or leaving site, a minimum of 10 calendar days prior to the start of site work (see paragraph 1.7 "PROJECT SECURITY").
2. Loading Plan; G
A minimum of 30 calendar days prior to on-site work (see paragraph 1.14 "CRANES AND HEAVY EQUIPMENT").
SECTION 01 10 10 Page 2
1.4 WORK AREAS AND ACCESS
1.4.1 Powerhouse and Lock Location
Cheatham Lock is located at 1799 Cheatham Dam Rd, Ashland City, TN 37015.
The replacement transformer is located at the powerhouse. The lock side can be accessed on the road of the Lock A Campground at 1797 Cheatham Dam Rd, Ashland City, TN 37015.
1.4.2 Access Roads
No new access roads are required. Any Contractor-caused damage to existing roadways that are used for access purposes shall be restored to its pre-damaged condition by the Contractor, less normal wear. Prior to the shipment of equipment and/or materials, the Contractor shall make an investigation of conditions of the facilities, such as clearances, restrictions, bridge load limits, and other limitations affecting transportation. Any such limitations to the transportation facilities shall not become the basis for claims or damages, or for the extension of time for completion of work. It shall be the responsibility of the Contractor to obtain the permits and licenses required for truck transportation of the transformer using existing roadways.
1.4.3 Access By Government Personnel
Clear access shall be maintained for Government personnel and equipment through all work areas.
1.4.4 Contractor's Staging Area and Employee Access
The Contractor's staging area shall be restricted to the area designated by the Government. The project areas off-limits to Contractor personnel will be as designated by the Contracting Officer. All Contractor site facilities shall be disposed of before final acceptance of all work.
1.5 VEHICLES
1.5.1 Use of Private Vehicles
Parking of private vehicles shall be restricted to the areas designated.
1.5.2 Identification of Vehicles
All Contractor's vehicles shall display permanent identification of such size and color to allow Government personnel to identify the vehicle.
1.6 PROJECT SECURITY
The access gates at the power plant and switchyards are locked during normal duty hours. The Contractor's on-site supervisor shall work with the power plant personnel for entry procedures. An Employee Identification and Control Procedure shall be submitted for approval for identification and control of employees entering or leaving the project.
After the stated Government project personnel working hours, the project gate accesses are locked. Contractor's personnel will not have access into the work area except during approved work hours, unless otherwise specifically approved for 24 hour oil processing operations. The security of the Contractor's property and items furnished under this contract, until accepted, are the responsibility of the Contractor whether stored
SECTION 01 10 10 Page 3 inside or outside the power plant security gate.
1.7 SITE WORKING HOURS
1.7.1 Government Project Personnel Working Hours
The scheduled working hours of the Project staff at Cheatham powerhouse and lock are Mondays through Thursdays from 06:00 a.m. until 4:30 p.m.
Fridays, Saturdays, Sundays and Federal Holidays are non-work days. All Project support required by the Contractor shall be scheduled during the Project staff working hours.
1.7.2 Contractor's Working Hours
The allowable Contractor's working hours shall be the same as that for the Government project personnel, unless otherwise specifically approved. The schedule of work hours, shifts and days of the week shall be coordinated with the COR. Notification of any proposed changes of the schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site shall be coordinated with the COR.
1.8 SAFE CLEARANCE PROCEDURES
A Safe Clearance System, as stated in EM 385-1-1 and the power plant Safe Clearance procedure, is used by project personnel to insure continuity of service and safety to personnel and equipment. Any work performed which requires taking project operating equipment out of service will be done only after a formal clearance is obtained by the Government with a seven calendar day notice. After the Government clearance tags have been placed on the equipment, the Contractor shall place his own clearance tag on the equipment. Safe Clearance procedures shall not be violated by Contractor personnel, and any violations will be grounds for requesting the removal of the offender(s). A copy of the Safe Clearance Procedure program will be supplied to the Contractor upon request.
1.9 DRAWINGS AND MANUALS
Existing drawings and manuals required for the work will be available for viewing at the power plant during normal project day shift working hours.
Drawings and manuals shall not be removed from the office; however, one copy of available technical data and drawings not included in the reference drawings will be made at no cost to the Contractor within 2 calendar days after the request for such copies has been made.
1.10 UTILITIES
1.10.1 General
All utilities provided by the Government shall be at no cost. Care shall be exercised in conserving all Government-furnished utilities. Extension cords shall be Contractor-furnished. Power plant electric power will be available for Contractor use. The Contractor shall not use Government compressed air systems. All temporary circuits and devices required for construction shall be provided, connected, and maintained and removed by the Contractor prior to final Government acceptance. Ground fault protection shall be provided for all circuits used and shall be Contractor-furnished.
SECTION 01 10 10 Page 4
1.10.2 Telephone
The project telephone system will not be available to the Contractor.
Cellular phones may be used. Cell phone reception may be poor at the work site area.
1.10.3 Area Lighting
The Contractor shall provide all lighting necessary to perform the work specified herein, and to provide a safe work environment.
1.11 CRANES AND HEAVY EQUIPMENT
1.11.1 Contractor Crane Safety
Contractor's cranes and equipment furnished for this work shall conform with all applicable OSHA requirements and referenced EM 385-1-1 in Clause 52.236-13, "ACCIDENT PREVENTION", including ALT1. The Contractor shall submit a lifting diagram addressing such issues as lift, trim, maximum load, maximum wind speed, lifting radius and all other applicable information required by EM 385-1-1 and OSHA as part of the loading plan.
1.11.2 Contractor Crane Testing
All Contractor cranes shall be tested in accordance with EM 385-1-1 prior to use on the project and the tests shall be witnessed by the COR.
Forty-eight hours notice of the test, excluding weekends and federal holidays, shall be given by the Contractor.
1.11.3 Contractor's Cranes and Heavy Equipment
A loading plan, which includes the planned method of transportation and operation of Contractor provided cranes and other heavy equipment to be used in the performance of this contract, shall be submitted for Government approval and coordinated with the COR. This shall include the type, size, loading, and placement of outriggers of all cranes or heavy equipment and the proposed transportation routes and work areas to be used on the project. Operation of heavy equipment adjacent to existing structures shall be avoided when possible.
1.11.4 Movement of Equipment and Materials by the Contractor
The Contractor shall provide all cranes, rigging, lifts, operators, and other necessary means to move equipment or material as required to pursue and complete the work whether owned by the Government or by the Contractor unless otherwise specifically mentioned. This includes but is not limited to the unloading and loading of equipment and material.
1.11.5 Use of Government Cranes
Government cranes will not be available for Contractor use.
1.12 DAMAGED EQUIPMENT OR ABNORMAL CONDITIONS
The Government shall be informed immediately upon finding any damaged equipment or other abnormal conditions. The failure or abnormality shall not be disturbed until witnessed by the COR. Prior to proceeding further with work on the unit, the Contractor and the Government shall agree in writing as to the responsibility for the damage or abnormality.
SECTION 01 10 10 Page 5
1.13 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.
1.14 NOISE CONTROL
Noise control and noise levels shall conform to requirements set forth in the appropriate regulations, including EM 385-1-1 , Section 05.C, 29 CFR PART 1910 .95, 29 CFR PART 1926 .52 and .101. The most conservative requirement shall govern.
1.15 FIRE CONTROL
All fire fighting equipment, supplies, and personnel shall be supplied in accordance with EM 385-1-1 . Delays due to Contractor caused fires will not be acceptable as the basis of a claim for additional compensation or additional time.
1.16 CARE OF DRAINS
Existing drains shall not be used for disposal of any solid material or any liquids other than clear water. Drains obstructed by the Contractor shall be cleaned by the Contractor. All costs incurred in the cleaning and clearing of plugged drains, shall be borne by the Contractor.
1.17 DAILY CLEANUP AND DISPOSAL
Work areas shall be kept reasonably neat on a daily basis. All debris resulting from the work, such as waste metalwork, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. The location of the Contractor's off-site disposal area and a plan for safe disposal of material shall be submitted for approval. The Government's trash cans, dumpboxes, and other containers shall not be used. Liquid waste shall not be disposed of in project drains. All costs of removing debris shall be incidental to the work, and no separate payment will be made therefore.
The area of work is subject to high winds. All equipment and materials shall be secured at the end of each day to prevent blowing into energized equipment.
1.18 SITE INVESTIGATIONS AND CONDITIONS AFFECTING THE WORK
The Contractor shall take steps reasonably necessary to ascertain the nature and location of the work, the general and local conditions shall be investigated which can affect the work or its cost, including but not limited to the following. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the Government. The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made
SECTION 01 10 10 Page 6 available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless the understanding or representation is expressly stated in this contract.
a. Conditions bearing upon transportation, disposal, handling, and storage of materials.
b. The availability of labor, water, electrical power, and roads.
c. Uncertainties of weather, river stages, or similar physical conditions at the site.
d. The conformation and conditions of the ground and equipment and facilities to be replaced and/or rehabilitated.
e. The character of equipment and facilities needed preliminary to and during work performance.
f. The amount of work space, accessibility, lighting, etc.
1.19 PERMITS AND RESPONSIBILITIES
The Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor's fault or negligence, and shall take proper safety and health precautions to protect the work, the workers, the public, and property of others. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for completed unit of work that may have been accepted under the contract.
1.20 PARTS CONTROL AT THE JOBSITE
A complete written record shall be maintained of the location and estimated date of return of all parts shipped from the project for repair. This record shall be available for review at all times.
1.21 COORDINATION
All work shall be coordinated with the Contracting Officer or his designated representatives. The work to be performed under this contract is subject to the safe clearances and operating procedures currently practiced at the project. Safe clearances shall be obtained before opening, entering, or working on any equipment in the power plant and transformer yard. All working areas shall be kept clean and orderly at all times. Tools and equipment shall be put away at the end of each workday.
The Contractor shall coordinate all work required for the removal of the existing electrical equipment and any associated appurtenances.
1.22 CONTRACTOR'S PERSONNEL
1.22.1 Contractor's Personnel
a. General . The Contractor shall prepare and revise whenever
SECTION 01 10 10 Page 7 organizational changes occur, a project organization chart reflecting at least those positions described herein and defining their work relationships, etc. The Contractor shall maintain a complete organizational chart of all positions that will be working on the project. All personnel employed by the Contractor shall be fully qualified in their respective fields to render the services necessary. The Contractor's organizational plan shall be maintained in the CQC Plan and submitted upon request by the COR.
b. Identification of Contractor's Employees . The Contractor shall be responsible for furnishing to each employee at the lock and for requiring each employee at the lock to display such identification as approved and specified below. All Contractor personnel, prior to engaging in work on project premises, shall either be issued an identification card by the Contractors or agree to provide their driver's license as I.D. upon request. If the Contractor so decides to furnish I.D. cards to all employees, the card must include the following information:
Name of Contractor Name of Employee Birth date Weight Hair color Eye color Recent photo
All prescribed identifications shall be returned immediately to the Contractor upon release of any employee. The Contractor shall include a list of all Contractor employees in the Employee Identification and Control Procedure, which includes their titles and who will be working on the project. This listing shall be revised and resubmitted when personnel changes occur. When required by the Government, the Contractor shall obtain and submit fingerprints of all persons employed to work at the power plant.
c. Sign-in/Sign-out Sheet . The Contractor shall maintain a daily sign-in/sign-out sheet for all Contractor and subcontractor personnel accessing Cheatham lock during performance of this contract.
1.23 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK
The Government will limit interference with the Contractor's work to the maximum reasonable extent and the Government and Contractor shall coordinate as necessary.
1.24 QUALITY CONTROL AT THE JOB SITE
In conjunction with Section 01 45 00, the Contractor's Quality Control system shall encompass actions involving selection of construction material sources and suppliers, on-site and off-site fabrication of Contractor-furnished items to be included in the work, on-site and off-site production of construction materials, work placement procedures, workmanship, inspection, and testing. The system shall provide supervision, inspection, and tests of all items of work, including that of its suppliers and subcontractors, that will assure the compliance of all work with applicable specifications and drawings in respect to the Contractor furnished equipment, materials, workmanship, construction, finish, functional performance, and identification. The Contractor's
SECTION 01 10 10 Page 8 system shall encompass all management and supervisory actions taken by its staff that affect quality of the finished work, including all inspection controls and tests required for compliance with the contract, except for those inspections and tests specifically reserved to be accomplished by the Government.
SECTION 01 10 10 Page 9
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 PAYMENT ITEMS
1.1.1 Performance and Payment Bonds
1.1.1.1 Payment
1.1.1.2 Unit of Measure
1.1.2 Demolition and Removal of Transformer
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.3 Installation of New Transformer
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.4 Installation of New Transformer Feeder Cable
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.5 Transformer Acceptance Testing
1.1.5.1 Payment
1.1.5.2 Unit of Measure
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 22 00 Page 1
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Performance and Payment Bonds
1.1.1.1 Payment
Payment will be made for costs associated with performance and payment bonds at each site. In accordance with Contract Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, the premiums for performance and payment bonds shall be included in the contract price. Payment for the premiums for performance and payment bonds will be made at the contract price per Job for "Performance & Payment Bonds." Payments made under this provision shall not exceed the amount included for "Performance & Payment Bonds," which payment shall take into consideration any discounts or rebates to the Contractor from the Surety. The Contractor is advised that the pay item "Performance & Payment Bonds" is only for the cost of bonds.
Other costs should be allocated to the appropriate bid items. The Contractor shall provide evidence of payment (paid invoice) from the bonding company or agency. If the actual cost of the bonds is less than the payment item amount, the contract will be modified to adjust the payment item accordingly.
1.1.1.2 Unit of Measure
Unit of measure: job.
1.1.2 Demolition and Removal of Transformer
1.1.2.1 Payment
Payment will be made for costs associated with the Demolition and Removal of the existing transformer as specified in Section 02 41 00 DEMOLITION.
Payment will be made at the contract price per Job for "Demolition and Removal of Transformer."
1.1.2.2 Unit of Measure
Unit of measure: job.
SECTION 01 22 00 Page 2
1.1.3 Installation of New Transformer
1.1.3.1 Payment
Payment will be made for costs associated with the Installation of the New Transformer as specified in Section 48 20 00 TRANSFORMER SHIPMENT, HAULING AND SITE ASSEMBLY. Payment will be made at the contract price per Job for "Installation of the New Transformer".
1.1.3.2 Unit of Measure
Unit of measure: job.
1.1.4 Installation of New Transformer Feeder Cable
1.1.4.1 Payment
Payment will be made for costs associated with the Installation of the New Transformer Feeder Cable as specified in Section 26 05 13 MEDIUM-VOLTAGE CABLE. Payment will be made at the contract price per Linear Foot for "Installation of the New Transformer Feeder Cable"
1.1.4.2 Unit of Measure
Unit of measure: Linear Feet.
1.1.5 Transformer Acceptance Testing
1.1.5.1 Payment
Payment will be made for costs associated with the Transformer Acceptance Testing as specified in Section 26 08 01 TRANSFORMER COMMISSIONING.
Payment will be made at the contract price per Job for the "Transformer Acceptance Testing".
1.1.5.2 Unit of Measure
Unit of measure: job.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 22 00 Page 3
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
1.1.2 Approving Authority
1.1.3 Work
1.2 SUBMITTALS
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
1.4 PREPARATION
1.4.1 Transmittal Form
1.4.2 Source Drawings for Shop Drawings
1.4.2.1 Terms and Conditions
1.4.3 Electronic File Format
1.5 INFORMATION ONLY SUBMITTALS
1.6 SUBMITTAL REGISTER
1.6.1 Use of Submittal Register
1.6.2 Contractor Use of Submittal Register
1.6.3 Approving Authority Use of Submittal Register
1.6.4 Copies Delivered to the Government
1.7 VARIATIONS
1.7.1 Considering Variations
1.7.2 Proposing Variations
1.7.3 Warranting that Variations are Compatible
1.7.4 Review Schedule Extension
1.8 SCHEDULING
1.9 GOVERNMENT APPROVING AUTHORITY
1.9.1 Review Notations
1.10 DISAPPROVED SUBMITTALS
1.11 APPROVED SUBMITTALS
1.12 APPROVED SAMPLES
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to;
Certificates of Insurance
Surety Bonds
List of Proposed Subcontractors
List of Proposed Products
Construction Progress Schedule Network Analysis Schedule (NAS)
Submittal Register
Schedule of Prices or Earned Value Report
Health and Safety Plan
Work Plan
Quality Control(QC) Plan
Environmental Protection Plan
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have
SECTION 01 33 00 Page 2 been within three years of date of contract award for the project.
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.1.2 Approving Authority
Office or designated person authorized to approve submittal.
1.1.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G
1.3 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.3.1 Government Approved (G)
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR
SECTION 01 33 00 Page 3
CONSTRUCTION, they are considered to be "shop drawings."
1.4 PREPARATION
1.4.1 Transmittal Form
1.4.2 Source Drawings for Shop Drawings
The entire set of Source Drawing files (DWG) will not be provided to the Contractor. Only those requested by the Contractor to prepare shop drawings may be provided. Request the specific Drawing Number only for the preparation of Shop Drawings. These drawings may only be provided after award.
1.4.2.1 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic Source Drawing files are not construction documents.
Differences may exist between the Source Drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic Source Drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source Drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic Source Drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).
1.4.3 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples Items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are
SECTION 01 33 00 Page 4 scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
E-mail electronic submittal documents fewer than 10MB to an e-mail address as directed by the Contracting Officer. Provide electronic documents over 10MB on an optical disc, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:
https://safe.amrdec.army.mil/safe/ .
Provide hard copies of submittals when requested by the Contracting Officer.
1.5 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.6 SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and
(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.
1.6.1 Use of Submittal Register
Submit submittal register. Submit with QC plan and project schedule.
SECTION 01 33 00 Page 5
Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.6.2 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.6.3 Approving Authority Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.6.4 Copies Delivered to the Government
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.7 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
SECTION 01 33 00 Page 6
1.7.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.7.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
1.7.3 Warranting that Variations are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.7.4 Review Schedule Extension
In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.
1.8 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have
SECTION 01 33 00 Page 7 been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
1.9 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, stamp and date submittals. One copy of the submittal will be retained by the Contracting Officer and one copy of the submittal will be returned to the Contractor.
1.9.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
1.10 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting Officer.