Huron_Dredge_Amendment02_package_W912P419B0002.pdf
PDF 396 KB Posted
- Attached to
- Huron Harbor Dredging Federal contract opportunity
- Solicitation number
- W912P419B0002
About this file
Huron Dredge Amendment02 package W912P419B0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| IGE_Adjusted_Abstract_Huron_Harbor_14Dec2018.xls | XLS spreadsheet | |
| Huron_Dredge_Amendment_01_W912P19B002_U0001.docx | DOCX document | |
| Final_W91P4180002_FY19_Huron_Harbor_Dredge_.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912P419B0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 04-Dec-2018 03:00 PM to 14-Dec-2018 03:00 PM.
SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS
Questions concerning this solicitation shall be submitted via electronic mail (e-mail) by 07 Dec 2018, 12:00 P.M. EST to Peter.R.Gembala@USACE.Army.mil and Frank.J.D’Andrea@USACE.Army.mil.
The following have been modified:
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:
Amendment 01: Bid due date and public opening is 11-December-2018, 3:00pm(ET) Amendment 02:
-Bid due date and public opening is 14-December-2018, 3:00pm(ET) -Bid form is updated to indicate 2 line items for the base bid.
-Section 01 35 13, table in paragraph 1.2 is updated , and subparagraph 1.2.2 Enviromental Window has been updated. (End of Provision)
(End of Summary of Changes) mailto:Peter.R.Gembala@USACE.Army.mil mailto:Andrea@USACE.Army.mil
AMENDMENT NO. 2
W91P418B0002
MAINTENANCE DREDGING
HURON HARBOR
HURON, OHIO
BID FORM CHANGE AND
CHANGES TO SECTION 01 35 13
04 DECEMBER 2018
Bid form is updated to indicate 2 line items for the base bid.
2. Section 01 35 13, table in paragraph 1.2 is updated, and subparagraph 1.2.1 Environmental Window has been updated.
SECTION 00 10 00
SOLICITATION, OFFER, AND AWARD (SF1142) AND BIDDING SCHEDULE
Bid will be based upon dredging and disposal of dredged material from Huron Harbor in the Government-furnished Open Lake Placement Site, as shown on the contract drawings, in accordance with these specifications.
Item Estimated Unit Estimated No. Description Quantity Unit Price Amount
1 Mobilization and Demobilization 1 JA $
2 Maintenance Dredging Sta. 25+00 to Lower Limit of Dredging w/placement in Government-furnished Open Lake Site 115,000 CY $ $
3 Maintenance Dredging Sta. 0+00 to Sta. 25+00 w/placement in Government-furnished Open Lake Site 60,000 CY $ $
Total Estimated Amount (Items 1 through 3) $
OPTION "A"
4 Maintenance Dredging Sta. 25+00 to Lower Limit of dredging w/placement in Government-furnished Open Lake Site 75,000 CY $ $
Total Estimated Amount (Items 1 through 4) $
Note 1: Bids must be complete as to all the items on the schedule. Failure to complete all items on the bid schedule will render the bid non-responsive.
Note 2: The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
Note 3: Regarding the option item, the government may elect to award or not to award the option. If the option item is awarded, the government reserves the right to limit the quantity of material up to the estimated quantity of the option item. If the option is awarded, it will be awarded within sixty (60) days of the contract award.
Milestone Maximum Calendar Days After Receipt of Notice to Proceed
Commence Work (Submittals, Administration, etc.) 10
Commence Actual Sediment Removal Operations 230
Complete Base Bid Work 270
b. The Notice to Proceed will be issued on or about 15 January 2019.
1.2.2 Environmental Window
Huron Harbor has dredging limitations based on environmental conditions. Between stations 0+00 and 25+00, dredging is only permitted between 01 July and 15 September. Complete dredging between stations 0+00 and 25+00 by 15 September 2019. Between station 25+00 and the lower limit of dredging, dredging is permitted only between 01 July and 15 April. Schedule the work accordingly.
TABLE FROM PARAGRAPH 1.2: